Federal nursing home survey record · CMS-certified nursing home· Not a state assisted-living licensing record

Uintah Health Care Special Service District

Vernal, UT · 110 certified beds · Last Life Safety survey September 25, 2025

CMS Certification Number 465092 · first certified February 1984

Ownership

Independently operated (no chain recorded by CMS) · Government - County

No change of ownership on CMS record since January 1, 2016, when the records begin.

13
Citations on file
Rolling three-year window
3
Life Safety surveys
In the same window
1
Tags cited more than once
Across separate surveys
6
Inspection & testing records
Of the citations on file

Position within UT

13 citations — more than 80% of the 97 certified nursing homes in UT. Compared within UT rather than nationally because which state a facility is in explains about 30% of the variation in citation counts between facilities, while bed count explains under 1%. State survey agencies differ far more than the buildings do. How this is calculated

Improvingfewer citations at the latest survey than at its earlier surveys in the window.

The latest survey found 2 citations; the earlier surveys in the window averaged 5.5. With 3 surveys on file this is a direction of travel, not a conclusion.

When is the next survey likely?

The window opens April 2027 — about 7 months from now. This facility’s last Life Safety survey was September 2025. Facilities in UT are typically surveyed 19–24 months after the last one (median 21), measured over 88 consecutive surveys in the last two years of CMS records.

A range the record supports, not a prediction of a date. State agencies vary widely — from about 11 months in Pennsylvania to three years in Maryland. How the window is measured

Get an email about Uintah Health Care Special Service District

One email when it happens. No account; stop it any time with one click.

Which alerts

1 inspection-and-testing tag has been cited here at more than one survey. Nationally, that pattern is common: about three quarters of cited facilities have at least one repeated tag, and half of the facilities ever cited for sprinkler inspection and testing are cited for it again. A repeat is usually a recordkeeping gap rather than a new hazard.

Physical environment (health survey)

2 physical-environment citations on the health survey. Cited by the health surveyors under Appendix PP, not the Life Safety Code surveyor: equipment in safe operating condition, the call system, bed rails, pest control, hazards, the environment. Counted separately from the 13 Life Safety citations above. The Physical Environment Index

  • F-0880 Provide and implement an infection prevention and control program.

How that compares

Citations on file over three years

Compared with the median facility in UT, and nationally. Surveyors differ markedly between states, so the UT figure is the meaningful one.

This facility13UT median3National median11
Citations on file over three years, compared
MeasureCitations
This facility13
Median facility in UT3
Median facility nationally11

Survey history

Citations at each Life Safety survey
62022-0252023-0922025-09
Citations at each Life Safety survey
Survey dateCitations
February 9, 20226
September 14, 20235
September 25, 20252

Most-cited tags

Most-cited tags at this facility
K-05112K-01001K-02001K-03451K-09211K-09141K-03531K-02221
Most-cited tags at this facility
TagWhat the surveyor checksTimes citedLast cited
K-0511Have properly installed electrical wiring and gas equipment.22023-09-14
K-0100Meet other general requirements.12022-02-09
K-0200Meet other general requirements.12023-09-14
K-0345Have approved installation, maintenance and testing program for fire alarm systems.12022-02-09
K-0921Ensure that testing and maintenance of electrical equipment is performed.12025-09-25
K-0914Ensure receptacles at patient bed locations and where general anesthesia is administered, are tested after initial installation, replacement or servicing.12022-02-09
K-0353Inspect, test, and maintain automatic sprinkler systems.12022-02-09
K-0222Add doors in an exit area that do not require the use of a key from the exit side unless in case of special locking arrangements.12023-09-14

What the citations cover

Citations by CMS category
  • Smoke Deficiencies 4
  • Egress Deficiencies 3
  • Services Deficiencies 2
  • Gas, Vacuum, and Electrical Systems Deficiencies 2
  • Other 2
Citations by CMS category
CategoryCitations
Smoke Deficiencies4
Egress Deficiencies3
Services Deficiencies2
Gas, Vacuum, and Electrical Systems Deficiencies2
Construction Deficiencies1
Miscellaneous Deficiencies1

Every citation on file

As published by CMS, newest survey first. Descriptions are CMS’s own wording.

September 25, 2025 — 2 citations

Citations issued on September 25, 2025
TagWhat the surveyor checksStatus
K-0321Ensure that special areas are constructed so that walls can resist fire for one hour or have an approved fire extinguishing system.Deficient, Provider has date of correction (January 18, 2026)
K-0921Ensure that testing and maintenance of electrical equipment is performed.Deficient, Provider has date of correction (January 18, 2026)

September 14, 2023 — 5 citations

Citations issued on September 14, 2023
TagWhat the surveyor checksStatus
K-0200Meet other general requirements.Deficient, Provider has date of correction (September 26, 2023)
K-0222Add doors in an exit area that do not require the use of a key from the exit side unless in case of special locking arrangements.Deficient, Provider has date of correction (September 26, 2023)
K-0291Install emergency lighting that can last at least 1 1/2 hours.Deficient, Provider has date of correction (September 26, 2023)
K-0344Have an alternate power supply for its alarm system.Deficient, Provider has date of correction (October 25, 2023)
K-0511Have properly installed electrical wiring and gas equipment.Deficient, Provider has date of correction (October 7, 2023)

February 9, 2022 — 6 citations

Citations issued on February 9, 2022
TagWhat the surveyor checksStatus
K-0100Meet other general requirements.Deficient, Provider has date of correction (April 9, 2022)
K-0345Have approved installation, maintenance and testing program for fire alarm systems.Deficient, Provider has date of correction (March 2, 2022)
K-0353Inspect, test, and maintain automatic sprinkler systems.Deficient, Provider has date of correction (April 9, 2022)
K-0511Have properly installed electrical wiring and gas equipment.Deficient, Provider has date of correction (April 9, 2022)
K-0712Have simulated fire drills held at unexpected times.Deficient, Provider has date of correction (April 9, 2022)
K-0914Ensure receptacles at patient bed locations and where general anesthesia is administered, are tested after initial installation, replacement or servicing.Deficient, Provider has date of correction (April 9, 2022)

Reflects the CMS posting of August 1, 2026. Surveys conducted in the last few months may not appear yet.