Federal nursing home survey record · CMS-certified nursing home· Not a state assisted-living licensing record
ATRIUM AT NAVESINK HARBOR, THE
RED BANK, NJ · 43 certified beds · Last Life Safety survey February 25, 2026
CMS Certification Number 315515 · first certified December 2013
Ownership
Operated by SPRINGPOINT SENIOR LIVING · Non profit - Corporation
No change of ownership on CMS record since January 1, 2016, when the records begin.
Position within NJ
8 citations — more than 14% of the 348 certified nursing homes in NJ. Compared within NJ rather than nationally because which state a facility is in explains about 30% of the variation in citation counts between facilities, while bed count explains under 1%. State survey agencies differ far more than the buildings do. How this is calculated
The latest survey found 1 citation; the earlier surveys in the window averaged 3.5. With 3 surveys on file this is a direction of travel, not a conclusion.
When is the next survey likely?
The window opens June 2027 — about 9 months from now. This facility’s last Life Safety survey was February 2026. Facilities in NJ are typically surveyed 16–20 months after the last one (median 17), measured over 431 consecutive surveys in the last two years of CMS records.
A range the record supports, not a prediction of a date. State agencies vary widely — from about 11 months in Pennsylvania to three years in Maryland. How the window is measured
Get an email about ATRIUM AT NAVESINK HARBOR, THE
One email when it happens. No account; stop it any time with one click.
Emergency preparedness
2 of the 8 citations on file are Emergency Preparedness E-tags. E-tags are cited under 42 CFR §483.73 and concern the emergency plan, training, drills, communications and supplies. Nationally about half of certified facilities have at least one. The Emergency Preparedness Index
Physical environment (health survey)
2 physical-environment citations on the health survey. Cited by the health surveyors under Appendix PP, not the Life Safety Code surveyor: equipment in safe operating condition, the call system, bed rails, pest control, hazards, the environment. Counted separately from the 8 Life Safety citations above. The Physical Environment Index
How that compares
Compared with the median facility in NJ, and nationally. Surveyors differ markedly between states, so the NJ figure is the meaningful one.
| Measure | Citations |
|---|---|
| This facility | 8 |
| Median facility in NJ | 15 |
| Median facility nationally | 11 |
Survey history
| Survey date | Citations |
|---|---|
| July 7, 2023 | 3 |
| September 19, 2024 | 4 |
| February 25, 2026 | 1 |
Most-cited tags
| Tag | What the surveyor checks | Times cited | Last cited |
|---|---|---|---|
| K-0293 | Have properly located and lighted "Exit" signs. | 1 | 2024-09-19 |
| K-0920 | Ensure proper usage of power strips and extension cords. | 1 | 2023-07-07 |
| K-0741 | Have posted "No-smoking" signs in areas where smoking is not permitted or ashtrays provided where smoking was allowed. | 1 | 2023-07-07 |
| K-0222 | Add doors in an exit area that do not require the use of a key from the exit side unless in case of special locking arrangements. | 1 | 2026-02-25 |
| E-0039 | Conduct testing and exercise requirements. | 1 | 2024-09-19 |
| K-0200 | Meet other general requirements. | 1 | 2023-07-07 |
| E-0009 | Include a process for Emergency Preparedness collaboration. | 1 | 2024-09-19 |
| K-0223 | Provide exit doors that are held open by devices that will automatically close on the activation of a fire alarm or smoke detector. | 1 | 2024-09-19 |
What the citations cover
- Egress Deficiencies 4
- Emergency Preparedness Deficiencies 2
- Gas, Vacuum, and Electrical Systems Deficiencies 1
- Miscellaneous Deficiencies 1
| Category | Citations |
|---|---|
| Egress Deficiencies | 4 |
| Emergency Preparedness Deficiencies | 2 |
| Gas, Vacuum, and Electrical Systems Deficiencies | 1 |
| Miscellaneous Deficiencies | 1 |
Every citation on file
As published by CMS, newest survey first. Descriptions are CMS’s own wording.
February 25, 2026 — 1 citation
| Tag | What the surveyor checks | Status |
|---|---|---|
| K-0222 | Add doors in an exit area that do not require the use of a key from the exit side unless in case of special locking arrangements. | Deficient, Provider has date of correction (March 4, 2026) |
September 19, 2024 — 4 citations
| Tag | What the surveyor checks | Status |
|---|---|---|
| E-0009 | Include a process for Emergency Preparedness collaboration. | Deficient, Provider has date of correction (November 4, 2024) |
| E-0039 | Conduct testing and exercise requirements. | Deficient, Provider has date of correction (November 8, 2024) |
| K-0223 | Provide exit doors that are held open by devices that will automatically close on the activation of a fire alarm or smoke detector. | Deficient, Provider has date of correction (October 7, 2024) |
| K-0293 | Have properly located and lighted "Exit" signs. | Deficient, Provider has date of correction (October 2, 2024) |
July 7, 2023 — 3 citations
| Tag | What the surveyor checks | Status |
|---|---|---|
| K-0200 | Meet other general requirements. | Deficient, Provider has date of correction (August 18, 2023) |
| K-0741 | Have posted "No-smoking" signs in areas where smoking is not permitted or ashtrays provided where smoking was allowed. | Deficient, Provider has date of correction (August 31, 2023) |
| K-0920 | Ensure proper usage of power strips and extension cords. | Deficient, Provider has date of correction (August 4, 2023) |