Federal nursing home survey record · CMS-certified nursing home· Not a state assisted-living licensing record

King Street Home Inc

Port Chester, NY · 120 certified beds · Last Life Safety survey January 29, 2025

CMS Certification Number 335447 · first certified July 1975

Ownership

Independently operated (no chain recorded by CMS) · For profit - Corporation

No change of ownership on CMS record since January 1, 2016, when the records begin.

22
Citations on file
Rolling three-year window
4
Life Safety surveys
In the same window
4
Tags cited more than once
Across separate surveys
11
Inspection & testing records
Of the citations on file

Position within NY

22 citations — more than 78% of the 593 certified nursing homes in NY. Compared within NY rather than nationally because which state a facility is in explains about 30% of the variation in citation counts between facilities, while bed count explains under 1%. State survey agencies differ far more than the buildings do. How this is calculated

Improvingfewer citations at the latest survey than at its earlier surveys in the window.

The latest survey found 1 citation; the earlier surveys in the window averaged 7. With 4 surveys on file this is a direction of travel, not a conclusion.

When is the next survey likely?

The window is open now: July 2026 to March 2027. This facility’s last Life Safety survey was January 2025. Facilities in NY are typically surveyed 18–25 months after the last one (median 22), measured over 523 consecutive surveys in the last two years of CMS records.

A range the record supports, not a prediction of a date. State agencies vary widely — from about 11 months in Pennsylvania to three years in Maryland. How the window is measured

Get an email about King Street Home Inc

One email when it happens. No account; stop it any time with one click.

Which alerts

3 inspection-and-testing tags have been cited here at more than one survey. Nationally, that pattern is common: about three quarters of cited facilities have at least one repeated tag, and half of the facilities ever cited for sprinkler inspection and testing are cited for it again. A repeat is usually a recordkeeping gap rather than a new hazard.

Emergency preparedness

4 of the 22 citations on file are Emergency Preparedness E-tags. E-tags are cited under 42 CFR §483.73 and concern the emergency plan, training, drills, communications and supplies. Nationally about half of certified facilities have at least one. The Emergency Preparedness Index

Physical environment (health survey)

2 physical-environment citations on the health survey. Cited by the health surveyors under Appendix PP, not the Life Safety Code surveyor: equipment in safe operating condition, the call system, bed rails, pest control, hazards, the environment. Counted separately from the 22 Life Safety citations above. The Physical Environment Index

  • F-0880 Provide and implement an infection prevention and control program.

How that compares

Citations on file over three years

Compared with the median facility in NY, and nationally. Surveyors differ markedly between states, so the NY figure is the meaningful one.

This facility22NY median13National median11
Citations on file over three years, compared
MeasureCitations
This facility22
Median facility in NY13
Median facility nationally11

Survey history

Citations at each Life Safety survey
62018-11112020-1142024-0112025-01
Citations at each Life Safety survey
Survey dateCitations
November 21, 20186
November 12, 202011
January 11, 20244
January 29, 20251

Most-cited tags

Most-cited tags at this facility
K-03533K-05112K-09212K-07122E-00301E-00411K-09141K-09011
Most-cited tags at this facility
TagWhat the surveyor checksTimes citedLast cited
K-0353Inspect, test, and maintain automatic sprinkler systems.32024-01-11
K-0511Have properly installed electrical wiring and gas equipment.22020-11-12
K-0921Ensure that testing and maintenance of electrical equipment is performed.22024-01-11
K-0712Have simulated fire drills held at unexpected times.22024-01-11
E-0030List the names and contact information of those in the facility.12020-11-12
E-0041Implement emergency and standby power systems.12020-11-12
K-0914Ensure receptacles at patient bed locations and where general anesthesia is administered, are tested after initial installation, replacement or servicing.12018-11-21
K-0901Ensure that building systems meet requirements determined by risk assessment procedures performed by qualified personnel.12018-11-21

What the citations cover

Citations by CMS category
  • Smoke Deficiencies 7
  • Emergency Preparedness Deficiencies 4
  • Gas, Vacuum, and Electrical Systems Deficiencies 4
  • Services Deficiencies 2
  • Other 5
Citations by CMS category
CategoryCitations
Smoke Deficiencies7
Emergency Preparedness Deficiencies4
Gas, Vacuum, and Electrical Systems Deficiencies4
Services Deficiencies2
Egress Deficiencies2
Miscellaneous Deficiencies2
Electrical Deficiencies1

Every citation on file

As published by CMS, newest survey first. Descriptions are CMS’s own wording.

January 29, 2025 — 1 citation

Citations issued on January 29, 2025
TagWhat the surveyor checksStatus
K-0346Follow proper procedures when the fire alarm was out of service for more than 4 hours.Deficient, Provider has date of correction (February 10, 2025)

January 11, 2024 — 4 citations

Citations issued on January 11, 2024
TagWhat the surveyor checksStatus
K-0353Inspect, test, and maintain automatic sprinkler systems.Deficient, Provider has date of correction (January 11, 2024)
K-0363Install corridor and hallway doors that block smoke.Deficient, Provider has date of correction (January 11, 2024)
K-0712Have simulated fire drills held at unexpected times.Deficient, Provider has date of correction (January 11, 2024)
K-0921Ensure that testing and maintenance of electrical equipment is performed.Deficient, Provider has date of correction (January 11, 2024)

November 12, 2020 — 11 citations

Citations issued on November 12, 2020
TagWhat the surveyor checksStatus
E-0004Develop and maintain an Emergency Preparedness Program (EP).Deficient, Provider has date of correction (January 4, 2021)
E-0006Conduct risk assessment and an All-Hazards approach.Deficient, Provider has date of correction (January 4, 2021)
E-0030List the names and contact information of those in the facility.Deficient, Provider has date of correction (January 4, 2021)
E-0041Implement emergency and standby power systems.Deficient, Provider has date of correction (January 4, 2021)
K-0271Have exits that are accessible at all times.Deficient, Provider has date of correction (January 4, 2021)
K-0291Install emergency lighting that can last at least 1 1/2 hours.Deficient, Provider has date of correction (January 4, 2021)
K-0321Ensure that special areas are constructed so that walls can resist fire for one hour or have an approved fire extinguishing system.Deficient, Provider has date of correction (January 4, 2021)
K-0353Inspect, test, and maintain automatic sprinkler systems.Deficient, Provider has date of correction (January 4, 2021)
K-0372Ensure smoke barriers are constructed to a 1 hour fire resistance rating.Deficient, Provider has date of correction (January 4, 2021)
K-0511Have properly installed electrical wiring and gas equipment.Deficient, Provider has date of correction (January 4, 2021)
K-0923Have proper medical gas storage and administration areas.Deficient, Provider has date of correction (January 4, 2021)

November 21, 2018 — 6 citations

Citations issued on November 21, 2018
TagWhat the surveyor checksStatus
K-0353Inspect, test, and maintain automatic sprinkler systems.Deficient, Provider has date of correction (January 22, 2019)
K-0511Have properly installed electrical wiring and gas equipment.Deficient, Provider has date of correction (January 22, 2019)
K-0712Have simulated fire drills held at unexpected times.Deficient, Provider has date of correction (January 22, 2019)
K-0901Ensure that building systems meet requirements determined by risk assessment procedures performed by qualified personnel.Deficient, Provider has date of correction (January 22, 2019)
K-0914Ensure receptacles at patient bed locations and where general anesthesia is administered, are tested after initial installation, replacement or servicing.Deficient, Provider has date of correction (January 22, 2019)
K-0921Ensure that testing and maintenance of electrical equipment is performed.Deficient, Provider has date of correction (January 22, 2019)