Federal nursing home survey record · CMS-certified nursing home· Not a state assisted-living licensing record
Clapps Nursing Center Inc
Pleasant Garden, NC · 118 certified beds · Last Life Safety survey June 26, 2024
CMS Certification Number 345024 · first certified October 1976
Ownership
Independently operated (no chain recorded by CMS) · For profit - Individual
No change of ownership on CMS record since January 1, 2016, when the records begin.
Position within NC
8 citations — more than 34% of the 419 certified nursing homes in NC. Compared within NC rather than nationally because which state a facility is in explains about 30% of the variation in citation counts between facilities, while bed count explains under 1%. State survey agencies differ far more than the buildings do. How this is calculated
When is the next survey likely?
Well past the typical window (August 2025 to October 2025), and past the point by which nine in ten NC facilities have been surveyed. This facility’s last Life Safety survey was June 2024. Facilities in NC are typically surveyed 14–16 months after the last one (median 15), measured over 412 consecutive surveys in the last two years of CMS records.
A range the record supports, not a prediction of a date. State agencies vary widely — from about 11 months in Pennsylvania to three years in Maryland. How the window is measured
Get an email about Clapps Nursing Center Inc
One email when it happens. No account; stop it any time with one click.
How that compares
Compared with the median facility in NC, and nationally. Surveyors differ markedly between states, so the NC figure is the meaningful one.
| Measure | Citations |
|---|---|
| This facility | 8 |
| Median facility in NC | 9 |
| Median facility nationally | 11 |
Survey history
| Survey date | Citations |
|---|---|
| March 31, 2022 | 0 |
| May 24, 2023 | 0 |
| June 26, 2024 | 8 |
Most-cited tags
| Tag | What the surveyor checks | Times cited | Last cited |
|---|---|---|---|
| K-0211 | Keep aisles, corridors, and exits free of obstruction in case of emergency. | 1 | 2024-06-26 |
| K-0914 | Ensure receptacles at patient bed locations and where general anesthesia is administered, are tested after initial installation, replacement or servicing. | 1 | 2024-06-26 |
| K-0281 | Install proper backup exit lighting. | 1 | 2024-06-26 |
| K-0321 | Ensure that special areas are constructed so that walls can resist fire for one hour or have an approved fire extinguishing system. | 1 | 2024-06-26 |
| K-0511 | Have properly installed electrical wiring and gas equipment. | 1 | 2024-06-26 |
| K-0700 | Meet requirements for operating features, such as evacuation plans, fire drills, smoking regulations, draperies, decorations and the inspection, testing and maintenance of fire doors. | 1 | 2024-06-26 |
| K-0521 | Ensure heating and ventilation systems that have been properly installed according to the manufacturer's instructions. | 1 | 2024-06-26 |
| K-0351 | Install an approved automatic sprinkler system. | 1 | 2024-06-26 |
What the citations cover
- Egress Deficiencies 2
- Smoke Deficiencies 2
- Services Deficiencies 2
- Gas, Vacuum, and Electrical Systems Deficiencies 1
- Other 1
| Category | Citations |
|---|---|
| Egress Deficiencies | 2 |
| Smoke Deficiencies | 2 |
| Services Deficiencies | 2 |
| Gas, Vacuum, and Electrical Systems Deficiencies | 1 |
| Miscellaneous Deficiencies | 1 |
Every citation on file
As published by CMS, newest survey first. Descriptions are CMS’s own wording.
June 26, 2024 — 8 citations
| Tag | What the surveyor checks | Status |
|---|---|---|
| K-0211 | Keep aisles, corridors, and exits free of obstruction in case of emergency. | Deficient, Provider has date of correction (September 23, 2024) |
| K-0281 | Install proper backup exit lighting. | Deficient, Provider has date of correction (September 23, 2024) |
| K-0321 | Ensure that special areas are constructed so that walls can resist fire for one hour or have an approved fire extinguishing system. | Deficient, Provider has date of correction (September 23, 2024) |
| K-0351 | Install an approved automatic sprinkler system. | Deficient, Provider has date of correction (September 23, 2024) |
| K-0511 | Have properly installed electrical wiring and gas equipment. | Deficient, Provider has date of correction (September 23, 2024) |
| K-0521 | Ensure heating and ventilation systems that have been properly installed according to the manufacturer's instructions. | Deficient, Provider has date of correction (September 23, 2024) |
| K-0700 | Meet requirements for operating features, such as evacuation plans, fire drills, smoking regulations, draperies, decorations and the inspection, testing and maintenance of fire doors. | Deficient, Provider has date of correction (September 23, 2024) |
| K-0914 | Ensure receptacles at patient bed locations and where general anesthesia is administered, are tested after initial installation, replacement or servicing. | Deficient, Provider has date of correction (September 23, 2024) |
Reflects the CMS posting of August 1, 2026. Surveys conducted in the last few months may not appear yet.