Federal nursing home survey record · CMS-certified nursing home· Not a state assisted-living licensing record
Harborview Lumberton
Lumberton, NC · 122 certified beds · Last Life Safety survey June 4, 2026
CMS Certification Number 345234 · first certified February 1983
Ownership
Operated by HARBORVIEW HEALTH SYSTEMS · For profit - Limited Liability company
- Ownership changed March 1, 2022 (change of ownership)from LUMBERTON OPERATING COMPANY LLC
Position within NC
12 citations — more than 58% of the 419 certified nursing homes in NC. Compared within NC rather than nationally because which state a facility is in explains about 30% of the variation in citation counts between facilities, while bed count explains under 1%. State survey agencies differ far more than the buildings do. How this is calculated
The latest survey found 4 citations; the earlier surveys on file averaged 4. With 3 surveys on file this is a direction of travel, not a conclusion.
When is the next survey likely?
The window opens July 2027 — about 9 months from now. This facility’s last Life Safety survey was June 2026. Facilities in NC are typically surveyed 14–15 months after the last one (median 14), measured over 458 consecutive surveys in the last two years of CMS records.
A range the record supports, not a prediction of a date. State agencies vary widely — from about 11 months in Pennsylvania to about three years in Virginia. How the window is measured
Get an email about Harborview Lumberton
One email when it happens. No account; stop it any time with one click.
How that compares
Compared with the median facility in NC, and nationally. Surveyors differ markedly between states, so the NC figure is the meaningful one.
| Measure | Citations |
|---|---|
| This facility | 12 |
| Median facility in NC | 10 |
| Median facility nationally | 11 |
Survey history
| Survey date | Citations |
|---|---|
| January 25, 2024 | 2 |
| April 10, 2025 | 6 |
| June 4, 2026 | 4 |
Most-cited tags
| Tag | What the surveyor checks | Times cited | Last cited |
|---|---|---|---|
| K-0321 | Ensure that special areas are constructed so that walls can resist fire for one hour or have an approved fire extinguishing system. | 2 | 2025-04-10 |
| K-0912 | Have power receptacles that are properly grounded. | 1 | 2026-06-04 |
| K-0347 | Properly provide smoke detection systems in areas open to corridors. | 1 | 2026-06-04 |
| K-0923 | Have proper medical gas storage and administration areas. | 1 | 2025-04-10 |
| K-0345 | Have approved installation, maintenance and testing program for fire alarm systems. | 1 | 2025-04-10 |
| K-0351 | Install an approved automatic sprinkler system. | 1 | 2026-06-04 |
| K-0353 | Inspect, test, and maintain automatic sprinkler systems. | 1 | 2025-04-10 |
| K-0211 | Keep aisles, corridors, and exits free of obstruction in case of emergency. | 1 | 2025-04-10 |
What the citations cover
- Smoke Deficiencies 7
- Gas, Vacuum, and Electrical Systems Deficiencies 2
- Egress Deficiencies 2
- Construction Deficiencies 1
| Category | Citations |
|---|---|
| Smoke Deficiencies | 7 |
| Gas, Vacuum, and Electrical Systems Deficiencies | 2 |
| Egress Deficiencies | 2 |
| Construction Deficiencies | 1 |
Every citation on file
As published by CMS, newest survey first. Descriptions are CMS’s own wording.
June 4, 2026 — 4 citations
| Tag | What the surveyor checks | Status |
|---|---|---|
| K-0222 | Add doors in an exit area that do not require the use of a key from the exit side unless in case of special locking arrangements. | Deficient, Provider has plan of correction (August 26, 2026) |
| K-0347 | Properly provide smoke detection systems in areas open to corridors. | Deficient, Provider has plan of correction (September 11, 2026) |
| K-0351 | Install an approved automatic sprinkler system. | Deficient, Provider has plan of correction (August 26, 2026) |
| K-0912 | Have power receptacles that are properly grounded. | Deficient, Provider has plan of correction (August 24, 2026) |
April 10, 2025 — 6 citations
| Tag | What the surveyor checks | Status |
|---|---|---|
| K-0211 | Keep aisles, corridors, and exits free of obstruction in case of emergency. | Deficient, Provider has date of correction (June 25, 2025) |
| K-0321 | Ensure that special areas are constructed so that walls can resist fire for one hour or have an approved fire extinguishing system. | Deficient, Provider has date of correction (June 25, 2025) |
| K-0345 | Have approved installation, maintenance and testing program for fire alarm systems. | Deficient, Provider has date of correction (June 25, 2025) |
| K-0353 | Inspect, test, and maintain automatic sprinkler systems. | Deficient, Provider has date of correction (June 25, 2025) |
| K-0363 | Install corridor and hallway doors that block smoke. | Deficient, Provider has date of correction (June 25, 2025) |
| K-0923 | Have proper medical gas storage and administration areas. | Deficient, Provider has date of correction (June 25, 2025) |
January 25, 2024 — 2 citations
| Tag | What the surveyor checks | Status |
|---|---|---|
| K-0161 | Use approved construction type or materials. | Deficient, Provider has date of correction (March 8, 2024) |
| K-0321 | Ensure that special areas are constructed so that walls can resist fire for one hour or have an approved fire extinguishing system. | Deficient, Provider has date of correction (March 8, 2024) |
Reflects the CMS posting of October 1, 2026. Surveys conducted in the last few months may not appear yet.