Federal nursing home survey record · CMS-certified nursing home· Not a state assisted-living licensing record

TROY HEALTH & REHABILITATION CENTER

TROY, AL · 220 certified beds · Last Life Safety survey October 20, 2022

CMS Certification Number 015213 · first certified January 1978

Ownership

Independently operated (no chain recorded by CMS) · For profit - Corporation

No change of ownership on CMS record since January 1, 2016, when the records begin.

21
Citations on file
Rolling three-year window
3
Life Safety surveys
In the same window
3
Tags cited more than once
Across separate surveys
8
Inspection & testing records
Of the citations on file

Position within AL

21 citations — more than 94% of the 224 certified nursing homes in AL. Compared within AL rather than nationally because which state a facility is in explains about 30% of the variation in citation counts between facilities, while bed count explains under 1%. State survey agencies differ far more than the buildings do. How this is calculated

Slippingmore citations at the latest survey than at its earlier surveys in the window.

The latest survey found 13 citations; the earlier surveys in the window averaged 4. With 3 surveys on file this is a direction of travel, not a conclusion.

When is the next survey likely?

Well past the typical window (November 2023 to March 2024), and past the point by which nine in ten US facilities have been surveyed. This facility’s last Life Safety survey was October 2022. Nursing homes nationally are typically surveyed 12–17 months after the last one (median 14), measured over 19,385 consecutive surveys in the last two years of CMS records. AL has too few recent surveys to measure on its own, so the national interval is used.

A range the record supports, not a prediction of a date. State agencies vary widely — from about 11 months in Pennsylvania to three years in Maryland. How the window is measured

Get an email about TROY HEALTH & REHABILITATION CENTER

One email when it happens. No account; stop it any time with one click.

Which alerts

2 inspection-and-testing tags have been cited here at more than one survey. Nationally, that pattern is common: about three quarters of cited facilities have at least one repeated tag, and half of the facilities ever cited for sprinkler inspection and testing are cited for it again. A repeat is usually a recordkeeping gap rather than a new hazard.

Emergency preparedness

3 of the 21 citations on file are Emergency Preparedness E-tags. E-tags are cited under 42 CFR §483.73 and concern the emergency plan, training, drills, communications and supplies. Nationally about half of certified facilities have at least one. The Emergency Preparedness Index

Physical environment (health survey)

2 physical-environment citations on the health survey. Cited by the health surveyors under Appendix PP, not the Life Safety Code surveyor: equipment in safe operating condition, the call system, bed rails, pest control, hazards, the environment. Counted separately from the 21 Life Safety citations above. The Physical Environment Index

  • F-0880 Provide and implement an infection prevention and control program.

How that compares

Citations on file over three years

Compared with the median facility in AL, and nationally. Surveyors differ markedly between states, so the AL figure is the meaningful one.

This facility21AL median9National median11
Citations on file over three years, compared
MeasureCitations
This facility21
Median facility in AL9
Median facility nationally11

Survey history

Citations at each Life Safety survey
42018-1042019-10132022-10
Citations at each Life Safety survey
Survey dateCitations
October 25, 20184
October 24, 20194
October 20, 202213

Most-cited tags

Most-cited tags at this facility
K-03633K-03532K-03512K-03211E-00251K-05111K-03451K-03461
Most-cited tags at this facility
TagWhat the surveyor checksTimes citedLast cited
K-0363Install corridor and hallway doors that block smoke.32022-10-20
K-0353Inspect, test, and maintain automatic sprinkler systems.22022-10-20
K-0351Install an approved automatic sprinkler system.22022-10-20
K-0321Ensure that special areas are constructed so that walls can resist fire for one hour or have an approved fire extinguishing system.12022-10-20
E-0025Create arrangements with other facilities to receive patients.12022-10-20
K-0511Have properly installed electrical wiring and gas equipment.12019-10-24
K-0345Have approved installation, maintenance and testing program for fire alarm systems.12022-10-20
K-0346Follow proper procedures when the fire alarm was out of service for more than 4 hours.12022-10-20

What the citations cover

Citations by CMS category
  • Smoke Deficiencies 11
  • Egress Deficiencies 3
  • Emergency Preparedness Deficiencies 3
  • Gas, Vacuum, and Electrical Systems Deficiencies 2
  • Other 2
Citations by CMS category
CategoryCitations
Smoke Deficiencies11
Egress Deficiencies3
Emergency Preparedness Deficiencies3
Gas, Vacuum, and Electrical Systems Deficiencies2
Services Deficiencies1
Miscellaneous Deficiencies1

Every citation on file

As published by CMS, newest survey first. Descriptions are CMS’s own wording.

October 20, 2022 — 13 citations

Citations issued on October 20, 2022
TagWhat the surveyor checksStatus
E-0015Address subsistence needs for staff and patients.Deficient, Provider has date of correction (December 1, 2022)
E-0025Create arrangements with other facilities to receive patients.Deficient, Provider has date of correction (December 1, 2022)
E-0037Establish staff and initial training requirements.Deficient, Provider has date of correction (December 1, 2022)
K-0211Keep aisles, corridors, and exits free of obstruction in case of emergency.Deficient, Provider has date of correction (December 1, 2022)
K-0232Have corridors or aisles that are unobstructed and are at least 8 feet in width.Deficient, Provider has date of correction (December 1, 2022)
K-0321Ensure that special areas are constructed so that walls can resist fire for one hour or have an approved fire extinguishing system.Deficient, Provider has date of correction (December 1, 2022)
K-0345Have approved installation, maintenance and testing program for fire alarm systems.Deficient, Provider has date of correction (December 1, 2022)
K-0346Follow proper procedures when the fire alarm was out of service for more than 4 hours.Deficient, Provider has date of correction (December 1, 2022)
K-0351Install an approved automatic sprinkler system.Deficient, Provider has date of correction (December 1, 2022)
K-0353Inspect, test, and maintain automatic sprinkler systems.Deficient, Provider has date of correction (December 1, 2022)
K-0363Install corridor and hallway doors that block smoke.Deficient, Provider has date of correction (December 1, 2022)
K-0741Have posted "No-smoking" signs in areas where smoking is not permitted or ashtrays provided where smoking was allowed.Deficient, Provider has date of correction (December 1, 2022)
K-0921Ensure that testing and maintenance of electrical equipment is performed.Deficient, Provider has date of correction (December 1, 2022)

October 24, 2019 — 4 citations

Citations issued on October 24, 2019
TagWhat the surveyor checksStatus
K-0363Install corridor and hallway doors that block smoke.Deficient, Provider has date of correction (December 3, 2019)
K-0372Ensure smoke barriers are constructed to a 1 hour fire resistance rating.Deficient, Provider has date of correction (December 3, 2019)
K-0511Have properly installed electrical wiring and gas equipment.Deficient, Provider has date of correction (December 3, 2019)
K-0920Ensure proper usage of power strips and extension cords.Deficient, Provider has date of correction (December 3, 2019)

October 25, 2018 — 4 citations

Citations issued on October 25, 2018
TagWhat the surveyor checksStatus
K-0293Have properly located and lighted "Exit" signs.Deficient, Provider has date of correction (December 6, 2018)
K-0351Install an approved automatic sprinkler system.Deficient, Provider has date of correction (December 6, 2018)
K-0353Inspect, test, and maintain automatic sprinkler systems.Deficient, Provider has date of correction (December 6, 2018)
K-0363Install corridor and hallway doors that block smoke.Deficient, Provider has date of correction (December 6, 2018)

Reflects the CMS posting of August 1, 2026. Surveys conducted in the last few months may not appear yet.