Federal nursing home survey record · CMS-certified nursing home· Not a state assisted-living licensing record

VERRAZANO NURSING AND POST-ACUTE CENTER

STATEN ISLAND, NY · 120 certified beds · Last Life Safety survey March 19, 2025

CMS Certification Number 335273 · first certified January 1970

Ownership

Independently operated (no chain recorded by CMS) · For profit - Corporation

No change of ownership on CMS record since January 1, 2016, when the records begin.

10
Citations on file
Rolling three-year window
3
Life Safety surveys
In the same window
1
Tags cited more than once
Across separate surveys
4
Inspection & testing records
Of the citations on file

Position within NY

10 citations — more than 29% of the 593 certified nursing homes in NY. Compared within NY rather than nationally because which state a facility is in explains about 30% of the variation in citation counts between facilities, while bed count explains under 1%. State survey agencies differ far more than the buildings do. How this is calculated

Improvingfewer citations at the latest survey than at its earlier surveys in the window.

The latest survey found 3 citations; the earlier surveys in the window averaged 3.5. With 3 surveys on file this is a direction of travel, not a conclusion.

When is the next survey likely?

The window is open now: September 2026 to May 2027. This facility’s last Life Safety survey was March 2025. Facilities in NY are typically surveyed 18–25 months after the last one (median 22), measured over 523 consecutive surveys in the last two years of CMS records.

A range the record supports, not a prediction of a date. State agencies vary widely — from about 11 months in Pennsylvania to three years in Maryland. How the window is measured

Get an email about VERRAZANO NURSING AND POST-ACUTE CENTER

One email when it happens. No account; stop it any time with one click.

Which alerts

Emergency preparedness

1 of the 10 citations on file is Emergency Preparedness E-tags. E-tags are cited under 42 CFR §483.73 and concern the emergency plan, training, drills, communications and supplies. Nationally about half of certified facilities have at least one. The Emergency Preparedness Index

How that compares

Citations on file over three years

Compared with the median facility in NY, and nationally. Surveyors differ markedly between states, so the NY figure is the meaningful one.

This facility10NY median13National median11
Citations on file over three years, compared
MeasureCitations
This facility10
Median facility in NY13
Median facility nationally11

Survey history

Citations at each Life Safety survey
02020-0172023-0132025-03
Citations at each Life Safety survey
Survey dateCitations
January 13, 20200
January 30, 20237
March 19, 20253

Most-cited tags

Most-cited tags at this facility
K-03512K-03741K-03251E-00011K-03721K-03451K-02111K-09181
Most-cited tags at this facility
TagWhat the surveyor checksTimes citedLast cited
K-0351Install an approved automatic sprinkler system.22025-03-19
K-0374Install smoke barrier doors that can resist smoke for at least 20 minutes.12023-01-30
K-0325Have properly installed hallway dispensers for alcohol-based hand rub.12025-03-19
E-0001Establish an Emergency Preparedness Program (EP).12023-01-30
K-0372Ensure smoke barriers are constructed to a 1 hour fire resistance rating.12023-01-30
K-0345Have approved installation, maintenance and testing program for fire alarm systems.12023-01-30
K-0211Keep aisles, corridors, and exits free of obstruction in case of emergency.12025-03-19
K-0918Have generator or other power source capable of supplying service within 10 seconds.12023-01-30

What the citations cover

Citations by CMS category
  • Smoke Deficiencies 7
  • Emergency Preparedness Deficiencies 1
  • Egress Deficiencies 1
  • Gas, Vacuum, and Electrical Systems Deficiencies 1
Citations by CMS category
CategoryCitations
Smoke Deficiencies7
Emergency Preparedness Deficiencies1
Egress Deficiencies1
Gas, Vacuum, and Electrical Systems Deficiencies1

Every citation on file

As published by CMS, newest survey first. Descriptions are CMS’s own wording.

March 19, 2025 — 3 citations

Citations issued on March 19, 2025
TagWhat the surveyor checksStatus
K-0211Keep aisles, corridors, and exits free of obstruction in case of emergency.Deficient, Provider has date of correction (April 25, 2025)
K-0325Have properly installed hallway dispensers for alcohol-based hand rub.Deficient, Provider has date of correction (April 25, 2025)
K-0351Install an approved automatic sprinkler system.Deficient, Provider has date of correction (April 25, 2025)

January 30, 2023 — 7 citations

Citations issued on January 30, 2023
TagWhat the surveyor checksStatus
E-0001Establish an Emergency Preparedness Program (EP).Deficient, Provider has date of correction (April 2, 2023)
K-0345Have approved installation, maintenance and testing program for fire alarm systems.Deficient, Provider has date of correction (April 2, 2023)
K-0351Install an approved automatic sprinkler system.Deficient, Provider has date of correction (April 2, 2023)
K-0353Inspect, test, and maintain automatic sprinkler systems.Deficient, Provider has date of correction (April 2, 2023)
K-0372Ensure smoke barriers are constructed to a 1 hour fire resistance rating.Deficient, Provider has date of correction (April 2, 2023)
K-0374Install smoke barrier doors that can resist smoke for at least 20 minutes.Deficient, Provider has date of correction (April 2, 2023)
K-0918Have generator or other power source capable of supplying service within 10 seconds.Deficient, Provider has date of correction (April 2, 2023)

Reflects the CMS posting of August 1, 2026. Surveys conducted in the last few months may not appear yet.