Federal nursing home survey record · CMS-certified nursing home· Not a state assisted-living licensing record

CHRISTIAN CARE CENTER OF UNICOI COUNTY

ERWIN, TN · 50 certified beds · Last Life Safety survey April 15, 2026

CMS Certification Number 445077 · first certified September 1969

Ownership

Independently operated (no chain recorded by CMS) · For profit - Limited Liability company

  • Ownership changed January 1, 2019 (change of ownership)from MOUNTAIN STATES HEALTH ALLIANCE
3
Citations on file
Rolling three-year window
3
Life Safety surveys
In the same window
0
Tags cited more than once
Across separate surveys
2
Inspection & testing records
Of the citations on file

Position within TN

3 citations — more than 13% of the 303 certified nursing homes in TN. Compared within TN rather than nationally because which state a facility is in explains about 30% of the variation in citation counts between facilities, while bed count explains under 1%. State survey agencies differ far more than the buildings do. How this is calculated

Slippingmore citations at the latest survey than at its earlier surveys in the window.

The latest survey found 2 citations; the earlier surveys in the window averaged 0.5. With 3 surveys on file this is a direction of travel, not a conclusion.

When is the next survey likely?

The window opens July 2027 — about 9 months from now. This facility’s last Life Safety survey was April 2026. Facilities in TN are typically surveyed 15–44 months after the last one (median 33), measured over 279 consecutive surveys in the last two years of CMS records.

A range the record supports, not a prediction of a date. State agencies vary widely — from about 11 months in Pennsylvania to three years in Maryland. How the window is measured

Get an email about CHRISTIAN CARE CENTER OF UNICOI COUNTY

One email when it happens. No account; stop it any time with one click.

Which alerts

Physical environment (health survey)

2 physical-environment citations on the health survey. Cited by the health surveyors under Appendix PP, not the Life Safety Code surveyor: equipment in safe operating condition, the call system, bed rails, pest control, hazards, the environment. Counted separately from the 3 Life Safety citations above. The Physical Environment Index

  • F-0584 Honor the resident's right to a safe, clean, comfortable and homelike environment, including but not limited to receiving treatment and supports for daily living safely.
  • F-0880 Provide and implement an infection prevention and control program.

How that compares

Citations on file over three years

Compared with the median facility in TN, and nationally. Surveyors differ markedly between states, so the TN figure is the meaningful one.

This facility3TN median8National median11
Citations on file over three years, compared
MeasureCitations
This facility3
Median facility in TN8
Median facility nationally11

Survey history

Citations at each Life Safety survey
02021-0812023-0822026-04
Citations at each Life Safety survey
Survey dateCitations
August 31, 20210
August 30, 20231
April 15, 20262

Most-cited tags

Most-cited tags at this facility
K-05111K-03631K-07111
Most-cited tags at this facility
TagWhat the surveyor checksTimes citedLast cited
K-0511Have properly installed electrical wiring and gas equipment.12026-04-15
K-0363Install corridor and hallway doors that block smoke.12026-04-15
K-0711Provide a written emergency evacuation plan.12023-08-30

What the citations cover

Citations by CMS category
  • Services Deficiencies 1
  • Miscellaneous Deficiencies 1
  • Smoke Deficiencies 1
Citations by CMS category
CategoryCitations
Services Deficiencies1
Miscellaneous Deficiencies1
Smoke Deficiencies1

Every citation on file

As published by CMS, newest survey first. Descriptions are CMS’s own wording.

April 15, 2026 — 2 citations

Citations issued on April 15, 2026
TagWhat the surveyor checksStatus
K-0363Install corridor and hallway doors that block smoke.Deficient, Provider has date of correction (April 22, 2026)
K-0511Have properly installed electrical wiring and gas equipment.Deficient, Provider has date of correction (April 22, 2026)

August 30, 2023 — 1 citation

Citations issued on August 30, 2023
TagWhat the surveyor checksStatus
K-0711Provide a written emergency evacuation plan.Deficient, Provider has date of correction (August 29, 2023)

Reflects the CMS posting of August 1, 2026. Surveys conducted in the last few months may not appear yet.