Federal nursing home survey record · CMS-certified nursing home· Not a state assisted-living licensing record
MATULAITIS REHABILITATION & SKILLED CARE
PUTNAM, CT · 119 certified beds · Last Life Safety survey December 19, 2024
CMS Certification Number 075411 · first certified February 1996
Ownership
Independently operated (no chain recorded by CMS) · Non profit - Corporation
No change of ownership on CMS record since January 1, 2016, when the records begin.
Position within CT
5 citations — more than 25% of the 191 certified nursing homes in CT. Compared within CT rather than nationally because which state a facility is in explains about 30% of the variation in citation counts between facilities, while bed count explains under 1%. State survey agencies differ far more than the buildings do. How this is calculated
The latest survey found 4 citations; the earlier surveys in the window averaged 0.5. With 3 surveys on file this is a direction of travel, not a conclusion.
When is the next survey likely?
The window opens October 2026. This facility’s last Life Safety survey was December 2024. Facilities in CT are typically surveyed 21–28 months after the last one (median 24), measured over 181 consecutive surveys in the last two years of CMS records.
A range the record supports, not a prediction of a date. State agencies vary widely — from about 11 months in Pennsylvania to three years in Maryland. How the window is measured
Get an email about MATULAITIS REHABILITATION & SKILLED CARE
One email when it happens. No account; stop it any time with one click.
Physical environment (health survey)
4 physical-environment citations on the health survey. Cited by the health surveyors under Appendix PP, not the Life Safety Code surveyor: equipment in safe operating condition, the call system, bed rails, pest control, hazards, the environment. Counted separately from the 5 Life Safety citations above. The Physical Environment Index
- F-0689 Ensure that a nursing home area is free from accident hazards and provides adequate supervision to prevent accidents.
- F-0584 Honor the resident's right to a safe, clean, comfortable and homelike environment, including but not limited to receiving treatment and supports for daily living safely.
How that compares
Compared with the median facility in CT, and nationally. Surveyors differ markedly between states, so the CT figure is the meaningful one.
| Measure | Citations |
|---|---|
| This facility | 5 |
| Median facility in CT | 10 |
| Median facility nationally | 11 |
Survey history
| Survey date | Citations |
|---|---|
| August 8, 2019 | 0 |
| March 1, 2022 | 1 |
| December 19, 2024 | 4 |
Most-cited tags
| Tag | What the surveyor checks | Times cited | Last cited |
|---|---|---|---|
| K-0345 | Have approved installation, maintenance and testing program for fire alarm systems. | 1 | 2024-12-19 |
| K-0712 | Have simulated fire drills held at unexpected times. | 1 | 2022-03-01 |
| K-0914 | Ensure receptacles at patient bed locations and where general anesthesia is administered, are tested after initial installation, replacement or servicing. | 1 | 2024-12-19 |
| K-0911 | Meet requirements for the installation and maintenance of electrical systems. | 1 | 2024-12-19 |
| K-0372 | Ensure smoke barriers are constructed to a 1 hour fire resistance rating. | 1 | 2024-12-19 |
What the citations cover
- Smoke Deficiencies 2
- Gas, Vacuum, and Electrical Systems Deficiencies 2
- Miscellaneous Deficiencies 1
| Category | Citations |
|---|---|
| Smoke Deficiencies | 2 |
| Gas, Vacuum, and Electrical Systems Deficiencies | 2 |
| Miscellaneous Deficiencies | 1 |
Every citation on file
As published by CMS, newest survey first. Descriptions are CMS’s own wording.
December 19, 2024 — 4 citations
| Tag | What the surveyor checks | Status |
|---|---|---|
| K-0345 | Have approved installation, maintenance and testing program for fire alarm systems. | Deficient, Provider has date of correction (December 20, 2024) |
| K-0372 | Ensure smoke barriers are constructed to a 1 hour fire resistance rating. | Deficient, Provider has date of correction (January 24, 2025) |
| K-0911 | Meet requirements for the installation and maintenance of electrical systems. | Deficient, Provider has date of correction (January 31, 2025) |
| K-0914 | Ensure receptacles at patient bed locations and where general anesthesia is administered, are tested after initial installation, replacement or servicing. | Deficient, Provider has date of correction (January 24, 2025) |
March 1, 2022 — 1 citation
| Tag | What the surveyor checks | Status |
|---|---|---|
| K-0712 | Have simulated fire drills held at unexpected times. | Deficient, Provider has date of correction (April 13, 2022) |
Reflects the CMS posting of August 1, 2026. Surveys conducted in the last few months may not appear yet.