Federal nursing home survey record · CMS-certified nursing home· Not a state assisted-living licensing record
VILLA AT STAMFORD, THE
STAMFORD, CT · 128 certified beds · Last Life Safety survey July 30, 2024
CMS Certification Number 075153 · first certified January 1967
Ownership
Operated by CENTER MANAGEMENT GROUP · For profit - Limited Liability company
- Ownership changed August 9, 2016 (change of ownership)to THE VILLA AT STAMFORD from CITY OF STAMFORD
Position within CT
6 citations — more than 33% of the 191 certified nursing homes in CT. Compared within CT rather than nationally because which state a facility is in explains about 30% of the variation in citation counts between facilities, while bed count explains under 1%. State survey agencies differ far more than the buildings do. How this is calculated
When is the next survey likely?
The window is open now: May 2026 to November 2026. This facility’s last Life Safety survey was July 2024. Facilities in CT are typically surveyed 21–28 months after the last one (median 24), measured over 181 consecutive surveys in the last two years of CMS records.
A range the record supports, not a prediction of a date. State agencies vary widely — from about 11 months in Pennsylvania to three years in Maryland. How the window is measured
Get an email about VILLA AT STAMFORD, THE
One email when it happens. No account; stop it any time with one click.
Physical environment (health survey)
2 physical-environment citations on the health survey. Cited by the health surveyors under Appendix PP, not the Life Safety Code surveyor: equipment in safe operating condition, the call system, bed rails, pest control, hazards, the environment. Counted separately from the 6 Life Safety citations above. The Physical Environment Index
How that compares
Compared with the median facility in CT, and nationally. Surveyors differ markedly between states, so the CT figure is the meaningful one.
| Measure | Citations |
|---|---|
| This facility | 6 |
| Median facility in CT | 10 |
| Median facility nationally | 11 |
Survey history
| Survey date | Citations |
|---|---|
| August 13, 2019 | 0 |
| February 2, 2022 | 0 |
| July 30, 2024 | 6 |
Most-cited tags
| Tag | What the surveyor checks | Times cited | Last cited |
|---|---|---|---|
| K-0222 | Add doors in an exit area that do not require the use of a key from the exit side unless in case of special locking arrangements. | 1 | 2024-07-30 |
| K-0921 | Ensure that testing and maintenance of electrical equipment is performed. | 1 | 2024-07-30 |
| K-0351 | Install an approved automatic sprinkler system. | 1 | 2024-07-30 |
| K-0353 | Inspect, test, and maintain automatic sprinkler systems. | 1 | 2024-07-30 |
| K-0363 | Install corridor and hallway doors that block smoke. | 1 | 2024-07-30 |
| K-0918 | Have generator or other power source capable of supplying service within 10 seconds. | 1 | 2024-07-30 |
What the citations cover
- Smoke Deficiencies 3
- Gas, Vacuum, and Electrical Systems Deficiencies 2
- Egress Deficiencies 1
| Category | Citations |
|---|---|
| Smoke Deficiencies | 3 |
| Gas, Vacuum, and Electrical Systems Deficiencies | 2 |
| Egress Deficiencies | 1 |
Every citation on file
As published by CMS, newest survey first. Descriptions are CMS’s own wording.
July 30, 2024 — 6 citations
| Tag | What the surveyor checks | Status |
|---|---|---|
| K-0222 | Add doors in an exit area that do not require the use of a key from the exit side unless in case of special locking arrangements. | Deficient, Provider has date of correction (September 3, 2024) |
| K-0351 | Install an approved automatic sprinkler system. | Deficient, Provider has date of correction (September 3, 2024) |
| K-0353 | Inspect, test, and maintain automatic sprinkler systems. | Deficient, Provider has date of correction (September 3, 2024) |
| K-0363 | Install corridor and hallway doors that block smoke. | Deficient, Provider has date of correction (September 3, 2024) |
| K-0918 | Have generator or other power source capable of supplying service within 10 seconds. | Deficient, Provider has date of correction (September 3, 2024) |
| K-0921 | Ensure that testing and maintenance of electrical equipment is performed. | Deficient, Provider has date of correction (September 3, 2024) |
Reflects the CMS posting of August 1, 2026. Surveys conducted in the last few months may not appear yet.