Federal nursing home survey record · CMS-certified nursing home· Not a state assisted-living licensing record

COMPLETE CARE AT CLARK LLC

CLARK, NJ · 140 certified beds · Last Life Safety survey May 15, 2025

CMS Certification Number 315341 · first certified March 1995

Ownership

Operated by COMPLETE CARE · For profit - Corporation

  • Ownership changed April 1, 2023 (change of ownership)from CLARK NURSING AND REHABILITATION CENTER LLC
19
Citations on file
Rolling three-year window
3
Life Safety surveys
In the same window
3
Tags cited more than once
Across separate surveys
9
Inspection & testing records
Of the citations on file

Position within NJ

19 citations — more than 68% of the 348 certified nursing homes in NJ. Compared within NJ rather than nationally because which state a facility is in explains about 30% of the variation in citation counts between facilities, while bed count explains under 1%. State survey agencies differ far more than the buildings do. How this is calculated

Slippingmore citations at the latest survey than at its earlier surveys in the window.

The latest survey found 12 citations; the earlier surveys in the window averaged 3.5. With 3 surveys on file this is a direction of travel, not a conclusion.

When is the next survey likely?

The window is open now: September 2026 to January 2027. This facility’s last Life Safety survey was May 2025. Facilities in NJ are typically surveyed 16–20 months after the last one (median 17), measured over 431 consecutive surveys in the last two years of CMS records.

A range the record supports, not a prediction of a date. State agencies vary widely — from about 11 months in Pennsylvania to three years in Maryland. How the window is measured

Get an email about COMPLETE CARE AT CLARK LLC

One email when it happens. No account; stop it any time with one click.

Which alerts

3 inspection-and-testing tags have been cited here at more than one survey. Nationally, that pattern is common: about three quarters of cited facilities have at least one repeated tag, and half of the facilities ever cited for sprinkler inspection and testing are cited for it again. A repeat is usually a recordkeeping gap rather than a new hazard.

Physical environment (health survey)

1 physical-environment citation on the health survey. Cited by the health surveyors under Appendix PP, not the Life Safety Code surveyor: equipment in safe operating condition, the call system, bed rails, pest control, hazards, the environment. Counted separately from the 19 Life Safety citations above. The Physical Environment Index

  • F-0880 Provide and implement an infection prevention and control program.

How that compares

Citations on file over three years

Compared with the median facility in NJ, and nationally. Surveyors differ markedly between states, so the NJ figure is the meaningful one.

This facility19NJ median15National median11
Citations on file over three years, compared
MeasureCitations
This facility19
Median facility in NJ15
Median facility nationally11

Survey history

Citations at each Life Safety survey
22022-0152023-11122025-05
Citations at each Life Safety survey
Survey dateCitations
January 5, 20222
November 6, 20235
May 15, 202512

Most-cited tags

Most-cited tags at this facility
K-09182K-03452K-03632K-05311K-02231K-09111K-03531K-03511
Most-cited tags at this facility
TagWhat the surveyor checksTimes citedLast cited
K-0918Have generator or other power source capable of supplying service within 10 seconds.22025-05-15
K-0345Have approved installation, maintenance and testing program for fire alarm systems.22025-05-15
K-0363Install corridor and hallway doors that block smoke.22025-05-15
K-0531Have elevators that firefighters can control in the event of a fire.12025-05-15
K-0223Provide exit doors that are held open by devices that will automatically close on the activation of a fire alarm or smoke detector.12025-05-15
K-0911Meet requirements for the installation and maintenance of electrical systems.12025-05-15
K-0353Inspect, test, and maintain automatic sprinkler systems.12025-05-15
K-0351Install an approved automatic sprinkler system.12022-01-05

What the citations cover

Citations by CMS category
  • Smoke Deficiencies 8
  • Gas, Vacuum, and Electrical Systems Deficiencies 5
  • Egress Deficiencies 5
  • Services Deficiencies 1
Citations by CMS category
CategoryCitations
Smoke Deficiencies8
Gas, Vacuum, and Electrical Systems Deficiencies5
Egress Deficiencies5
Services Deficiencies1

Every citation on file

As published by CMS, newest survey first. Descriptions are CMS’s own wording.

May 15, 2025 — 12 citations

Citations issued on May 15, 2025
TagWhat the surveyor checksStatus
K-0211Keep aisles, corridors, and exits free of obstruction in case of emergency.Deficient, Provider has date of correction (June 5, 2025)
K-0222Add doors in an exit area that do not require the use of a key from the exit side unless in case of special locking arrangements.Deficient, Provider has date of correction (June 5, 2025)
K-0223Provide exit doors that are held open by devices that will automatically close on the activation of a fire alarm or smoke detector.Deficient, Provider has date of correction (June 17, 2025)
K-0293Have properly located and lighted "Exit" signs.Deficient, Provider has date of correction (June 5, 2025)
K-0341Install a fire alarm system that can be heard throughout the facility.Deficient, Provider has date of correction (June 5, 2025)
K-0345Have approved installation, maintenance and testing program for fire alarm systems.Deficient, Provider has date of correction (June 5, 2025)
K-0353Inspect, test, and maintain automatic sprinkler systems.Deficient, Provider has date of correction (June 5, 2025)
K-0363Install corridor and hallway doors that block smoke.Deficient, Provider has date of correction (June 6, 2025)
K-0374Install smoke barrier doors that can resist smoke for at least 20 minutes.Deficient, Provider has date of correction (June 6, 2025)
K-0531Have elevators that firefighters can control in the event of a fire.Deficient, Provider has date of correction (June 17, 2025)
K-0911Meet requirements for the installation and maintenance of electrical systems.Deficient, Provider has date of correction (June 3, 2025)
K-0918Have generator or other power source capable of supplying service within 10 seconds.Deficient, Provider has date of correction (June 5, 2025)

November 6, 2023 — 5 citations

Citations issued on November 6, 2023
TagWhat the surveyor checksStatus
K-0345Have approved installation, maintenance and testing program for fire alarm systems.Deficient, Provider has date of correction (November 23, 2023)
K-0363Install corridor and hallway doors that block smoke.Deficient, Provider has date of correction (November 24, 2023)
K-0908Ensure gas and vacuum systems are inspected and tested as part of a maintenance program.Deficient, Provider has date of correction (November 24, 2023)
K-0918Have generator or other power source capable of supplying service within 10 seconds.Deficient, Provider has date of correction (November 24, 2023)
K-0923Have proper medical gas storage and administration areas.Deficient, Provider has date of correction (November 24, 2023)

January 5, 2022 — 2 citations

Citations issued on January 5, 2022
TagWhat the surveyor checksStatus
K-0291Install emergency lighting that can last at least 1 1/2 hours.Deficient, Provider has date of correction (January 23, 2022)
K-0351Install an approved automatic sprinkler system.Deficient, Provider has date of correction (January 23, 2022)

Reflects the CMS posting of August 1, 2026. Surveys conducted in the last few months may not appear yet.