HEART OF GEORGIA NURSING HOME
EASTMAN, GA · 100 certified beds · Last Life Safety survey January 11, 2026
CMS Certification Number 115471 · first certified January 1990
Ownership
Independently operated (no chain recorded by CMS) · For profit - Corporation
No change of ownership on CMS record since January 1, 2016, when the records begin.
Position within GA
10 citations — more than 58% of the 356 certified nursing homes in GA. Compared within GA rather than nationally because which state a facility is in explains about 30% of the variation in citation counts between facilities, while bed count explains under 1%. State survey agencies differ far more than the buildings do. How this is calculated
The latest survey found 1 citation; the earlier surveys in the window averaged 4.5. With 3 surveys on file this is a direction of travel, not a conclusion.
When is the next survey likely?
The window opens March 2027 — about 6 months from now. This facility’s last Life Safety survey was January 2026. Facilities in GA are typically surveyed 14–20 months after the last one (median 16), measured over 532 consecutive surveys in the last two years of CMS records.
A range the record supports, not a prediction of a date. State agencies vary widely — from about 11 months in Pennsylvania to three years in Maryland. How the window is measured
Get an email about HEART OF GEORGIA NURSING HOME
One email when it happens. No account; stop it any time with one click.
1 inspection-and-testing tag has been cited here at more than one survey. Nationally, that pattern is common: about three quarters of cited facilities have at least one repeated tag, and half of the facilities ever cited for sprinkler inspection and testing are cited for it again. A repeat is usually a recordkeeping gap rather than a new hazard.
Physical environment (health survey)
1 physical-environment citation on the health survey. Cited by the health surveyors under Appendix PP, not the Life Safety Code surveyor: equipment in safe operating condition, the call system, bed rails, pest control, hazards, the environment. Counted separately from the 10 Life Safety citations above. The Physical Environment Index
- F-0880 Provide and implement an infection prevention and control program.
How that compares
Compared with the median facility in GA, and nationally. Surveyors differ markedly between states, so the GA figure is the meaningful one.
| Measure | Citations |
|---|---|
| This facility | 10 |
| Median facility in GA | 8 |
| Median facility nationally | 11 |
Survey history
| Survey date | Citations |
|---|---|
| October 30, 2022 | 4 |
| September 13, 2024 | 5 |
| January 11, 2026 | 1 |
Most-cited tags
| Tag | What the surveyor checks | Times cited | Last cited |
|---|---|---|---|
| K-0353 | Inspect, test, and maintain automatic sprinkler systems. | 3 | 2026-01-11 |
| K-0341 | Install a fire alarm system that can be heard throughout the facility. | 2 | 2024-09-13 |
| K-0211 | Keep aisles, corridors, and exits free of obstruction in case of emergency. | 1 | 2024-09-13 |
| K-0781 | Have restrictions on the use of portable space heaters. | 1 | 2024-09-13 |
| K-0753 | Have restrictions on the use of highly flammable decorations. | 1 | 2022-10-30 |
| K-0511 | Have properly installed electrical wiring and gas equipment. | 1 | 2024-09-13 |
| K-0372 | Ensure smoke barriers are constructed to a 1 hour fire resistance rating. | 1 | 2022-10-30 |
What the citations cover
- Smoke Deficiencies 6
- Miscellaneous Deficiencies 2
- Egress Deficiencies 1
- Services Deficiencies 1
| Category | Citations |
|---|---|
| Smoke Deficiencies | 6 |
| Miscellaneous Deficiencies | 2 |
| Egress Deficiencies | 1 |
| Services Deficiencies | 1 |
Every citation on file
As published by CMS, newest survey first. Descriptions are CMS’s own wording.
January 11, 2026 — 1 citation
| Tag | What the surveyor checks | Status |
|---|---|---|
| K-0353 | Inspect, test, and maintain automatic sprinkler systems. | Deficient, Provider has date of correction (February 25, 2026) |
September 13, 2024 — 5 citations
| Tag | What the surveyor checks | Status |
|---|---|---|
| K-0211 | Keep aisles, corridors, and exits free of obstruction in case of emergency. | Deficient, Provider has date of correction (October 28, 2024) |
| K-0341 | Install a fire alarm system that can be heard throughout the facility. | Deficient, Provider has date of correction (October 28, 2024) |
| K-0353 | Inspect, test, and maintain automatic sprinkler systems. | Deficient, Provider has date of correction (October 28, 2024) |
| K-0511 | Have properly installed electrical wiring and gas equipment. | Deficient, Provider has date of correction (October 28, 2024) |
| K-0781 | Have restrictions on the use of portable space heaters. | Deficient, Provider has date of correction (October 28, 2024) |
October 30, 2022 — 4 citations
| Tag | What the surveyor checks | Status |
|---|---|---|
| K-0341 | Install a fire alarm system that can be heard throughout the facility. | Deficient, Provider has date of correction (December 12, 2022) |
| K-0353 | Inspect, test, and maintain automatic sprinkler systems. | Deficient, Provider has date of correction (December 12, 2022) |
| K-0372 | Ensure smoke barriers are constructed to a 1 hour fire resistance rating. | Deficient, Provider has date of correction (December 12, 2022) |
| K-0753 | Have restrictions on the use of highly flammable decorations. | Deficient, Provider has date of correction (December 12, 2022) |