Federal nursing home survey record · CMS-certified nursing home· Not a state assisted-living licensing record
Pruitthealth - Scenic View
BALDWIN, GA · 148 certified beds · Last Life Safety survey August 7, 2025
CMS Certification Number 115393 · first certified October 1989
Ownership
Operated by PRUITTHEALTH · For profit - Corporation
No change of ownership on CMS record since January 1, 2016, when the records begin.
Position within GA
5 citations — more than 23% of the 356 certified nursing homes in GA. Compared within GA rather than nationally because which state a facility is in explains about 30% of the variation in citation counts between facilities, while bed count explains under 1%. State survey agencies differ far more than the buildings do. How this is calculated
The latest survey found 3 citations; the earlier surveys in the window averaged 1. With 3 surveys on file this is a direction of travel, not a conclusion.
When is the next survey likely?
The window opens October 2026. This facility’s last Life Safety survey was August 2025. Facilities in GA are typically surveyed 14–20 months after the last one (median 16), measured over 532 consecutive surveys in the last two years of CMS records.
A range the record supports, not a prediction of a date. State agencies vary widely — from about 11 months in Pennsylvania to three years in Maryland. How the window is measured
Get an email about Pruitthealth - Scenic View
One email when it happens. No account; stop it any time with one click.
Physical environment (health survey)
3 physical-environment citations on the health survey. Cited by the health surveyors under Appendix PP, not the Life Safety Code surveyor: equipment in safe operating condition, the call system, bed rails, pest control, hazards, the environment. Counted separately from the 5 Life Safety citations above. The Physical Environment Index
How that compares
Compared with the median facility in GA, and nationally. Surveyors differ markedly between states, so the GA figure is the meaningful one.
| Measure | Citations |
|---|---|
| This facility | 5 |
| Median facility in GA | 8 |
| Median facility nationally | 11 |
Survey history
| Survey date | Citations |
|---|---|
| March 2, 2023 | 1 |
| March 28, 2024 | 1 |
| August 7, 2025 | 3 |
Most-cited tags
| Tag | What the surveyor checks | Times cited | Last cited |
|---|---|---|---|
| K-0281 | Install proper backup exit lighting. | 1 | 2025-08-07 |
| K-0355 | Properly select, install, inspect, or maintain portable fire extinguishes. | 1 | 2025-08-07 |
| K-0351 | Install an approved automatic sprinkler system. | 1 | 2023-03-02 |
| K-0293 | Have properly located and lighted "Exit" signs. | 1 | 2025-08-07 |
| K-0919 | Meet requirements for the use of electrical equipment. | 1 | 2024-03-28 |
What the citations cover
- Smoke Deficiencies 2
- Egress Deficiencies 2
- Gas, Vacuum, and Electrical Systems Deficiencies 1
| Category | Citations |
|---|---|
| Smoke Deficiencies | 2 |
| Egress Deficiencies | 2 |
| Gas, Vacuum, and Electrical Systems Deficiencies | 1 |
Every citation on file
As published by CMS, newest survey first. Descriptions are CMS’s own wording.
August 7, 2025 — 3 citations
| Tag | What the surveyor checks | Status |
|---|---|---|
| K-0281 | Install proper backup exit lighting. | Deficient, Provider has date of correction (September 5, 2025) |
| K-0293 | Have properly located and lighted "Exit" signs. | Deficient, Provider has date of correction (September 5, 2025) |
| K-0355 | Properly select, install, inspect, or maintain portable fire extinguishes. | Deficient, Provider has date of correction (September 5, 2025) |
March 28, 2024 — 1 citation
| Tag | What the surveyor checks | Status |
|---|---|---|
| K-0919 | Meet requirements for the use of electrical equipment. | Deficient, Provider has date of correction (April 10, 2024) |
March 2, 2023 — 1 citation
| Tag | What the surveyor checks | Status |
|---|---|---|
| K-0351 | Install an approved automatic sprinkler system. | Deficient, Provider has date of correction (April 12, 2023) |