Federal nursing home survey record · CMS-certified nursing home· Not a state assisted-living licensing record
CENTER AT LOWRY, LLC
DENVER, CO · 96 certified beds · Last Life Safety survey April 2, 2026
CMS Certification Number 065419 · first certified October 2016
Ownership
Independently operated (no chain recorded by CMS) · For profit - Limited Liability company
No change of ownership on CMS record since January 1, 2016, when the records begin.
Position within CO
19 citations — more than 58% of the 210 certified nursing homes in CO. Compared within CO rather than nationally because which state a facility is in explains about 30% of the variation in citation counts between facilities, while bed count explains under 1%. State survey agencies differ far more than the buildings do. How this is calculated
The latest survey found 6 citations; the earlier surveys in the window averaged 6.5. With 3 surveys on file this is a direction of travel, not a conclusion.
When is the next survey likely?
The window opens September 2027 — about 11 months from now. This facility’s last Life Safety survey was April 2026. Facilities in CO are typically surveyed 17–24 months after the last one (median 19), measured over 177 consecutive surveys in the last two years of CMS records.
A range the record supports, not a prediction of a date. State agencies vary widely — from about 11 months in Pennsylvania to three years in Maryland. How the window is measured
Get an email about CENTER AT LOWRY, LLC
One email when it happens. No account; stop it any time with one click.
5 inspection-and-testing tags have been cited here at more than one survey. Nationally, that pattern is common: about three quarters of cited facilities have at least one repeated tag, and half of the facilities ever cited for sprinkler inspection and testing are cited for it again. A repeat is usually a recordkeeping gap rather than a new hazard.
Physical environment (health survey)
2 physical-environment citations on the health survey. Cited by the health surveyors under Appendix PP, not the Life Safety Code surveyor: equipment in safe operating condition, the call system, bed rails, pest control, hazards, the environment. Counted separately from the 19 Life Safety citations above. The Physical Environment Index
How that compares
Compared with the median facility in CO, and nationally. Surveyors differ markedly between states, so the CO figure is the meaningful one.
| Measure | Citations |
|---|---|
| This facility | 19 |
| Median facility in CO | 16 |
| Median facility nationally | 11 |
Survey history
| Survey date | Citations |
|---|---|
| October 27, 2022 | 6 |
| February 23, 2024 | 7 |
| April 2, 2026 | 6 |
Most-cited tags
| Tag | What the surveyor checks | Times cited | Last cited |
|---|---|---|---|
| K-0521 | Ensure heating and ventilation systems that have been properly installed according to the manufacturer's instructions. | 3 | 2026-04-02 |
| K-0353 | Inspect, test, and maintain automatic sprinkler systems. | 3 | 2026-04-02 |
| K-0321 | Ensure that special areas are constructed so that walls can resist fire for one hour or have an approved fire extinguishing system. | 2 | 2024-02-23 |
| K-0345 | Have approved installation, maintenance and testing program for fire alarm systems. | 2 | 2026-04-02 |
| K-0918 | Have generator or other power source capable of supplying service within 10 seconds. | 2 | 2026-04-02 |
| K-0324 | Provide properly protected cooking facilities. | 2 | 2026-04-02 |
| K-0712 | Have simulated fire drills held at unexpected times. | 1 | 2022-10-27 |
| K-0914 | Ensure receptacles at patient bed locations and where general anesthesia is administered, are tested after initial installation, replacement or servicing. | 1 | 2024-02-23 |
What the citations cover
- Smoke Deficiencies 11
- Gas, Vacuum, and Electrical Systems Deficiencies 3
- Services Deficiencies 3
- Miscellaneous Deficiencies 1
- Other 1
| Category | Citations |
|---|---|
| Smoke Deficiencies | 11 |
| Gas, Vacuum, and Electrical Systems Deficiencies | 3 |
| Services Deficiencies | 3 |
| Miscellaneous Deficiencies | 1 |
| Egress Deficiencies | 1 |
Every citation on file
As published by CMS, newest survey first. Descriptions are CMS’s own wording.
April 2, 2026 — 6 citations
| Tag | What the surveyor checks | Status |
|---|---|---|
| K-0324 | Provide properly protected cooking facilities. | Deficient, Provider has plan of correction (June 1, 2026) |
| K-0345 | Have approved installation, maintenance and testing program for fire alarm systems. | Deficient, Provider has plan of correction (July 10, 2026) |
| K-0353 | Inspect, test, and maintain automatic sprinkler systems. | Deficient, Provider has plan of correction (June 1, 2026) |
| K-0374 | Install smoke barrier doors that can resist smoke for at least 20 minutes. | Deficient, Provider has plan of correction (February 1, 2027) |
| K-0521 | Ensure heating and ventilation systems that have been properly installed according to the manufacturer's instructions. | Deficient, Provider has plan of correction (June 30, 2026) |
| K-0918 | Have generator or other power source capable of supplying service within 10 seconds. | Deficient, Provider has plan of correction (June 1, 2026) |
February 23, 2024 — 7 citations
| Tag | What the surveyor checks | Status |
|---|---|---|
| K-0291 | Install emergency lighting that can last at least 1 1/2 hours. | Deficient, Provider has date of correction (March 15, 2024) |
| K-0321 | Ensure that special areas are constructed so that walls can resist fire for one hour or have an approved fire extinguishing system. | Deficient, Provider has date of correction (March 15, 2024) |
| K-0345 | Have approved installation, maintenance and testing program for fire alarm systems. | Waiver has been granted (March 18, 2024) |
| K-0353 | Inspect, test, and maintain automatic sprinkler systems. | Deficient, Provider has date of correction (March 23, 2024) |
| K-0521 | Ensure heating and ventilation systems that have been properly installed according to the manufacturer's instructions. | Waiver has been granted (April 5, 2024) |
| K-0914 | Ensure receptacles at patient bed locations and where general anesthesia is administered, are tested after initial installation, replacement or servicing. | Deficient, Provider has date of correction (March 18, 2024) |
| K-0918 | Have generator or other power source capable of supplying service within 10 seconds. | Deficient, Provider has date of correction (March 18, 2024) |
October 27, 2022 — 6 citations
| Tag | What the surveyor checks | Status |
|---|---|---|
| K-0321 | Ensure that special areas are constructed so that walls can resist fire for one hour or have an approved fire extinguishing system. | Deficient, Provider has date of correction (November 29, 2022) |
| K-0324 | Provide properly protected cooking facilities. | Deficient, Provider has date of correction (December 6, 2022) |
| K-0353 | Inspect, test, and maintain automatic sprinkler systems. | Deficient, Provider has date of correction (January 25, 2023) |
| K-0355 | Properly select, install, inspect, or maintain portable fire extinguishes. | Deficient, Provider has date of correction (November 29, 2022) |
| K-0521 | Ensure heating and ventilation systems that have been properly installed according to the manufacturer's instructions. | Deficient, Provider has date of correction (January 6, 2023) |
| K-0712 | Have simulated fire drills held at unexpected times. | Deficient, Provider has date of correction (December 27, 2022) |
Reflects the CMS posting of August 1, 2026. Surveys conducted in the last few months may not appear yet.