Federal nursing home survey record · CMS-certified nursing home· Not a state assisted-living licensing record

White Oak of Waxhaw

Waxhaw, NC · 100 certified beds · Last Life Safety survey August 2, 2024

CMS Certification Number 345550 · first certified April 2010

Ownership

Independently operated (no chain recorded by CMS) · For profit - Limited Liability company

No change of ownership on CMS record since January 1, 2016, when the records begin.

5
Citations on file
Rolling three-year window
3
Life Safety surveys
In the same window
1
Tags cited more than once
Across separate surveys
4
Inspection & testing records
Of the citations on file

Position within NC

5 citations — more than 16% of the 419 certified nursing homes in NC. Compared within NC rather than nationally because which state a facility is in explains about 30% of the variation in citation counts between facilities, while bed count explains under 1%. State survey agencies differ far more than the buildings do. How this is calculated

Improvingfewer citations at the latest survey than at its earlier surveys in the window.

The latest survey found 2 citations; the earlier surveys in the window averaged 1.5. With 3 surveys on file this is a direction of travel, not a conclusion.

When is the next survey likely?

Well past the typical window (September 2025 to November 2025), and past the point by which nine in ten NC facilities have been surveyed. This facility’s last Life Safety survey was August 2024. Facilities in NC are typically surveyed 14–16 months after the last one (median 15), measured over 412 consecutive surveys in the last two years of CMS records.

A range the record supports, not a prediction of a date. State agencies vary widely — from about 11 months in Pennsylvania to three years in Maryland. How the window is measured

Get an email about White Oak of Waxhaw

One email when it happens. No account; stop it any time with one click.

Which alerts

1 inspection-and-testing tag has been cited here at more than one survey. Nationally, that pattern is common: about three quarters of cited facilities have at least one repeated tag, and half of the facilities ever cited for sprinkler inspection and testing are cited for it again. A repeat is usually a recordkeeping gap rather than a new hazard.

How that compares

Citations on file over three years

Compared with the median facility in NC, and nationally. Surveyors differ markedly between states, so the NC figure is the meaningful one.

This facility5NC median9National median11
Citations on file over three years, compared
MeasureCitations
This facility5
Median facility in NC9
Median facility nationally11

Survey history

Citations at each Life Safety survey
02022-0232023-0322024-08
Citations at each Life Safety survey
Survey dateCitations
February 3, 20220
March 30, 20233
August 2, 20242

Most-cited tags

Most-cited tags at this facility
K-05112K-05211K-09181K-03211
Most-cited tags at this facility
TagWhat the surveyor checksTimes citedLast cited
K-0511Have properly installed electrical wiring and gas equipment.22024-08-02
K-0521Ensure heating and ventilation systems that have been properly installed according to the manufacturer's instructions.12023-03-30
K-0918Have generator or other power source capable of supplying service within 10 seconds.12024-08-02
K-0321Ensure that special areas are constructed so that walls can resist fire for one hour or have an approved fire extinguishing system.12023-03-30

What the citations cover

Citations by CMS category
  • Services Deficiencies 3
  • Gas, Vacuum, and Electrical Systems Deficiencies 1
  • Smoke Deficiencies 1
Citations by CMS category
CategoryCitations
Services Deficiencies3
Gas, Vacuum, and Electrical Systems Deficiencies1
Smoke Deficiencies1

Every citation on file

As published by CMS, newest survey first. Descriptions are CMS’s own wording.

August 2, 2024 — 2 citations

Citations issued on August 2, 2024
TagWhat the surveyor checksStatus
K-0511Have properly installed electrical wiring and gas equipment.Deficient, Provider has date of correction (September 30, 2024)
K-0918Have generator or other power source capable of supplying service within 10 seconds.Deficient, Provider has date of correction (September 30, 2024)

March 30, 2023 — 3 citations

Citations issued on March 30, 2023
TagWhat the surveyor checksStatus
K-0321Ensure that special areas are constructed so that walls can resist fire for one hour or have an approved fire extinguishing system.Deficient, Provider has date of correction (May 8, 2023)
K-0511Have properly installed electrical wiring and gas equipment.Deficient, Provider has date of correction (May 8, 2023)
K-0521Ensure heating and ventilation systems that have been properly installed according to the manufacturer's instructions.Deficient, Provider has date of correction (May 8, 2023)

Reflects the CMS posting of August 1, 2026. Surveys conducted in the last few months may not appear yet.