Federal nursing home survey record · CMS-certified nursing home· Not a state assisted-living licensing record
PROVIDENCE PLACE
KANSAS CITY, KS · 45 certified beds · Last Life Safety survey August 12, 2025
CMS Certification Number 175159 · first certified March 1987
Ownership
Operated by THE ENSIGN GROUP · For profit - Corporation
- Ownership changed October 1, 2023 (change of ownership)from PRIME HEALTHCARE SERVICES-PROVIDENCE, LLC
Position within KS
16 citations — more than 12% of the 296 certified nursing homes in KS. Compared within KS rather than nationally because which state a facility is in explains about 30% of the variation in citation counts between facilities, while bed count explains under 1%. State survey agencies differ far more than the buildings do. How this is calculated
The latest survey found 3 citations; the earlier surveys in the window averaged 6.5. With 3 surveys on file this is a direction of travel, not a conclusion.
When is the next survey likely?
The window opens April 2027 — about 6 months from now. This facility’s last Life Safety survey was August 2025. Facilities in KS are typically surveyed 20–22 months after the last one (median 21), measured over 298 consecutive surveys in the last two years of CMS records.
A range the record supports, not a prediction of a date. State agencies vary widely — from about 11 months in Pennsylvania to three years in Maryland. How the window is measured
Get an email about PROVIDENCE PLACE
One email when it happens. No account; stop it any time with one click.
3 inspection-and-testing tags have been cited here at more than one survey. Nationally, that pattern is common: about three quarters of cited facilities have at least one repeated tag, and half of the facilities ever cited for sprinkler inspection and testing are cited for it again. A repeat is usually a recordkeeping gap rather than a new hazard.
Physical environment (health survey)
4 physical-environment citations on the health survey. Cited by the health surveyors under Appendix PP, not the Life Safety Code surveyor: equipment in safe operating condition, the call system, bed rails, pest control, hazards, the environment. Counted separately from the 16 Life Safety citations above. The Physical Environment Index
How that compares
Compared with the median facility in KS, and nationally. Surveyors differ markedly between states, so the KS figure is the meaningful one.
| Measure | Citations |
|---|---|
| This facility | 16 |
| Median facility in KS | 27 |
| Median facility nationally | 11 |
Survey history
| Survey date | Citations |
|---|---|
| March 30, 2022 | 6 |
| November 1, 2023 | 7 |
| August 12, 2025 | 3 |
Most-cited tags
| Tag | What the surveyor checks | Times cited | Last cited |
|---|---|---|---|
| K-0353 | Inspect, test, and maintain automatic sprinkler systems. | 3 | 2025-08-12 |
| K-0511 | Have properly installed electrical wiring and gas equipment. | 3 | 2025-08-12 |
| K-0362 | Ensure that corridors are separated from use areas by walls constructed to limit the passage of smoke. | 2 | 2025-08-12 |
| K-0918 | Have generator or other power source capable of supplying service within 10 seconds. | 2 | 2023-11-01 |
| K-0372 | Ensure smoke barriers are constructed to a 1 hour fire resistance rating. | 1 | 2023-11-01 |
| K-0374 | Install smoke barrier doors that can resist smoke for at least 20 minutes. | 1 | 2022-03-30 |
| K-0712 | Have simulated fire drills held at unexpected times. | 1 | 2022-03-30 |
| K-0920 | Ensure proper usage of power strips and extension cords. | 1 | 2023-11-01 |
What the citations cover
- Smoke Deficiencies 8
- Services Deficiencies 4
- Gas, Vacuum, and Electrical Systems Deficiencies 3
- Miscellaneous Deficiencies 1
| Category | Citations |
|---|---|
| Smoke Deficiencies | 8 |
| Services Deficiencies | 4 |
| Gas, Vacuum, and Electrical Systems Deficiencies | 3 |
| Miscellaneous Deficiencies | 1 |
Every citation on file
As published by CMS, newest survey first. Descriptions are CMS’s own wording.
August 12, 2025 — 3 citations
| Tag | What the surveyor checks | Status |
|---|---|---|
| K-0353 | Inspect, test, and maintain automatic sprinkler systems. | Deficient, Provider has date of correction (September 26, 2025) |
| K-0362 | Ensure that corridors are separated from use areas by walls constructed to limit the passage of smoke. | Deficient, Provider has date of correction (September 26, 2025) |
| K-0511 | Have properly installed electrical wiring and gas equipment. | Deficient, Provider has date of correction (September 26, 2025) |
November 1, 2023 — 7 citations
| Tag | What the surveyor checks | Status |
|---|---|---|
| K-0353 | Inspect, test, and maintain automatic sprinkler systems. | Deficient, Provider has date of correction (March 1, 2024) |
| K-0362 | Ensure that corridors are separated from use areas by walls constructed to limit the passage of smoke. | Deficient, Provider has date of correction (March 1, 2024) |
| K-0372 | Ensure smoke barriers are constructed to a 1 hour fire resistance rating. | Deficient, Provider has date of correction (March 1, 2024) |
| K-0511 | Have properly installed electrical wiring and gas equipment. | Deficient, Provider has date of correction (March 1, 2024) |
| K-0521 | Ensure heating and ventilation systems that have been properly installed according to the manufacturer's instructions. | Deficient, Provider has date of correction (March 1, 2024) |
| K-0918 | Have generator or other power source capable of supplying service within 10 seconds. | Deficient, Provider has date of correction (March 1, 2024) |
| K-0920 | Ensure proper usage of power strips and extension cords. | Deficient, Provider has date of correction (March 1, 2024) |
March 30, 2022 — 6 citations
| Tag | What the surveyor checks | Status |
|---|---|---|
| K-0345 | Have approved installation, maintenance and testing program for fire alarm systems. | Deficient, Provider has date of correction (June 2, 2022) |
| K-0353 | Inspect, test, and maintain automatic sprinkler systems. | Deficient, Provider has date of correction (June 2, 2022) |
| K-0374 | Install smoke barrier doors that can resist smoke for at least 20 minutes. | Deficient, Provider has date of correction (June 2, 2022) |
| K-0511 | Have properly installed electrical wiring and gas equipment. | Deficient, Provider has date of correction (June 2, 2022) |
| K-0712 | Have simulated fire drills held at unexpected times. | Deficient, Provider has date of correction (June 2, 2022) |
| K-0918 | Have generator or other power source capable of supplying service within 10 seconds. | Deficient, Provider has date of correction (June 2, 2022) |
Reflects the CMS posting of August 1, 2026. Surveys conducted in the last few months may not appear yet.