Federal nursing home survey record · CMS-certified nursing home· Not a state assisted-living licensing record
CRESTVIEW HEALTH & REHAB CTR
ATLANTA, GA · 388 certified beds · Last Life Safety survey June 5, 2025
CMS Certification Number 115525 · first certified July 1992
Ownership
Independently operated (no chain recorded by CMS) · Non profit - Other
No change of ownership on CMS record since January 1, 2016, when the records begin.
Position within GA
10 citations — more than 58% of the 356 certified nursing homes in GA. Compared within GA rather than nationally because which state a facility is in explains about 30% of the variation in citation counts between facilities, while bed count explains under 1%. State survey agencies differ far more than the buildings do. How this is calculated
The latest survey found 0 citations; the earlier surveys in the window averaged 5. With 3 surveys on file this is a direction of travel, not a conclusion.
When is the next survey likely?
The window is open now: August 2026 to February 2027. This facility’s last Life Safety survey was June 2025. Facilities in GA are typically surveyed 14–20 months after the last one (median 16), measured over 532 consecutive surveys in the last two years of CMS records.
A range the record supports, not a prediction of a date. State agencies vary widely — from about 11 months in Pennsylvania to three years in Maryland. How the window is measured
Get an email about CRESTVIEW HEALTH & REHAB CTR
One email when it happens. No account; stop it any time with one click.
1 inspection-and-testing tag has been cited here at more than one survey. Nationally, that pattern is common: about three quarters of cited facilities have at least one repeated tag, and half of the facilities ever cited for sprinkler inspection and testing are cited for it again. A repeat is usually a recordkeeping gap rather than a new hazard.
Emergency preparedness
1 of the 10 citations on file is Emergency Preparedness E-tags. E-tags are cited under 42 CFR §483.73 and concern the emergency plan, training, drills, communications and supplies. Nationally about half of certified facilities have at least one. The Emergency Preparedness Index
Physical environment (health survey)
4 physical-environment citations on the health survey. Cited by the health surveyors under Appendix PP, not the Life Safety Code surveyor: equipment in safe operating condition, the call system, bed rails, pest control, hazards, the environment. Counted separately from the 10 Life Safety citations above. The Physical Environment Index
How that compares
Compared with the median facility in GA, and nationally. Surveyors differ markedly between states, so the GA figure is the meaningful one.
| Measure | Citations |
|---|---|
| This facility | 10 |
| Median facility in GA | 8 |
| Median facility nationally | 11 |
Survey history
| Survey date | Citations |
|---|---|
| February 2, 2023 | 5 |
| March 7, 2024 | 5 |
| June 5, 2025 | 0 |
Most-cited tags
| Tag | What the surveyor checks | Times cited | Last cited |
|---|---|---|---|
| K-0372 | Ensure smoke barriers are constructed to a 1 hour fire resistance rating. | 2 | 2024-03-07 |
| K-0331 | Construct fire resistant interior walls. | 1 | 2024-03-07 |
| K-0511 | Have properly installed electrical wiring and gas equipment. | 1 | 2024-03-07 |
| E-0004 | Develop and maintain an Emergency Preparedness Program (EP). | 1 | 2023-02-02 |
| K-0363 | Install corridor and hallway doors that block smoke. | 1 | 2024-03-07 |
| K-0918 | Have generator or other power source capable of supplying service within 10 seconds. | 1 | 2023-02-02 |
| K-0324 | Provide properly protected cooking facilities. | 1 | 2023-02-02 |
| K-0345 | Have approved installation, maintenance and testing program for fire alarm systems. | 1 | 2023-02-02 |
What the citations cover
- Smoke Deficiencies 6
- Emergency Preparedness Deficiencies 1
- Miscellaneous Deficiencies 1
- Services Deficiencies 1
- Other 1
| Category | Citations |
|---|---|
| Smoke Deficiencies | 6 |
| Emergency Preparedness Deficiencies | 1 |
| Miscellaneous Deficiencies | 1 |
| Services Deficiencies | 1 |
| Gas, Vacuum, and Electrical Systems Deficiencies | 1 |
Every citation on file
As published by CMS, newest survey first. Descriptions are CMS’s own wording.
March 7, 2024 — 5 citations
| Tag | What the surveyor checks | Status |
|---|---|---|
| K-0331 | Construct fire resistant interior walls. | Deficient, Provider has date of correction (April 21, 2024) |
| K-0363 | Install corridor and hallway doors that block smoke. | Deficient, Provider has date of correction (April 21, 2024) |
| K-0372 | Ensure smoke barriers are constructed to a 1 hour fire resistance rating. | Deficient, Provider has date of correction (April 21, 2024) |
| K-0511 | Have properly installed electrical wiring and gas equipment. | Deficient, Provider has date of correction (April 21, 2024) |
| K-0791 | Ensure that any exit in an area undergoing construction, repair, or improvements shall be inspected daily to ensure its ability to be used instantly in case of emergency. | Deficient, Provider has date of correction (April 21, 2024) |
February 2, 2023 — 5 citations
| Tag | What the surveyor checks | Status |
|---|---|---|
| E-0004 | Develop and maintain an Emergency Preparedness Program (EP). | Deficient, Provider has date of correction (March 19, 2023) |
| K-0324 | Provide properly protected cooking facilities. | Deficient, Provider has date of correction (March 19, 2023) |
| K-0345 | Have approved installation, maintenance and testing program for fire alarm systems. | Deficient, Provider has date of correction (March 19, 2023) |
| K-0372 | Ensure smoke barriers are constructed to a 1 hour fire resistance rating. | Deficient, Provider has date of correction (March 19, 2023) |
| K-0918 | Have generator or other power source capable of supplying service within 10 seconds. | Deficient, Provider has date of correction (March 19, 2023) |
Reflects the CMS posting of August 1, 2026. Surveys conducted in the last few months may not appear yet.