Federal nursing home survey record · CMS-certified nursing home· Not a state assisted-living licensing record
Maple Manor Rehab Center
Wayne, MI · 59 certified beds · Last Life Safety survey May 29, 2026
CMS Certification Number 235613 · first certified May 2004
Ownership
Independently operated (no chain recorded by CMS) · For profit - Individual
No change of ownership on CMS record since January 1, 2016, when the records begin.
Position within MI
14 citations — more than 51% of the 422 certified nursing homes in MI. Compared within MI rather than nationally because which state a facility is in explains about 30% of the variation in citation counts between facilities, while bed count explains under 1%. State survey agencies differ far more than the buildings do. How this is calculated
The latest survey found 3 citations; the earlier surveys on file averaged 5.5. With 3 surveys on file this is a direction of travel, not a conclusion.
When is the next survey likely?
The window opens May 2027 — about 6 months from now. This facility’s last Life Safety survey was May 2026. Facilities in MI are typically surveyed 12–14 months after the last one (median 13), measured over 731 consecutive surveys in the last two years of CMS records.
A range the record supports, not a prediction of a date. State agencies vary widely — from about 11 months in Pennsylvania to about three years in Virginia. How the window is measured
Get an email about Maple Manor Rehab Center
One email when it happens. No account; stop it any time with one click.
2 inspection-and-testing tags have been cited here at more than one survey. Nationally, that pattern is common: about three quarters of cited facilities have at least one repeated tag, and half of the facilities cited for sprinkler inspection and testing in CMS’s current file are cited for it again. A repeat is usually a recordkeeping gap rather than a new hazard.
Physical environment (health survey)
2 physical-environment citations on the health survey. Cited by the health surveyors under Appendix PP, not the Life Safety Code surveyor: equipment in safe operating condition, the call system, bed rails, pest control, hazards, the environment. Counted separately from the 14 Life Safety citations above. The Physical Environment Index
- F-0880 Provide and implement an infection prevention and control program.
How that compares
Compared with the median facility in MI, and nationally. Surveyors differ markedly between states, so the MI figure is the meaningful one.
| Measure | Citations |
|---|---|
| This facility | 14 |
| Median facility in MI | 13 |
| Median facility nationally | 11 |
Survey history
| Survey date | Citations |
|---|---|
| September 27, 2024 | 7 |
| July 17, 2025 | 4 |
| May 29, 2026 | 3 |
Most-cited tags
| Tag | What the surveyor checks | Times cited | Last cited |
|---|---|---|---|
| K-0324 | Provide properly protected cooking facilities. | 3 | 2026-05-29 |
| K-0353 | Inspect, test, and maintain automatic sprinkler systems. | 2 | 2025-07-17 |
| K-0345 | Have approved installation, maintenance and testing program for fire alarm systems. | 1 | 2026-05-29 |
| K-0918 | Have generator or other power source capable of supplying service within 10 seconds. | 1 | 2024-09-27 |
| K-0781 | Have restrictions on the use of portable space heaters. | 1 | 2024-09-27 |
| K-0211 | Keep aisles, corridors, and exits free of obstruction in case of emergency. | 1 | 2024-09-27 |
| K-0321 | Ensure that special areas are constructed so that walls can resist fire for one hour or have an approved fire extinguishing system. | 1 | 2024-09-27 |
| K-0511 | Have properly installed electrical wiring and gas equipment. | 1 | 2026-05-29 |
What the citations cover
- Smoke Deficiencies 8
- Gas, Vacuum, and Electrical Systems Deficiencies 3
- Miscellaneous Deficiencies 1
- Services Deficiencies 1
- Other 1
| Category | Citations |
|---|---|
| Smoke Deficiencies | 8 |
| Gas, Vacuum, and Electrical Systems Deficiencies | 3 |
| Miscellaneous Deficiencies | 1 |
| Services Deficiencies | 1 |
| Egress Deficiencies | 1 |
Every citation on file
As published by CMS, newest survey first. Descriptions are CMS’s own wording.
May 29, 2026 — 3 citations
| Tag | What the surveyor checks | Status |
|---|---|---|
| K-0324 | Provide properly protected cooking facilities. | Deficient, Provider has date of correction (July 27, 2026) |
| K-0345 | Have approved installation, maintenance and testing program for fire alarm systems. | Deficient, Provider has date of correction (July 27, 2026) |
| K-0511 | Have properly installed electrical wiring and gas equipment. | Deficient, Provider has date of correction (July 27, 2026) |
July 17, 2025 — 4 citations
| Tag | What the surveyor checks | Status |
|---|---|---|
| K-0324 | Provide properly protected cooking facilities. | Deficient, Provider has date of correction (September 12, 2025) |
| K-0353 | Inspect, test, and maintain automatic sprinkler systems. | Deficient, Provider has date of correction (September 12, 2025) |
| K-0371 | Have properly sized and located compartments to protect residents from smoke. | Deficient, Provider has date of correction (September 12, 2025) |
| K-0923 | Have proper medical gas storage and administration areas. | Deficient, Provider has date of correction (September 12, 2025) |
September 27, 2024 — 7 citations
| Tag | What the surveyor checks | Status |
|---|---|---|
| K-0211 | Keep aisles, corridors, and exits free of obstruction in case of emergency. | Deficient, Provider has date of correction (November 18, 2024) |
| K-0321 | Ensure that special areas are constructed so that walls can resist fire for one hour or have an approved fire extinguishing system. | Deficient, Provider has date of correction (November 18, 2024) |
| K-0324 | Provide properly protected cooking facilities. | Deficient, Provider has date of correction (November 18, 2024) |
| K-0353 | Inspect, test, and maintain automatic sprinkler systems. | Deficient, Provider has date of correction (November 26, 2024) |
| K-0781 | Have restrictions on the use of portable space heaters. | Deficient, Provider has date of correction (November 18, 2024) |
| K-0914 | Ensure receptacles at patient bed locations and where general anesthesia is administered, are tested after initial installation, replacement or servicing. | Deficient, Provider has date of correction (November 18, 2024) |
| K-0918 | Have generator or other power source capable of supplying service within 10 seconds. | Deficient, Provider has date of correction (November 18, 2024) |