Federal nursing home survey record · CMS-certified nursing home· Not a state assisted-living licensing record

LIFE CARE CENTER OF PLYMOUTH

PLYMOUTH, MA · 150 certified beds · Last Life Safety survey June 16, 2026

CMS Certification Number 225666 · first certified February 1995

Ownership

Operated by LIFE CARE CENTERS OF AMERICA · For profit - Corporation

No change of ownership on CMS record since January 1, 2016, when the records begin.

9
Citations on file
CMS's current file
3
Life Safety surveys
CMS's current file
0
Tags cited more than once
Across separate surveys
5
Inspection & testing records
Of the citations on file

Position within MA

9 citations — more than 38% of the 341 certified nursing homes in MA. Compared within MA rather than nationally because which state a facility is in explains about 30% of the variation in citation counts between facilities, while bed count explains under 1%. State survey agencies differ far more than the buildings do. How this is calculated

Improvingfewer citations at the latest survey than at its earlier surveys in CMS's current file.

The latest survey found 2 citations; the earlier surveys on file averaged 3.5. With 3 surveys on file this is a direction of travel, not a conclusion.

When is the next survey likely?

The window opens June 2027 — about 7 months from now. This facility’s last Life Safety survey was June 2026. Facilities in MA are typically surveyed 12–14 months after the last one (median 13), measured over 553 consecutive surveys in the last two years of CMS records.

A range the record supports, not a prediction of a date. State agencies vary widely — from about 11 months in Pennsylvania to about three years in Virginia. How the window is measured

Get an email about LIFE CARE CENTER OF PLYMOUTH

One email when it happens. No account; stop it any time with one click.

Which alerts

How that compares

Citations in CMS's current file

Compared with the median facility in MA, and nationally. Surveyors differ markedly between states, so the MA figure is the meaningful one.

This facility9MA median11National median11
Citations in CMS's current file, compared
MeasureCitations
This facility9
Median facility in MA11
Median facility nationally11

Survey history

Citations at each Life Safety survey
12024-0162025-0322026-06
Citations at each Life Safety survey
Survey dateCitations
January 26, 20241
March 17, 20256
June 16, 20262

Most-cited tags

Most-cited tags at this facility
K-03451K-09181K-07611K-07111K-03531K-03211K-02911K-01611
Most-cited tags at this facility
TagWhat the surveyor checksTimes citedLast cited
K-0345Have approved installation, maintenance and testing program for fire alarm systems.12026-06-16
K-0918Have generator or other power source capable of supplying service within 10 seconds.12026-06-16
K-0761To conduct inspection, testing and maintenance of fire doors by qualified individuals.12025-03-17
K-0711Provide a written emergency evacuation plan.12025-03-17
K-0353Inspect, test, and maintain automatic sprinkler systems.12025-03-17
K-0321Ensure that special areas are constructed so that walls can resist fire for one hour or have an approved fire extinguishing system.12024-01-26
K-0291Install emergency lighting that can last at least 1 1/2 hours.12025-03-17
K-0161Use approved construction type or materials.12025-03-17

What the citations cover

Citations by CMS category
  • Smoke Deficiencies 3
  • Miscellaneous Deficiencies 2
  • Gas, Vacuum, and Electrical Systems Deficiencies 1
  • Construction Deficiencies 1
  • Other 2
Citations by CMS category
CategoryCitations
Smoke Deficiencies3
Miscellaneous Deficiencies2
Gas, Vacuum, and Electrical Systems Deficiencies1
Construction Deficiencies1
Egress Deficiencies1
Services Deficiencies1

Every citation on file

As published by CMS, newest survey first. Descriptions are CMS’s own wording.

June 16, 2026 — 2 citations

Citations issued on June 16, 2026
TagWhat the surveyor checksStatus
K-0345Have approved installation, maintenance and testing program for fire alarm systems.Deficient, Provider has date of correction (August 10, 2026)
K-0918Have generator or other power source capable of supplying service within 10 seconds.Deficient, Provider has date of correction (July 30, 2026)

March 17, 2025 — 6 citations

Citations issued on March 17, 2025
TagWhat the surveyor checksStatus
K-0161Use approved construction type or materials.Deficient, Provider has date of correction (April 10, 2025)
K-0291Install emergency lighting that can last at least 1 1/2 hours.Deficient, Provider has date of correction (April 17, 2025)
K-0353Inspect, test, and maintain automatic sprinkler systems.Deficient, Provider has date of correction (April 15, 2025)
K-0541Install properly constructed and protected linen or trash chutes.Deficient, Provider has date of correction (April 23, 2025)
K-0711Provide a written emergency evacuation plan.Deficient, Provider has date of correction (April 4, 2025)
K-0761To conduct inspection, testing and maintenance of fire doors by qualified individuals.Deficient, Provider has date of correction (April 11, 2025)

January 26, 2024 — 1 citation

Citations issued on January 26, 2024
TagWhat the surveyor checksStatus
K-0321Ensure that special areas are constructed so that walls can resist fire for one hour or have an approved fire extinguishing system.Deficient, Provider has date of correction (February 9, 2024)

Reflects the CMS posting of October 1, 2026. Surveys conducted in the last few months may not appear yet.