Federal nursing home survey record · CMS-certified nursing home· Not a state assisted-living licensing record

ALLIANCE HEALTH AT ROSEWOOD

PEABODY, MA · 135 certified beds · Last Life Safety survey January 23, 2026

CMS Certification Number 225651 · first certified October 1994

Ownership

Operated by ALLIANCE HEALTH & HUMAN SERVICES · Non profit - Corporation

No change of ownership on CMS record since January 1, 2016, when the records begin.

7
Citations on file
Rolling three-year window
3
Life Safety surveys
In the same window
0
Tags cited more than once
Across separate surveys
4
Inspection & testing records
Of the citations on file

Position within MA

7 citations — more than 31% of the 341 certified nursing homes in MA. Compared within MA rather than nationally because which state a facility is in explains about 30% of the variation in citation counts between facilities, while bed count explains under 1%. State survey agencies differ far more than the buildings do. How this is calculated

Improvingfewer citations at the latest survey than at its earlier surveys in the window.

The latest survey found 3 citations; the earlier surveys in the window averaged 2. With 3 surveys on file this is a direction of travel, not a conclusion.

When is the next survey likely?

The window opens January 2027 — about 4 months from now. This facility’s last Life Safety survey was January 2026. Facilities in MA are typically surveyed 12–15 months after the last one (median 13), measured over 556 consecutive surveys in the last two years of CMS records.

A range the record supports, not a prediction of a date. State agencies vary widely — from about 11 months in Pennsylvania to three years in Maryland. How the window is measured

Get an email about ALLIANCE HEALTH AT ROSEWOOD

One email when it happens. No account; stop it any time with one click.

Which alerts

Physical environment (health survey)

2 physical-environment citations on the health survey. Cited by the health surveyors under Appendix PP, not the Life Safety Code surveyor: equipment in safe operating condition, the call system, bed rails, pest control, hazards, the environment. Counted separately from the 7 Life Safety citations above. The Physical Environment Index

  • F-0880 Provide and implement an infection prevention and control program.

How that compares

Citations on file over three years

Compared with the median facility in MA, and nationally. Surveyors differ markedly between states, so the MA figure is the meaningful one.

This facility7MA median11National median11
Citations on file over three years, compared
MeasureCitations
This facility7
Median facility in MA11
Median facility nationally11

Survey history

Citations at each Life Safety survey
02024-0142025-0132026-01
Citations at each Life Safety survey
Survey dateCitations
January 4, 20240
January 23, 20254
January 23, 20263

Most-cited tags

Most-cited tags at this facility
K-07121K-03631K-09271K-02911K-09111K-03451K-03211
Most-cited tags at this facility
TagWhat the surveyor checksTimes citedLast cited
K-0712Have simulated fire drills held at unexpected times.12025-01-23
K-0363Install corridor and hallway doors that block smoke.12025-01-23
K-0927Have proper fire barriers, ventilation and signs for the transfilling of oxygen.12026-01-23
K-0291Install emergency lighting that can last at least 1 1/2 hours.12026-01-23
K-0911Meet requirements for the installation and maintenance of electrical systems.12025-01-23
K-0345Have approved installation, maintenance and testing program for fire alarm systems.12025-01-23
K-0321Ensure that special areas are constructed so that walls can resist fire for one hour or have an approved fire extinguishing system.12026-01-23

What the citations cover

Citations by CMS category
  • Smoke Deficiencies 3
  • Gas, Vacuum, and Electrical Systems Deficiencies 2
  • Miscellaneous Deficiencies 1
  • Egress Deficiencies 1
Citations by CMS category
CategoryCitations
Smoke Deficiencies3
Gas, Vacuum, and Electrical Systems Deficiencies2
Miscellaneous Deficiencies1
Egress Deficiencies1

Every citation on file

As published by CMS, newest survey first. Descriptions are CMS’s own wording.

January 23, 2026 — 3 citations

Citations issued on January 23, 2026
TagWhat the surveyor checksStatus
K-0291Install emergency lighting that can last at least 1 1/2 hours.Deficient, Provider has date of correction (March 24, 2026)
K-0321Ensure that special areas are constructed so that walls can resist fire for one hour or have an approved fire extinguishing system.Deficient, Provider has date of correction (March 24, 2026)
K-0927Have proper fire barriers, ventilation and signs for the transfilling of oxygen.Deficient, Provider has date of correction (March 24, 2026)

January 23, 2025 — 4 citations

Citations issued on January 23, 2025
TagWhat the surveyor checksStatus
K-0345Have approved installation, maintenance and testing program for fire alarm systems.Deficient, Provider has date of correction (March 10, 2025)
K-0363Install corridor and hallway doors that block smoke.Deficient, Provider has date of correction (March 10, 2025)
K-0712Have simulated fire drills held at unexpected times.Deficient, Provider has date of correction (March 10, 2025)
K-0911Meet requirements for the installation and maintenance of electrical systems.Deficient, Provider has date of correction (March 10, 2025)

Reflects the CMS posting of August 1, 2026. Surveys conducted in the last few months may not appear yet.