CALHOUN NURSING HOME
EDISON, GA · 60 certified beds · Last Life Safety survey May 1, 2025
CMS Certification Number 115264 · first certified August 1979
Ownership
Independently operated (no chain recorded by CMS) · Government - Hospital district
No change of ownership on CMS record since January 1, 2016, when the records begin.
Position within GA
3 citations — more than 11% of the 356 certified nursing homes in GA. Compared within GA rather than nationally because which state a facility is in explains about 30% of the variation in citation counts between facilities, while bed count explains under 1%. State survey agencies differ far more than the buildings do. How this is calculated
The latest survey found 1 citation; the earlier surveys in the window averaged 1. With 3 surveys on file this is a direction of travel, not a conclusion.
When is the next survey likely?
The window is open now: July 2026 to December 2026. This facility’s last Life Safety survey was May 2025. Facilities in GA are typically surveyed 14–20 months after the last one (median 16), measured over 532 consecutive surveys in the last two years of CMS records.
A range the record supports, not a prediction of a date. State agencies vary widely — from about 11 months in Pennsylvania to three years in Maryland. How the window is measured
Get an email about CALHOUN NURSING HOME
One email when it happens. No account; stop it any time with one click.
Physical environment (health survey)
2 physical-environment citations on the health survey. Cited by the health surveyors under Appendix PP, not the Life Safety Code surveyor: equipment in safe operating condition, the call system, bed rails, pest control, hazards, the environment. Counted separately from the 3 Life Safety citations above. The Physical Environment Index
How that compares
Compared with the median facility in GA, and nationally. Surveyors differ markedly between states, so the GA figure is the meaningful one.
| Measure | Citations |
|---|---|
| This facility | 3 |
| Median facility in GA | 8 |
| Median facility nationally | 11 |
Survey history
| Survey date | Citations |
|---|---|
| January 21, 2022 | 0 |
| October 26, 2023 | 2 |
| May 1, 2025 | 1 |
Most-cited tags
| Tag | What the surveyor checks | Times cited | Last cited |
|---|---|---|---|
| K-0781 | Have restrictions on the use of portable space heaters. | 1 | 2023-10-26 |
| K-0511 | Have properly installed electrical wiring and gas equipment. | 1 | 2023-10-26 |
| K-0372 | Ensure smoke barriers are constructed to a 1 hour fire resistance rating. | 1 | 2025-05-01 |
What the citations cover
- Smoke Deficiencies 1
- Miscellaneous Deficiencies 1
- Services Deficiencies 1
| Category | Citations |
|---|---|
| Smoke Deficiencies | 1 |
| Miscellaneous Deficiencies | 1 |
| Services Deficiencies | 1 |
Every citation on file
As published by CMS, newest survey first. Descriptions are CMS’s own wording.
May 1, 2025 — 1 citation
| Tag | What the surveyor checks | Status |
|---|---|---|
| K-0372 | Ensure smoke barriers are constructed to a 1 hour fire resistance rating. | Deficient, Provider has date of correction (June 15, 2025) |
October 26, 2023 — 2 citations
| Tag | What the surveyor checks | Status |
|---|---|---|
| K-0511 | Have properly installed electrical wiring and gas equipment. | Deficient, Provider has date of correction (December 8, 2023) |
| K-0781 | Have restrictions on the use of portable space heaters. | Deficient, Provider has date of correction (December 8, 2023) |
Reflects the CMS posting of August 1, 2026. Surveys conducted in the last few months may not appear yet.