Federal nursing home survey record · CMS-certified nursing home· Not a state assisted-living licensing record
Village Green Health and Rehabilitation
Fayetteville, NC · 170 certified beds · Last Life Safety survey February 20, 2025
CMS Certification Number 345380 · first certified July 1991
Ownership
Operated by SANSTONE HEALTH & REHABILITATION · For profit - Individual
- Ownership changed April 1, 2017 (change of ownership)to VILLAGE GREEN HEALTH AND REHABILITATION LLC from REHABILITATION AND HEALTH CARE CENTER AT VILLAGE GREEN
Position within NC
8 citations — more than 34% of the 419 certified nursing homes in NC. Compared within NC rather than nationally because which state a facility is in explains about 30% of the variation in citation counts between facilities, while bed count explains under 1%. State survey agencies differ far more than the buildings do. How this is calculated
The latest survey found 3 citations; the earlier surveys in the window averaged 2.5. With 3 surveys on file this is a direction of travel, not a conclusion.
When is the next survey likely?
Well past the typical window (April 2026 to June 2026), and past the point by which nine in ten NC facilities have been surveyed. This facility’s last Life Safety survey was February 2025. Facilities in NC are typically surveyed 14–16 months after the last one (median 15), measured over 412 consecutive surveys in the last two years of CMS records.
A range the record supports, not a prediction of a date. State agencies vary widely — from about 11 months in Pennsylvania to three years in Maryland. How the window is measured
Get an email about Village Green Health and Rehabilitation
One email when it happens. No account; stop it any time with one click.
1 inspection-and-testing tag has been cited here at more than one survey. Nationally, that pattern is common: about three quarters of cited facilities have at least one repeated tag, and half of the facilities ever cited for sprinkler inspection and testing are cited for it again. A repeat is usually a recordkeeping gap rather than a new hazard.
How that compares
Compared with the median facility in NC, and nationally. Surveyors differ markedly between states, so the NC figure is the meaningful one.
| Measure | Citations |
|---|---|
| This facility | 8 |
| Median facility in NC | 9 |
| Median facility nationally | 11 |
Survey history
| Survey date | Citations |
|---|---|
| August 3, 2022 | 1 |
| January 19, 2024 | 4 |
| February 20, 2025 | 3 |
Most-cited tags
| Tag | What the surveyor checks | Times cited | Last cited |
|---|---|---|---|
| K-0521 | Ensure heating and ventilation systems that have been properly installed according to the manufacturer's instructions. | 2 | 2025-02-20 |
| K-0341 | Install a fire alarm system that can be heard throughout the facility. | 2 | 2025-02-20 |
| K-0161 | Use approved construction type or materials. | 1 | 2024-01-19 |
| K-0344 | Have an alternate power supply for its alarm system. | 1 | 2022-08-03 |
| K-0923 | Have proper medical gas storage and administration areas. | 1 | 2024-01-19 |
| K-0200 | Meet other general requirements. | 1 | 2025-02-20 |
What the citations cover
- Smoke Deficiencies 3
- Services Deficiencies 2
- Gas, Vacuum, and Electrical Systems Deficiencies 1
- Egress Deficiencies 1
- Other 1
| Category | Citations |
|---|---|
| Smoke Deficiencies | 3 |
| Services Deficiencies | 2 |
| Gas, Vacuum, and Electrical Systems Deficiencies | 1 |
| Egress Deficiencies | 1 |
| Construction Deficiencies | 1 |
Every citation on file
As published by CMS, newest survey first. Descriptions are CMS’s own wording.
February 20, 2025 — 3 citations
| Tag | What the surveyor checks | Status |
|---|---|---|
| K-0200 | Meet other general requirements. | Deficient, Provider has date of correction (June 27, 2025) |
| K-0341 | Install a fire alarm system that can be heard throughout the facility. | Deficient, Provider has date of correction (June 27, 2025) |
| K-0521 | Ensure heating and ventilation systems that have been properly installed according to the manufacturer's instructions. | Deficient, Provider has date of correction (June 27, 2025) |
January 19, 2024 — 4 citations
| Tag | What the surveyor checks | Status |
|---|---|---|
| K-0161 | Use approved construction type or materials. | Deficient, Provider has date of correction (March 15, 2024) |
| K-0341 | Install a fire alarm system that can be heard throughout the facility. | Deficient, Provider has date of correction (March 15, 2024) |
| K-0521 | Ensure heating and ventilation systems that have been properly installed according to the manufacturer's instructions. | Deficient, Provider has date of correction (March 15, 2024) |
| K-0923 | Have proper medical gas storage and administration areas. | Deficient, Provider has date of correction (March 15, 2024) |
August 3, 2022 — 1 citation
| Tag | What the surveyor checks | Status |
|---|---|---|