Federal nursing home survey record · CMS-certified nursing home· Not a state assisted-living licensing record
Barren County Nursing and Rehabilitation
Glasgow, KY · 94 certified beds · Last Life Safety survey August 8, 2025
CMS Certification Number 185229 · first certified January 1991
Ownership
Operated by SIMCHA HYMAN & NAFTALI ZANZIPER · For profit - Limited Liability company
- Ownership changed December 1, 2018 (change of ownership)from DIVERSICARE OF GLASGOW LLC
Position within KY
4 citations — more than 19% of the 267 certified nursing homes in KY. Compared within KY rather than nationally because which state a facility is in explains about 30% of the variation in citation counts between facilities, while bed count explains under 1%. State survey agencies differ far more than the buildings do. How this is calculated
The latest survey found 1 citation; the earlier surveys in the window averaged 1.5. With 3 surveys on file this is a direction of travel, not a conclusion.
When is the next survey likely?
The window is open now: September 2026 to July 2030. This facility’s last Life Safety survey was August 2025. Facilities in KY are typically surveyed 14–59 months after the last one (median 28), measured over 391 consecutive surveys in the last two years of CMS records.
A range the record supports, not a prediction of a date. State agencies vary widely — from about 11 months in Pennsylvania to three years in Maryland. How the window is measured
Get an email about Barren County Nursing and Rehabilitation
One email when it happens. No account; stop it any time with one click.
How that compares
Compared with the median facility in KY, and nationally. Surveyors differ markedly between states, so the KY figure is the meaningful one.
| Measure | Citations |
|---|---|
| This facility | 4 |
| Median facility in KY | 7 |
| Median facility nationally | 11 |
Survey history
| Survey date | Citations |
|---|---|
| December 4, 2019 | 0 |
| March 9, 2023 | 3 |
| August 8, 2025 | 1 |
Most-cited tags
| Tag | What the surveyor checks | Times cited | Last cited |
|---|---|---|---|
| K-0920 | Ensure proper usage of power strips and extension cords. | 1 | 2023-03-09 |
| K-0355 | Properly select, install, inspect, or maintain portable fire extinguishes. | 1 | 2023-03-09 |
| K-0321 | Ensure that special areas are constructed so that walls can resist fire for one hour or have an approved fire extinguishing system. | 1 | 2023-03-09 |
| K-0374 | Install smoke barrier doors that can resist smoke for at least 20 minutes. | 1 | 2025-08-08 |
What the citations cover
- Smoke Deficiencies 3
- Gas, Vacuum, and Electrical Systems Deficiencies 1
| Category | Citations |
|---|---|
| Smoke Deficiencies | 3 |
| Gas, Vacuum, and Electrical Systems Deficiencies | 1 |
Every citation on file
As published by CMS, newest survey first. Descriptions are CMS’s own wording.
August 8, 2025 — 1 citation
| Tag | What the surveyor checks | Status |
|---|---|---|
| K-0374 | Install smoke barrier doors that can resist smoke for at least 20 minutes. | Deficient, Provider has date of correction (August 27, 2025) |
March 9, 2023 — 3 citations
| Tag | What the surveyor checks | Status |
|---|---|---|
| K-0321 | Ensure that special areas are constructed so that walls can resist fire for one hour or have an approved fire extinguishing system. | Deficient, Provider has date of correction (April 21, 2023) |
| K-0355 | Properly select, install, inspect, or maintain portable fire extinguishes. | Deficient, Provider has date of correction (April 21, 2023) |
| K-0920 | Ensure proper usage of power strips and extension cords. | Deficient, Provider has date of correction (April 21, 2023) |
Reflects the CMS posting of August 1, 2026. Surveys conducted in the last few months may not appear yet.