Federal nursing home survey record · CMS-certified nursing home· Not a state assisted-living licensing record

SCENIC WELLNESS AND REHABILITATION CENTER

HERCULANEUM, MO · 189 certified beds · Last Life Safety survey June 18, 2026

CMS Certification Number 265216 · first certified February 1984

Ownership

Independently operated (no chain recorded by CMS) · For profit - Limited Liability company

No change of ownership on CMS record since January 1, 2016, when the records begin.

12
Citations on file
CMS's current file
3
Life Safety surveys
CMS's current file
2
Tags cited more than once
Across separate surveys
7
Inspection & testing records
Of the citations on file

Position within MO

12 citations — more than 30% of the 486 certified nursing homes in MO. Compared within MO rather than nationally because which state a facility is in explains about 30% of the variation in citation counts between facilities, while bed count explains under 1%. State survey agencies differ far more than the buildings do. How this is calculated

Holding steadyabout the same at the latest survey as at its earlier surveys in CMS's current file.

The latest survey found 4 citations; the earlier surveys on file averaged 4. With 3 surveys on file this is a direction of travel, not a conclusion.

When is the next survey likely?

The window opens August 2027 — about 9 months from now. This facility’s last Life Safety survey was June 2026. Facilities in MO are typically surveyed 14–21 months after the last one (median 17), measured over 523 consecutive surveys in the last two years of CMS records.

A range the record supports, not a prediction of a date. State agencies vary widely — from about 11 months in Pennsylvania to about three years in Virginia. How the window is measured

Get an email about SCENIC WELLNESS AND REHABILITATION CENTER

One email when it happens. No account; stop it any time with one click.

Which alerts

1 inspection-and-testing tag has been cited here at more than one survey. Nationally, that pattern is common: about three quarters of cited facilities have at least one repeated tag, and half of the facilities cited for sprinkler inspection and testing in CMS’s current file are cited for it again. A repeat is usually a recordkeeping gap rather than a new hazard.

Physical environment (health survey)

4 physical-environment citations on the health survey. Cited by the health surveyors under Appendix PP, not the Life Safety Code surveyor: equipment in safe operating condition, the call system, bed rails, pest control, hazards, the environment. Counted separately from the 12 Life Safety citations above. The Physical Environment Index

  • F-0584 Honor the resident's right to a safe, clean, comfortable and homelike environment, including but not limited to receiving treatment and supports for daily living safely.
  • F-0880 Provide and implement an infection prevention and control program.
  • F-0909 Regularly inspect all bed frames, mattresses, and bed rails (if any) for safety; and all bed rails and mattresses must attach safely to the bed frame.

How that compares

Citations in CMS's current file

Compared with the median facility in MO, and nationally. Surveyors differ markedly between states, so the MO figure is the meaningful one.

This facility12MO median18National median11
Citations in CMS's current file, compared
MeasureCitations
This facility12
Median facility in MO18
Median facility nationally11

Survey history

Citations at each Life Safety survey
62024-0322025-0442026-06
Citations at each Life Safety survey
Survey dateCitations
March 1, 20246
April 11, 20252
June 18, 20264

Most-cited tags

Most-cited tags at this facility
K-03532K-09202K-03211K-07411K-03741K-03551K-02911K-03721
Most-cited tags at this facility
TagWhat the surveyor checksTimes citedLast cited
K-0353Inspect, test, and maintain automatic sprinkler systems.22026-06-18
K-0920Ensure proper usage of power strips and extension cords.22026-06-18
K-0321Ensure that special areas are constructed so that walls can resist fire for one hour or have an approved fire extinguishing system.12024-03-01
K-0741Have posted "No-smoking" signs in areas where smoking is not permitted or ashtrays provided where smoking was allowed.12025-04-11
K-0374Install smoke barrier doors that can resist smoke for at least 20 minutes.12024-03-01
K-0355Properly select, install, inspect, or maintain portable fire extinguishes.12026-06-18
K-0291Install emergency lighting that can last at least 1 1/2 hours.12024-03-01
K-0372Ensure smoke barriers are constructed to a 1 hour fire resistance rating.12024-03-01

What the citations cover

Citations by CMS category
  • Smoke Deficiencies 6
  • Gas, Vacuum, and Electrical Systems Deficiencies 4
  • Egress Deficiencies 1
  • Miscellaneous Deficiencies 1
Citations by CMS category
CategoryCitations
Smoke Deficiencies6
Gas, Vacuum, and Electrical Systems Deficiencies4
Egress Deficiencies1
Miscellaneous Deficiencies1

Every citation on file

As published by CMS, newest survey first. Descriptions are CMS’s own wording.

June 18, 2026 — 4 citations

Citations issued on June 18, 2026
TagWhat the surveyor checksStatus
K-0353Inspect, test, and maintain automatic sprinkler systems.Deficient, Provider has date of correction (July 31, 2026)
K-0355Properly select, install, inspect, or maintain portable fire extinguishes.Deficient, Provider has date of correction (July 31, 2026)
K-0920Ensure proper usage of power strips and extension cords.Deficient, Provider has date of correction (July 31, 2026)
K-0923Have proper medical gas storage and administration areas.Deficient, Provider has date of correction (July 31, 2026)

April 11, 2025 — 2 citations

Citations issued on April 11, 2025
TagWhat the surveyor checksStatus
K-0741Have posted "No-smoking" signs in areas where smoking is not permitted or ashtrays provided where smoking was allowed.Deficient, Provider has date of correction (May 6, 2025)
K-0920Ensure proper usage of power strips and extension cords.Deficient, Provider has date of correction (May 6, 2025)

March 1, 2024 — 6 citations

Citations issued on March 1, 2024
TagWhat the surveyor checksStatus
K-0291Install emergency lighting that can last at least 1 1/2 hours.Deficient, Provider has date of correction (April 3, 2024)
K-0321Ensure that special areas are constructed so that walls can resist fire for one hour or have an approved fire extinguishing system.Deficient, Provider has date of correction (April 3, 2024)
K-0353Inspect, test, and maintain automatic sprinkler systems.Deficient, Provider has date of correction (April 3, 2024)
K-0372Ensure smoke barriers are constructed to a 1 hour fire resistance rating.Deficient, Provider has date of correction (April 3, 2024)
K-0374Install smoke barrier doors that can resist smoke for at least 20 minutes.Deficient, Provider has date of correction (April 3, 2024)
K-0918Have generator or other power source capable of supplying service within 10 seconds.Deficient, Provider has date of correction (April 3, 2024)

Reflects the CMS posting of October 1, 2026. Surveys conducted in the last few months may not appear yet.