Federal nursing home survey record · CMS-certified nursing home· Not a state assisted-living licensing record
FRIENDSHIP MANOR
ROCK ISLAND, IL · 94 certified beds · Last Life Safety survey June 4, 2026
CMS Certification Number 146099 · first certified December 2005
Ownership
Independently operated (no chain recorded by CMS) · Non profit - Other
No change of ownership on CMS record since January 1, 2016, when the records begin.
Position within IL
17 citations — more than 56% of the 664 certified nursing homes in IL. Compared within IL rather than nationally because which state a facility is in explains about 30% of the variation in citation counts between facilities, while bed count explains under 1%. State survey agencies differ far more than the buildings do. How this is calculated
The latest survey found 6 citations; the earlier surveys on file averaged 5.5. With 3 surveys on file this is a direction of travel, not a conclusion.
When is the next survey likely?
The window opens May 2027 — about 6 months from now. This facility’s last Life Safety survey was June 2026. Facilities in IL are typically surveyed 11–14 months after the last one (median 13), measured over 739 consecutive surveys in the last two years of CMS records.
A range the record supports, not a prediction of a date. State agencies vary widely — from about 11 months in Pennsylvania to about three years in Virginia. How the window is measured
Get an email about FRIENDSHIP MANOR
One email when it happens. No account; stop it any time with one click.
Emergency preparedness
1 of the 17 citations on file is Emergency Preparedness E-tags. E-tags are cited under 42 CFR §483.73 and concern the emergency plan, training, drills, communications and supplies. Nationally about half of certified facilities have at least one. The Emergency Preparedness Index
Physical environment (health survey)
7 physical-environment citations on the health survey. Cited by the health surveyors under Appendix PP, not the Life Safety Code surveyor: equipment in safe operating condition, the call system, bed rails, pest control, hazards, the environment. Counted separately from the 17 Life Safety citations above. The Physical Environment Index
How that compares
Compared with the median facility in IL, and nationally. Surveyors differ markedly between states, so the IL figure is the meaningful one.
| Measure | Citations |
|---|---|
| This facility | 17 |
| Median facility in IL | 15 |
| Median facility nationally | 11 |
Survey history
| Survey date | Citations |
|---|---|
| July 19, 2023 | 3 |
| July 24, 2024 | 8 |
| June 4, 2026 | 6 |
Most-cited tags
| Tag | What the surveyor checks | Times cited | Last cited |
|---|---|---|---|
| K-0341 | Install a fire alarm system that can be heard throughout the facility. | 2 | 2026-06-04 |
| K-0271 | Have exits that are accessible at all times. | 1 | 2023-07-19 |
| K-0712 | Have simulated fire drills held at unexpected times. | 1 | 2026-06-04 |
| K-0345 | Have approved installation, maintenance and testing program for fire alarm systems. | 1 | 2024-07-24 |
| K-0225 | Have stairways and smokeproof enclosures used as exits that meet safety requirements. | 1 | 2024-07-24 |
| E-0015 | Address subsistence needs for staff and patients. | 1 | 2024-07-24 |
| K-0293 | Have properly located and lighted "Exit" signs. | 1 | 2026-06-04 |
| K-0351 | Install an approved automatic sprinkler system. | 1 | 2023-07-19 |
What the citations cover
- Smoke Deficiencies 7
- Egress Deficiencies 4
- Gas, Vacuum, and Electrical Systems Deficiencies 3
- Emergency Preparedness Deficiencies 1
- Other 2
| Category | Citations |
|---|---|
| Smoke Deficiencies | 7 |
| Egress Deficiencies | 4 |
| Gas, Vacuum, and Electrical Systems Deficiencies | 3 |
| Emergency Preparedness Deficiencies | 1 |
| Miscellaneous Deficiencies | 1 |
| Construction Deficiencies | 1 |
Every citation on file
As published by CMS, newest survey first. Descriptions are CMS’s own wording.
June 4, 2026 — 6 citations
| Tag | What the surveyor checks | Status |
|---|---|---|
| K-0291 | Install emergency lighting that can last at least 1 1/2 hours. | Deficient, Provider has date of correction (June 24, 2026) |
| K-0293 | Have properly located and lighted "Exit" signs. | Deficient, Provider has date of correction (June 23, 2026) |
| K-0341 | Install a fire alarm system that can be heard throughout the facility. | Deficient, Provider has date of correction (June 23, 2026) |
| K-0355 | Properly select, install, inspect, or maintain portable fire extinguishes. | Deficient, Provider has date of correction (June 23, 2026) |
| K-0712 | Have simulated fire drills held at unexpected times. | Deficient, Provider has date of correction (June 23, 2026) |
| K-0918 | Have generator or other power source capable of supplying service within 10 seconds. | Deficient, Provider has date of correction (June 30, 2026) |
July 24, 2024 — 8 citations
| Tag | What the surveyor checks | Status |
|---|---|---|
| E-0015 | Address subsistence needs for staff and patients. | Deficient, Provider has date of correction (September 3, 2024) |
| K-0225 | Have stairways and smokeproof enclosures used as exits that meet safety requirements. | Deficient, Provider has date of correction (August 13, 2024) |
| K-0341 | Install a fire alarm system that can be heard throughout the facility. | Deficient, Provider has date of correction (August 13, 2024) |
| K-0345 | Have approved installation, maintenance and testing program for fire alarm systems. | Deficient, Provider has date of correction (August 15, 2024) |
| K-0346 | Follow proper procedures when the fire alarm was out of service for more than 4 hours. | Deficient, Provider has date of correction (August 14, 2024) |
| K-0354 | Follow proper procedures when the automatic sprinkler systems was out of service for more than 10 hours. | Deficient, Provider has date of correction (August 14, 2024) |
| K-0914 | Ensure receptacles at patient bed locations and where general anesthesia is administered, are tested after initial installation, replacement or servicing. | Deficient, Provider has date of correction (August 5, 2024) |
| K-0920 | Ensure proper usage of power strips and extension cords. | Deficient, Provider has date of correction (August 15, 2024) |
July 19, 2023 — 3 citations
| Tag | What the surveyor checks | Status |
|---|---|---|
| K-0133 | Install a two-hour-resistant firewall separation. | Deficient, Provider has date of correction (July 18, 2023) |
| K-0271 | Have exits that are accessible at all times. | Deficient, Provider has date of correction (July 19, 2023) |
| K-0351 | Install an approved automatic sprinkler system. | Deficient, Provider has date of correction (July 19, 2023) |
Reflects the CMS posting of October 1, 2026. Surveys conducted in the last few months may not appear yet.