Federal nursing home survey record · CMS-certified nursing home· Not a state assisted-living licensing record
Rennes Health and Rehab Center-West
Peshtigo, WI · 90 certified beds · Last Life Safety survey February 25, 2026
CMS Certification Number 525451 · first certified December 1989
Ownership
Operated by RENNES GROUP · For profit - Limited Liability company
No change of ownership on CMS record since January 1, 2016, when the records begin.
Position within WI
9 citations — more than 14% of the 323 certified nursing homes in WI. Compared within WI rather than nationally because which state a facility is in explains about 30% of the variation in citation counts between facilities, while bed count explains under 1%. State survey agencies differ far more than the buildings do. How this is calculated
The latest survey found 3 citations; the earlier surveys in the window averaged 3. With 3 surveys on file this is a direction of travel, not a conclusion.
When is the next survey likely?
The window opens April 2027 — about 6 months from now. This facility’s last Life Safety survey was February 2026. Facilities in WI are typically surveyed 13–15 months after the last one (median 14), measured over 516 consecutive surveys in the last two years of CMS records.
A range the record supports, not a prediction of a date. State agencies vary widely — from about 11 months in Pennsylvania to three years in Maryland. How the window is measured
Get an email about Rennes Health and Rehab Center-West
One email when it happens. No account; stop it any time with one click.
1 inspection-and-testing tag has been cited here at more than one survey. Nationally, that pattern is common: about three quarters of cited facilities have at least one repeated tag, and half of the facilities ever cited for sprinkler inspection and testing are cited for it again. A repeat is usually a recordkeeping gap rather than a new hazard.
How that compares
Compared with the median facility in WI, and nationally. Surveyors differ markedly between states, so the WI figure is the meaningful one.
| Measure | Citations |
|---|---|
| This facility | 9 |
| Median facility in WI | 17 |
| Median facility nationally | 11 |
Survey history
| Survey date | Citations |
|---|---|
| August 23, 2023 | 3 |
| October 2, 2024 | 3 |
| February 25, 2026 | 3 |
Most-cited tags
| Tag | What the surveyor checks | Times cited | Last cited |
|---|---|---|---|
| K-0372 | Ensure smoke barriers are constructed to a 1 hour fire resistance rating. | 2 | 2026-02-25 |
| K-0353 | Inspect, test, and maintain automatic sprinkler systems. | 1 | 2026-02-25 |
| K-0222 | Add doors in an exit area that do not require the use of a key from the exit side unless in case of special locking arrangements. | 1 | 2023-08-23 |
| K-0911 | Meet requirements for the installation and maintenance of electrical systems. | 1 | 2023-08-23 |
| K-0919 | Meet requirements for the use of electrical equipment. | 1 | 2023-08-23 |
| K-0912 | Have power receptacles that are properly grounded. | 1 | 2026-02-25 |
| K-0161 | Use approved construction type or materials. | 1 | 2024-10-02 |
| K-0324 | Provide properly protected cooking facilities. | 1 | 2024-10-02 |
What the citations cover
- Smoke Deficiencies 4
- Gas, Vacuum, and Electrical Systems Deficiencies 3
- Construction Deficiencies 1
- Egress Deficiencies 1
| Category | Citations |
|---|---|
| Smoke Deficiencies | 4 |
| Gas, Vacuum, and Electrical Systems Deficiencies | 3 |
| Construction Deficiencies | 1 |
| Egress Deficiencies | 1 |
Every citation on file
As published by CMS, newest survey first. Descriptions are CMS’s own wording.
February 25, 2026 — 3 citations
| Tag | What the surveyor checks | Status |
|---|---|---|
| K-0353 | Inspect, test, and maintain automatic sprinkler systems. | Deficient, Provider has date of correction (March 26, 2026) |
| K-0372 | Ensure smoke barriers are constructed to a 1 hour fire resistance rating. | Deficient, Provider has date of correction (March 26, 2026) |
| K-0912 | Have power receptacles that are properly grounded. | Deficient, Provider has date of correction (March 26, 2026) |
October 2, 2024 — 3 citations
| Tag | What the surveyor checks | Status |
|---|---|---|
| K-0161 | Use approved construction type or materials. | Deficient, Provider has date of correction (November 1, 2024) |
| K-0324 | Provide properly protected cooking facilities. | Deficient, Provider has date of correction (November 1, 2024) |
| K-0372 | Ensure smoke barriers are constructed to a 1 hour fire resistance rating. | Deficient, Provider has date of correction (November 1, 2024) |
August 23, 2023 — 3 citations
| Tag | What the surveyor checks | Status |
|---|---|---|
| K-0222 | Add doors in an exit area that do not require the use of a key from the exit side unless in case of special locking arrangements. | Deficient, Provider has date of correction (August 25, 2023) |
| K-0911 | Meet requirements for the installation and maintenance of electrical systems. | Deficient, Provider has date of correction (August 22, 2023) |
| K-0919 | Meet requirements for the use of electrical equipment. | Deficient, Provider has date of correction (August 25, 2023) |
Reflects the CMS posting of August 1, 2026. Surveys conducted in the last few months may not appear yet.