Federal nursing home survey record · CMS-certified nursing home· Not a state assisted-living licensing record
CLAY COUNTY NURSING HOME
ASHLAND, AL · 83 certified beds · Last Life Safety survey March 16, 2022
CMS Certification Number 015124 · first certified December 1974
Ownership
Independently operated (no chain recorded by CMS) · Non profit - Other
No change of ownership on CMS record since January 1, 2016, when the records begin.
Position within AL
5 citations — more than 16% of the 224 certified nursing homes in AL. Compared within AL rather than nationally because which state a facility is in explains about 30% of the variation in citation counts between facilities, while bed count explains under 1%. State survey agencies differ far more than the buildings do. How this is calculated
The latest survey found 0 citations; the earlier surveys in the window averaged 2.5. With 3 surveys on file this is a direction of travel, not a conclusion.
When is the next survey likely?
Well past the typical window (March 2023 to August 2023), and past the point by which nine in ten US facilities have been surveyed. This facility’s last Life Safety survey was March 2022. Nursing homes nationally are typically surveyed 12–17 months after the last one (median 14), measured over 19,385 consecutive surveys in the last two years of CMS records. AL has too few recent surveys to measure on its own, so the national interval is used.
A range the record supports, not a prediction of a date. State agencies vary widely — from about 11 months in Pennsylvania to three years in Maryland. How the window is measured
Get an email about CLAY COUNTY NURSING HOME
One email when it happens. No account; stop it any time with one click.
Physical environment (health survey)
2 physical-environment citations on the health survey. Cited by the health surveyors under Appendix PP, not the Life Safety Code surveyor: equipment in safe operating condition, the call system, bed rails, pest control, hazards, the environment. Counted separately from the 5 Life Safety citations above. The Physical Environment Index
How that compares
Compared with the median facility in AL, and nationally. Surveyors differ markedly between states, so the AL figure is the meaningful one.
| Measure | Citations |
|---|---|
| This facility | 5 |
| Median facility in AL | 9 |
| Median facility nationally | 11 |
Survey history
| Survey date | Citations |
|---|---|
| June 21, 2018 | 2 |
| May 16, 2019 | 3 |
| March 16, 2022 | 0 |
Most-cited tags
| Tag | What the surveyor checks | Times cited | Last cited |
|---|---|---|---|
| K-0363 | Install corridor and hallway doors that block smoke. | 1 | 2018-06-21 |
| K-0232 | Have corridors or aisles that are unobstructed and are at least 8 feet in width. | 1 | 2019-05-16 |
| K-0711 | Provide a written emergency evacuation plan. | 1 | 2019-05-16 |
| K-0345 | Have approved installation, maintenance and testing program for fire alarm systems. | 1 | 2018-06-21 |
| K-0929 | Ensure precautions for handling oxygen cylinders and equipment are correctly followed. | 1 | 2019-05-16 |
What the citations cover
- Smoke Deficiencies 2
- Miscellaneous Deficiencies 1
- Gas, Vacuum, and Electrical Systems Deficiencies 1
- Egress Deficiencies 1
| Category | Citations |
|---|---|
| Smoke Deficiencies | 2 |
| Miscellaneous Deficiencies | 1 |
| Gas, Vacuum, and Electrical Systems Deficiencies | 1 |
| Egress Deficiencies | 1 |
Every citation on file
As published by CMS, newest survey first. Descriptions are CMS’s own wording.
May 16, 2019 — 3 citations
| Tag | What the surveyor checks | Status |
|---|---|---|
| K-0232 | Have corridors or aisles that are unobstructed and are at least 8 feet in width. | Deficient, Provider has date of correction (May 17, 2019) |
| K-0711 | Provide a written emergency evacuation plan. | Deficient, Provider has date of correction (June 20, 2019) |
| K-0929 | Ensure precautions for handling oxygen cylinders and equipment are correctly followed. | Deficient, Provider has date of correction (June 20, 2019) |
June 21, 2018 — 2 citations
| Tag | What the surveyor checks | Status |
|---|---|---|
| K-0345 | Have approved installation, maintenance and testing program for fire alarm systems. | Deficient, Provider has date of correction (July 13, 2018) |
| K-0363 | Install corridor and hallway doors that block smoke. | Deficient, Provider has date of correction (June 27, 2018) |
Reflects the CMS posting of August 1, 2026. Surveys conducted in the last few months may not appear yet.