Federal nursing home survey record · CMS-certified nursing home· Not a state assisted-living licensing record
GREEN HOUSE HOMES AT MIRASOL, THE
LOVELAND, CO · 90 certified beds · Last Life Safety survey March 12, 2025
CMS Certification Number 065412 · first certified January 2015
Ownership
Independently operated (no chain recorded by CMS) · For profit - Limited Liability company
No change of ownership on CMS record since January 1, 2016, when the records begin.
Position within CO
14 citations — more than 39% of the 210 certified nursing homes in CO. Compared within CO rather than nationally because which state a facility is in explains about 30% of the variation in citation counts between facilities, while bed count explains under 1%. State survey agencies differ far more than the buildings do. How this is calculated
The latest survey found 11 citations; the earlier surveys in the window averaged 1.5. With 3 surveys on file this is a direction of travel, not a conclusion.
When is the next survey likely?
The window is open now: August 2026 to March 2027. This facility’s last Life Safety survey was March 2025. Facilities in CO are typically surveyed 17–24 months after the last one (median 19), measured over 177 consecutive surveys in the last two years of CMS records.
A range the record supports, not a prediction of a date. State agencies vary widely — from about 11 months in Pennsylvania to three years in Maryland. How the window is measured
Get an email about GREEN HOUSE HOMES AT MIRASOL, THE
One email when it happens. No account; stop it any time with one click.
1 inspection-and-testing tag has been cited here at more than one survey. Nationally, that pattern is common: about three quarters of cited facilities have at least one repeated tag, and half of the facilities ever cited for sprinkler inspection and testing are cited for it again. A repeat is usually a recordkeeping gap rather than a new hazard.
Emergency preparedness
1 of the 14 citations on file is Emergency Preparedness E-tags. E-tags are cited under 42 CFR §483.73 and concern the emergency plan, training, drills, communications and supplies. Nationally about half of certified facilities have at least one. The Emergency Preparedness Index
Physical environment (health survey)
4 physical-environment citations on the health survey. Cited by the health surveyors under Appendix PP, not the Life Safety Code surveyor: equipment in safe operating condition, the call system, bed rails, pest control, hazards, the environment. Counted separately from the 14 Life Safety citations above. The Physical Environment Index
How that compares
Compared with the median facility in CO, and nationally. Surveyors differ markedly between states, so the CO figure is the meaningful one.
| Measure | Citations |
|---|---|
| This facility | 14 |
| Median facility in CO | 16 |
| Median facility nationally | 11 |
Survey history
| Survey date | Citations |
|---|---|
| September 11, 2019 | 3 |
| August 31, 2023 | 0 |
| March 12, 2025 | 11 |
Most-cited tags
| Tag | What the surveyor checks | Times cited | Last cited |
|---|---|---|---|
| K-0353 | Inspect, test, and maintain automatic sprinkler systems. | 2 | 2025-03-12 |
| K-0914 | Ensure receptacles at patient bed locations and where general anesthesia is administered, are tested after initial installation, replacement or servicing. | 1 | 2025-03-12 |
| K-0222 | Add doors in an exit area that do not require the use of a key from the exit side unless in case of special locking arrangements. | 1 | 2025-03-12 |
| K-0911 | Meet requirements for the installation and maintenance of electrical systems. | 1 | 2019-09-11 |
| K-0363 | Install corridor and hallway doors that block smoke. | 1 | 2019-09-11 |
| K-0324 | Provide properly protected cooking facilities. | 1 | 2025-03-12 |
| K-0521 | Ensure heating and ventilation systems that have been properly installed according to the manufacturer's instructions. | 1 | 2025-03-12 |
| K-0927 | Have proper fire barriers, ventilation and signs for the transfilling of oxygen. | 1 | 2025-03-12 |
What the citations cover
- Smoke Deficiencies 5
- Gas, Vacuum, and Electrical Systems Deficiencies 3
- Egress Deficiencies 2
- Miscellaneous Deficiencies 2
- Other 2
| Category | Citations |
|---|---|
| Smoke Deficiencies | 5 |
| Gas, Vacuum, and Electrical Systems Deficiencies | 3 |
| Egress Deficiencies | 2 |
| Miscellaneous Deficiencies | 2 |
| Emergency Preparedness Deficiencies | 1 |
| Services Deficiencies | 1 |
Every citation on file
As published by CMS, newest survey first. Descriptions are CMS’s own wording.
March 12, 2025 — 11 citations
| Tag | What the surveyor checks | Status |
|---|---|---|
| E-0039 | Conduct testing and exercise requirements. | Deficient, Provider has date of correction (April 4, 2025) |
| K-0222 | Add doors in an exit area that do not require the use of a key from the exit side unless in case of special locking arrangements. | Deficient, Provider has date of correction (April 28, 2025) |
| K-0300 | Meet other general requirements that are deficient. | Deficient, Provider has date of correction (June 1, 2025) |
| K-0324 | Provide properly protected cooking facilities. | Deficient, Provider has date of correction (June 6, 2025) |
| K-0343 | Have a fire alarm with audible and visual signals that transmits the alarm automatically to notify emergency forces in event of fire. | Deficient, Provider has date of correction (April 28, 2025) |
| K-0353 | Inspect, test, and maintain automatic sprinkler systems. | Deficient, Provider has date of correction (June 1, 2025) |
| K-0521 | Ensure heating and ventilation systems that have been properly installed according to the manufacturer's instructions. | Deficient, Provider has date of correction (June 1, 2025) |
| K-0711 | Provide a written emergency evacuation plan. | Deficient, Provider has date of correction (May 15, 2025) |
| K-0712 | Have simulated fire drills held at unexpected times. | Deficient, Provider has date of correction (April 28, 2025) |
| K-0914 | Ensure receptacles at patient bed locations and where general anesthesia is administered, are tested after initial installation, replacement or servicing. | Deficient, Provider has date of correction (April 28, 2025) |
| K-0927 | Have proper fire barriers, ventilation and signs for the transfilling of oxygen. | Deficient, Provider has date of correction (April 28, 2025) |
September 11, 2019 — 3 citations
| Tag | What the surveyor checks | Status |
|---|---|---|
| K-0353 | Inspect, test, and maintain automatic sprinkler systems. | Deficient, Provider has date of correction (October 2, 2019) |
| K-0363 | Install corridor and hallway doors that block smoke. | Deficient, Provider has date of correction (October 2, 2019) |
| K-0911 | Meet requirements for the installation and maintenance of electrical systems. | Deficient, Provider has date of correction (October 2, 2019) |
Reflects the CMS posting of August 1, 2026. Surveys conducted in the last few months may not appear yet.