Federal nursing home survey record · CMS-certified nursing home· Not a state assisted-living licensing record
REGENCY PARK HEALTH AND REHABILITATION
DALTON, GA · 100 certified beds · Last Life Safety survey August 14, 2025
CMS Certification Number 115663 · first certified July 1999
Ownership
Independently operated (no chain recorded by CMS) · Non profit - Corporation
No change of ownership on CMS record since January 1, 2016, when the records begin.
Position within GA
6 citations — more than 33% of the 356 certified nursing homes in GA. Compared within GA rather than nationally because which state a facility is in explains about 30% of the variation in citation counts between facilities, while bed count explains under 1%. State survey agencies differ far more than the buildings do. How this is calculated
The latest survey found 3 citations; the earlier surveys in the window averaged 1.5. With 3 surveys on file this is a direction of travel, not a conclusion.
When is the next survey likely?
The window opens October 2026 — about 1 month from now. This facility’s last Life Safety survey was August 2025. Facilities in GA are typically surveyed 14–20 months after the last one (median 16), measured over 532 consecutive surveys in the last two years of CMS records.
A range the record supports, not a prediction of a date. State agencies vary widely — from about 11 months in Pennsylvania to three years in Maryland. How the window is measured
Get an email about REGENCY PARK HEALTH AND REHABILITATION
One email when it happens. No account; stop it any time with one click.
Emergency preparedness
1 of the 6 citations on file is Emergency Preparedness E-tags. E-tags are cited under 42 CFR §483.73 and concern the emergency plan, training, drills, communications and supplies. Nationally about half of certified facilities have at least one. The Emergency Preparedness Index
Physical environment (health survey)
4 physical-environment citations on the health survey. Cited by the health surveyors under Appendix PP, not the Life Safety Code surveyor: equipment in safe operating condition, the call system, bed rails, pest control, hazards, the environment. Counted separately from the 6 Life Safety citations above. The Physical Environment Index
- F-0880 Provide and implement an infection prevention and control program.
- F-0689 Ensure that a nursing home area is free from accident hazards and provides adequate supervision to prevent accidents.
- F-0584 Honor the resident's right to a safe, clean, comfortable and homelike environment, including but not limited to receiving treatment and supports for daily living safely.
How that compares
Compared with the median facility in GA, and nationally. Surveyors differ markedly between states, so the GA figure is the meaningful one.
| Measure | Citations |
|---|---|
| This facility | 6 |
| Median facility in GA | 8 |
| Median facility nationally | 11 |
Survey history
| Survey date | Citations |
|---|---|
| May 12, 2022 | 3 |
| April 11, 2024 | 0 |
| August 14, 2025 | 3 |
Most-cited tags
| Tag | What the surveyor checks | Times cited | Last cited |
|---|---|---|---|
| K-0111 | Satisfy building requirements after a repair, renovation, modification, or change of user/occupancy. | 1 | 2022-05-12 |
| K-0712 | Have simulated fire drills held at unexpected times. | 1 | 2022-05-12 |
| K-0353 | Inspect, test, and maintain automatic sprinkler systems. | 1 | 2025-08-14 |
| K-0225 | Have stairways and smokeproof enclosures used as exits that meet safety requirements. | 1 | 2025-08-14 |
| E-0041 | Implement emergency and standby power systems. | 1 | 2022-05-12 |
| K-0511 | Have properly installed electrical wiring and gas equipment. | 1 | 2025-08-14 |
What the citations cover
- Emergency Preparedness Deficiencies 1
- Smoke Deficiencies 1
- Egress Deficiencies 1
- Miscellaneous Deficiencies 1
- Other 2
| Category | Citations |
|---|---|
| Emergency Preparedness Deficiencies | 1 |
| Smoke Deficiencies | 1 |
| Egress Deficiencies | 1 |
| Miscellaneous Deficiencies | 1 |
| Services Deficiencies | 1 |
| Construction Deficiencies | 1 |
Every citation on file
As published by CMS, newest survey first. Descriptions are CMS’s own wording.
August 14, 2025 — 3 citations
| Tag | What the surveyor checks | Status |
|---|---|---|
| K-0225 | Have stairways and smokeproof enclosures used as exits that meet safety requirements. | Deficient, Provider has date of correction (September 28, 2025) |
| K-0353 | Inspect, test, and maintain automatic sprinkler systems. | Deficient, Provider has date of correction (October 21, 2025) |
| K-0511 | Have properly installed electrical wiring and gas equipment. | Deficient, Provider has date of correction (September 28, 2025) |
May 12, 2022 — 3 citations
| Tag | What the surveyor checks | Status |
|---|---|---|
| E-0041 | Implement emergency and standby power systems. | Deficient, Provider has date of correction (July 8, 2022) |
| K-0111 | Satisfy building requirements after a repair, renovation, modification, or change of user/occupancy. | Deficient, Provider has date of correction (July 8, 2022) |
| K-0712 | Have simulated fire drills held at unexpected times. | Deficient, Provider has date of correction (July 8, 2022) |
Reflects the CMS posting of August 1, 2026. Surveys conducted in the last few months may not appear yet.