Federal nursing home survey record · CMS-certified nursing home· Not a state assisted-living licensing record

NHC HEALTHCARE ROSSVILLE

ROSSVILLE, GA · 112 certified beds · Last Life Safety survey September 4, 2025

CMS Certification Number 115104 · first certified June 1969

Ownership

Operated by NATIONAL HEALTHCARE CORPORATION · For profit - Corporation

No change of ownership on CMS record since January 1, 2016, when the records begin.

4
Citations on file
Rolling three-year window
3
Life Safety surveys
In the same window
0
Tags cited more than once
Across separate surveys
0
Inspection & testing records
Of the citations on file

Position within GA

4 citations — more than 17% of the 356 certified nursing homes in GA. Compared within GA rather than nationally because which state a facility is in explains about 30% of the variation in citation counts between facilities, while bed count explains under 1%. State survey agencies differ far more than the buildings do. How this is calculated

When is the next survey likely?

The window opens November 2026 — about 1 month from now. This facility’s last Life Safety survey was September 2025. Facilities in GA are typically surveyed 14–20 months after the last one (median 16), measured over 532 consecutive surveys in the last two years of CMS records.

A range the record supports, not a prediction of a date. State agencies vary widely — from about 11 months in Pennsylvania to three years in Maryland. How the window is measured

Get an email about NHC HEALTHCARE ROSSVILLE

One email when it happens. No account; stop it any time with one click.

Which alerts

Physical environment (health survey)

2 physical-environment citations on the health survey. Cited by the health surveyors under Appendix PP, not the Life Safety Code surveyor: equipment in safe operating condition, the call system, bed rails, pest control, hazards, the environment. Counted separately from the 4 Life Safety citations above. The Physical Environment Index

  • F-0689 Ensure that a nursing home area is free from accident hazards and provides adequate supervision to prevent accidents.
  • F-0925 Make sure there is a pest control program to prevent/deal with mice, insects, or other pests.

How that compares

Citations on file over three years

Compared with the median facility in GA, and nationally. Surveyors differ markedly between states, so the GA figure is the meaningful one.

This facility4GA median8National median11
Citations on file over three years, compared
MeasureCitations
This facility4
Median facility in GA8
Median facility nationally11

Survey history

Citations at each Life Safety survey
02023-0142024-0302025-09
Citations at each Life Safety survey
Survey dateCitations
January 19, 20230
March 8, 20244
September 4, 20250

Most-cited tags

Most-cited tags at this facility
K-02111K-03111K-03641K-09111
Most-cited tags at this facility
TagWhat the surveyor checksTimes citedLast cited
K-0211Keep aisles, corridors, and exits free of obstruction in case of emergency.12024-03-08
K-0311Have an enclosure around a vertical opening shaft.12024-03-08
K-0364Install properly constructed windows in hallway walls or doors.12024-03-08
K-0911Meet requirements for the installation and maintenance of electrical systems.12024-03-08

What the citations cover

Citations by CMS category
  • Smoke Deficiencies 2
  • Gas, Vacuum, and Electrical Systems Deficiencies 1
  • Egress Deficiencies 1
Citations by CMS category
CategoryCitations
Smoke Deficiencies2
Gas, Vacuum, and Electrical Systems Deficiencies1
Egress Deficiencies1

Every citation on file

As published by CMS, newest survey first. Descriptions are CMS’s own wording.

March 8, 2024 — 4 citations

Citations issued on March 8, 2024
TagWhat the surveyor checksStatus
K-0211Keep aisles, corridors, and exits free of obstruction in case of emergency.Deficient, Provider has date of correction (March 29, 2024)
K-0311Have an enclosure around a vertical opening shaft.Deficient, Provider has date of correction (March 29, 2024)
K-0364Install properly constructed windows in hallway walls or doors.Deficient, Provider has date of correction (March 29, 2024)
K-0911Meet requirements for the installation and maintenance of electrical systems.Deficient, Provider has date of correction (March 29, 2024)

Reflects the CMS posting of August 1, 2026. Surveys conducted in the last few months may not appear yet.