Federal nursing home survey record · CMS-certified nursing home· Not a state assisted-living licensing record
PRESBYTERIAN VILLAGE - ATHENS
ATHENS, GA · 40 certified beds · Last Life Safety survey November 18, 2025
CMS Certification Number 115775 · first certified September 2021
Also on this campus
The same campus holds a state-licensed assisted living facility, with its own state record on the Assisted Living Index: Presbyterian Village - Athens (1400 Live Oak Lane, Building 100). Matched by the telephone number the two records share. The records are separate and are never added together.
Ownership
Independently operated (no chain recorded by CMS) · Non profit - Corporation
No change of ownership on CMS record since January 1, 2016, when the records begin.
Position within GA
6 citations — more than 33% of the 356 certified nursing homes in GA. Compared within GA rather than nationally because which state a facility is in explains about 30% of the variation in citation counts between facilities, while bed count explains under 1%. State survey agencies differ far more than the buildings do. How this is calculated
The latest survey found 1 citation; the earlier surveys in the window averaged 2.5. With 3 surveys on file this is a direction of travel, not a conclusion.
When is the next survey likely?
The window opens January 2027 — about 4 months from now. This facility’s last Life Safety survey was November 2025. Facilities in GA are typically surveyed 14–20 months after the last one (median 16), measured over 532 consecutive surveys in the last two years of CMS records.
A range the record supports, not a prediction of a date. State agencies vary widely — from about 11 months in Pennsylvania to three years in Maryland. How the window is measured
Get an email about PRESBYTERIAN VILLAGE - ATHENS
One email when it happens. No account; stop it any time with one click.
1 inspection-and-testing tag has been cited here at more than one survey. Nationally, that pattern is common: about three quarters of cited facilities have at least one repeated tag, and half of the facilities ever cited for sprinkler inspection and testing are cited for it again. A repeat is usually a recordkeeping gap rather than a new hazard.
Physical environment (health survey)
3 physical-environment citations on the health survey. Cited by the health surveyors under Appendix PP, not the Life Safety Code surveyor: equipment in safe operating condition, the call system, bed rails, pest control, hazards, the environment. Counted separately from the 6 Life Safety citations above. The Physical Environment Index
How that compares
Compared with the median facility in GA, and nationally. Surveyors differ markedly between states, so the GA figure is the meaningful one.
| Measure | Citations |
|---|---|
| This facility | 6 |
| Median facility in GA | 8 |
| Median facility nationally | 11 |
Survey history
| Survey date | Citations |
|---|---|
| April 16, 2023 | 2 |
| July 22, 2024 | 3 |
| November 18, 2025 | 1 |
Most-cited tags
| Tag | What the surveyor checks | Times cited | Last cited |
|---|---|---|---|
| K-0341 | Install a fire alarm system that can be heard throughout the facility. | 2 | 2024-07-22 |
| K-0372 | Ensure smoke barriers are constructed to a 1 hour fire resistance rating. | 2 | 2024-07-22 |
| K-0511 | Have properly installed electrical wiring and gas equipment. | 1 | 2024-07-22 |
| K-0363 | Install corridor and hallway doors that block smoke. | 1 | 2025-11-18 |
What the citations cover
- Smoke Deficiencies 5
- Services Deficiencies 1
| Category | Citations |
|---|---|
| Smoke Deficiencies | 5 |
| Services Deficiencies | 1 |
Every citation on file
As published by CMS, newest survey first. Descriptions are CMS’s own wording.
November 18, 2025 — 1 citation
| Tag | What the surveyor checks | Status |
|---|---|---|
| K-0363 | Install corridor and hallway doors that block smoke. | Deficient, Provider has date of correction (December 31, 2025) |
July 22, 2024 — 3 citations
| Tag | What the surveyor checks | Status |
|---|---|---|
| K-0341 | Install a fire alarm system that can be heard throughout the facility. | Deficient, Provider has date of correction (August 29, 2024) |
| K-0372 | Ensure smoke barriers are constructed to a 1 hour fire resistance rating. | Deficient, Provider has date of correction (August 29, 2024) |
| K-0511 | Have properly installed electrical wiring and gas equipment. | Deficient, Provider has date of correction (August 29, 2024) |
April 16, 2023 — 2 citations
| Tag | What the surveyor checks | Status |
|---|---|---|
| K-0341 | Install a fire alarm system that can be heard throughout the facility. | Deficient, Provider has date of correction (May 31, 2023) |
| K-0372 | Ensure smoke barriers are constructed to a 1 hour fire resistance rating. | Deficient, Provider has date of correction (May 31, 2023) |
Reflects the CMS posting of August 1, 2026. Surveys conducted in the last few months may not appear yet.