Federal nursing home survey record · CMS-certified nursing home· Not a state assisted-living licensing record

PROVIDENCE PLACE

KANSAS CITY, KS · 45 certified beds · Last Life Safety survey August 12, 2025

CMS Certification Number 175159 · first certified March 1987

Ownership

Operated by THE ENSIGN GROUP · For profit - Corporation

  • Ownership changed October 1, 2023 (change of ownership)from PRIME HEALTHCARE SERVICES-PROVIDENCE, LLC
16
Citations on file
Rolling three-year window
3
Life Safety surveys
In the same window
4
Tags cited more than once
Across separate surveys
12
Inspection & testing records
Of the citations on file

Position within KS

16 citations — more than 12% of the 296 certified nursing homes in KS. Compared within KS rather than nationally because which state a facility is in explains about 30% of the variation in citation counts between facilities, while bed count explains under 1%. State survey agencies differ far more than the buildings do. How this is calculated

Improvingfewer citations at the latest survey than at its earlier surveys in the window.

The latest survey found 3 citations; the earlier surveys in the window averaged 6.5. With 3 surveys on file this is a direction of travel, not a conclusion.

When is the next survey likely?

The window opens April 2027 — about 6 months from now. This facility’s last Life Safety survey was August 2025. Facilities in KS are typically surveyed 20–22 months after the last one (median 21), measured over 298 consecutive surveys in the last two years of CMS records.

A range the record supports, not a prediction of a date. State agencies vary widely — from about 11 months in Pennsylvania to three years in Maryland. How the window is measured

Get an email about PROVIDENCE PLACE

One email when it happens. No account; stop it any time with one click.

Which alerts

3 inspection-and-testing tags have been cited here at more than one survey. Nationally, that pattern is common: about three quarters of cited facilities have at least one repeated tag, and half of the facilities ever cited for sprinkler inspection and testing are cited for it again. A repeat is usually a recordkeeping gap rather than a new hazard.

Physical environment (health survey)

4 physical-environment citations on the health survey. Cited by the health surveyors under Appendix PP, not the Life Safety Code surveyor: equipment in safe operating condition, the call system, bed rails, pest control, hazards, the environment. Counted separately from the 16 Life Safety citations above. The Physical Environment Index

  • F-0689 Ensure that a nursing home area is free from accident hazards and provides adequate supervision to prevent accidents.
  • F-0880 Provide and implement an infection prevention and control program.

How that compares

Citations on file over three years

Compared with the median facility in KS, and nationally. Surveyors differ markedly between states, so the KS figure is the meaningful one.

This facility16KS median27National median11
Citations on file over three years, compared
MeasureCitations
This facility16
Median facility in KS27
Median facility nationally11

Survey history

Citations at each Life Safety survey
62022-0372023-1132025-08
Citations at each Life Safety survey
Survey dateCitations
March 30, 20226
November 1, 20237
August 12, 20253

Most-cited tags

Most-cited tags at this facility
K-03533K-05113K-03622K-09182K-03721K-03741K-07121K-09201
Most-cited tags at this facility
TagWhat the surveyor checksTimes citedLast cited
K-0353Inspect, test, and maintain automatic sprinkler systems.32025-08-12
K-0511Have properly installed electrical wiring and gas equipment.32025-08-12
K-0362Ensure that corridors are separated from use areas by walls constructed to limit the passage of smoke.22025-08-12
K-0918Have generator or other power source capable of supplying service within 10 seconds.22023-11-01
K-0372Ensure smoke barriers are constructed to a 1 hour fire resistance rating.12023-11-01
K-0374Install smoke barrier doors that can resist smoke for at least 20 minutes.12022-03-30
K-0712Have simulated fire drills held at unexpected times.12022-03-30
K-0920Ensure proper usage of power strips and extension cords.12023-11-01

What the citations cover

Citations by CMS category
  • Smoke Deficiencies 8
  • Services Deficiencies 4
  • Gas, Vacuum, and Electrical Systems Deficiencies 3
  • Miscellaneous Deficiencies 1
Citations by CMS category
CategoryCitations
Smoke Deficiencies8
Services Deficiencies4
Gas, Vacuum, and Electrical Systems Deficiencies3
Miscellaneous Deficiencies1

Every citation on file

As published by CMS, newest survey first. Descriptions are CMS’s own wording.

August 12, 2025 — 3 citations

Citations issued on August 12, 2025
TagWhat the surveyor checksStatus
K-0353Inspect, test, and maintain automatic sprinkler systems.Deficient, Provider has date of correction (September 26, 2025)
K-0362Ensure that corridors are separated from use areas by walls constructed to limit the passage of smoke.Deficient, Provider has date of correction (September 26, 2025)
K-0511Have properly installed electrical wiring and gas equipment.Deficient, Provider has date of correction (September 26, 2025)

November 1, 2023 — 7 citations

Citations issued on November 1, 2023
TagWhat the surveyor checksStatus
K-0353Inspect, test, and maintain automatic sprinkler systems.Deficient, Provider has date of correction (March 1, 2024)
K-0362Ensure that corridors are separated from use areas by walls constructed to limit the passage of smoke.Deficient, Provider has date of correction (March 1, 2024)
K-0372Ensure smoke barriers are constructed to a 1 hour fire resistance rating.Deficient, Provider has date of correction (March 1, 2024)
K-0511Have properly installed electrical wiring and gas equipment.Deficient, Provider has date of correction (March 1, 2024)
K-0521Ensure heating and ventilation systems that have been properly installed according to the manufacturer's instructions.Deficient, Provider has date of correction (March 1, 2024)
K-0918Have generator or other power source capable of supplying service within 10 seconds.Deficient, Provider has date of correction (March 1, 2024)
K-0920Ensure proper usage of power strips and extension cords.Deficient, Provider has date of correction (March 1, 2024)

March 30, 2022 — 6 citations

Citations issued on March 30, 2022
TagWhat the surveyor checksStatus
K-0345Have approved installation, maintenance and testing program for fire alarm systems.Deficient, Provider has date of correction (June 2, 2022)
K-0353Inspect, test, and maintain automatic sprinkler systems.Deficient, Provider has date of correction (June 2, 2022)
K-0374Install smoke barrier doors that can resist smoke for at least 20 minutes.Deficient, Provider has date of correction (June 2, 2022)
K-0511Have properly installed electrical wiring and gas equipment.Deficient, Provider has date of correction (June 2, 2022)
K-0712Have simulated fire drills held at unexpected times.Deficient, Provider has date of correction (June 2, 2022)
K-0918Have generator or other power source capable of supplying service within 10 seconds.Deficient, Provider has date of correction (June 2, 2022)

Reflects the CMS posting of August 1, 2026. Surveys conducted in the last few months may not appear yet.