Federal nursing home survey record · CMS-certified nursing home· Not a state assisted-living licensing record
CROWLEY RIDGE CARE CENTER
DEXTER, MO · 90 certified beds · Last Life Safety survey March 20, 2025
CMS Certification Number 265552 · first certified October 1993
Ownership
Operated by JAMES & JUDY LINCOLN · For profit - Individual
No change of ownership on CMS record since January 1, 2016, when the records begin.
Position within MO
5 citations — more than 9% of the 487 certified nursing homes in MO. Compared within MO rather than nationally because which state a facility is in explains about 30% of the variation in citation counts between facilities, while bed count explains under 1%. State survey agencies differ far more than the buildings do. How this is calculated
The latest survey found 2 citations; the earlier surveys in the window averaged 1.5. With 3 surveys on file this is a direction of travel, not a conclusion.
When is the next survey likely?
The window is open now: May 2026 to December 2026. This facility’s last Life Safety survey was March 2025. Facilities in MO are typically surveyed 14–21 months after the last one (median 17), measured over 567 consecutive surveys in the last two years of CMS records.
A range the record supports, not a prediction of a date. State agencies vary widely — from about 11 months in Pennsylvania to three years in Maryland. How the window is measured
Get an email about CROWLEY RIDGE CARE CENTER
One email when it happens. No account; stop it any time with one click.
Physical environment (health survey)
1 physical-environment citation on the health survey. Cited by the health surveyors under Appendix PP, not the Life Safety Code surveyor: equipment in safe operating condition, the call system, bed rails, pest control, hazards, the environment. Counted separately from the 5 Life Safety citations above. The Physical Environment Index
- F-0880 Provide and implement an infection prevention and control program.
How that compares
Compared with the median facility in MO, and nationally. Surveyors differ markedly between states, so the MO figure is the meaningful one.
| Measure | Citations |
|---|---|
| This facility | 5 |
| Median facility in MO | 18 |
| Median facility nationally | 11 |
Survey history
| Survey date | Citations |
|---|---|
| November 4, 2022 | 2 |
| April 5, 2024 | 1 |
| March 20, 2025 | 2 |
Most-cited tags
| Tag | What the surveyor checks | Times cited | Last cited |
|---|---|---|---|
| K-0211 | Keep aisles, corridors, and exits free of obstruction in case of emergency. | 2 | 2024-04-05 |
| K-0351 | Install an approved automatic sprinkler system. | 1 | 2025-03-20 |
| K-0372 | Ensure smoke barriers are constructed to a 1 hour fire resistance rating. | 1 | 2025-03-20 |
| K-0321 | Ensure that special areas are constructed so that walls can resist fire for one hour or have an approved fire extinguishing system. | 1 | 2022-11-04 |
What the citations cover
- Smoke Deficiencies 3
- Egress Deficiencies 2
| Category | Citations |
|---|---|
| Smoke Deficiencies | 3 |
| Egress Deficiencies | 2 |
Every citation on file
As published by CMS, newest survey first. Descriptions are CMS’s own wording.
March 20, 2025 — 2 citations
| Tag | What the surveyor checks | Status |
|---|---|---|
| K-0351 | Install an approved automatic sprinkler system. | Deficient, Provider has date of correction (April 28, 2025) |
| K-0372 | Ensure smoke barriers are constructed to a 1 hour fire resistance rating. | Deficient, Provider has date of correction (April 28, 2025) |
April 5, 2024 — 1 citation
| Tag | What the surveyor checks | Status |
|---|---|---|
| K-0211 | Keep aisles, corridors, and exits free of obstruction in case of emergency. | Deficient, Provider has date of correction (May 19, 2024) |
November 4, 2022 — 2 citations
| Tag | What the surveyor checks | Status |
|---|---|---|
| K-0211 | Keep aisles, corridors, and exits free of obstruction in case of emergency. | Deficient, Provider has date of correction (November 5, 2022) |
| K-0321 | Ensure that special areas are constructed so that walls can resist fire for one hour or have an approved fire extinguishing system. | Deficient, Provider has date of correction (December 16, 2022) |
Reflects the CMS posting of August 1, 2026. Surveys conducted in the last few months may not appear yet.