Federal nursing home survey record · CMS-certified nursing home· Not a state assisted-living licensing record

ST JOSEPH REHAB & NURSING CARE CENTER

DORCHESTER, MA · 123 certified beds · Last Life Safety survey February 19, 2026

CMS Certification Number 225493 · first certified July 1990

Ownership

Independently operated (no chain recorded by CMS) · For profit - Limited Liability company

No change of ownership on CMS record since January 1, 2016, when the records begin.

17
Citations on file
Rolling three-year window
3
Life Safety surveys
In the same window
2
Tags cited more than once
Across separate surveys
9
Inspection & testing records
Of the citations on file

Position within MA

17 citations — more than 71% of the 341 certified nursing homes in MA. Compared within MA rather than nationally because which state a facility is in explains about 30% of the variation in citation counts between facilities, while bed count explains under 1%. State survey agencies differ far more than the buildings do. How this is calculated

Improvingfewer citations at the latest survey than at its earlier surveys in the window.

The latest survey found 1 citation; the earlier surveys in the window averaged 8. With 3 surveys on file this is a direction of travel, not a conclusion.

When is the next survey likely?

The window opens February 2027 — about 5 months from now. This facility’s last Life Safety survey was February 2026. Facilities in MA are typically surveyed 12–15 months after the last one (median 13), measured over 556 consecutive surveys in the last two years of CMS records.

A range the record supports, not a prediction of a date. State agencies vary widely — from about 11 months in Pennsylvania to three years in Maryland. How the window is measured

Get an email about ST JOSEPH REHAB & NURSING CARE CENTER

One email when it happens. No account; stop it any time with one click.

Which alerts

2 inspection-and-testing tags have been cited here at more than one survey. Nationally, that pattern is common: about three quarters of cited facilities have at least one repeated tag, and half of the facilities ever cited for sprinkler inspection and testing are cited for it again. A repeat is usually a recordkeeping gap rather than a new hazard.

Physical environment (health survey)

3 physical-environment citations on the health survey. Cited by the health surveyors under Appendix PP, not the Life Safety Code surveyor: equipment in safe operating condition, the call system, bed rails, pest control, hazards, the environment. Counted separately from the 17 Life Safety citations above. The Physical Environment Index

  • F-0880 Provide and implement an infection prevention and control program.
  • F-0584 Honor the resident's right to a safe, clean, comfortable and homelike environment, including but not limited to receiving treatment and supports for daily living safely.
  • F-0689 Ensure that a nursing home area is free from accident hazards and provides adequate supervision to prevent accidents.

How that compares

Citations on file over three years

Compared with the median facility in MA, and nationally. Surveyors differ markedly between states, so the MA figure is the meaningful one.

This facility17MA median11National median11
Citations on file over three years, compared
MeasureCitations
This facility17
Median facility in MA11
Median facility nationally11

Survey history

Citations at each Life Safety survey
22024-02142025-0212026-02
Citations at each Life Safety survey
Survey dateCitations
February 9, 20242
February 5, 202514
February 19, 20261

Most-cited tags

Most-cited tags at this facility
K-07123K-03452K-03531K-03741K-09181K-09141K-03111K-03631
Most-cited tags at this facility
TagWhat the surveyor checksTimes citedLast cited
K-0712Have simulated fire drills held at unexpected times.32026-02-19
K-0345Have approved installation, maintenance and testing program for fire alarm systems.22025-02-05
K-0353Inspect, test, and maintain automatic sprinkler systems.12025-02-05
K-0374Install smoke barrier doors that can resist smoke for at least 20 minutes.12025-02-05
K-0918Have generator or other power source capable of supplying service within 10 seconds.12025-02-05
K-0914Ensure receptacles at patient bed locations and where general anesthesia is administered, are tested after initial installation, replacement or servicing.12025-02-05
K-0311Have an enclosure around a vertical opening shaft.12025-02-05
K-0363Install corridor and hallway doors that block smoke.12025-02-05

What the citations cover

Citations by CMS category
  • Smoke Deficiencies 6
  • Miscellaneous Deficiencies 6
  • Gas, Vacuum, and Electrical Systems Deficiencies 3
  • Egress Deficiencies 1
  • Other 1
Citations by CMS category
CategoryCitations
Smoke Deficiencies6
Miscellaneous Deficiencies6
Gas, Vacuum, and Electrical Systems Deficiencies3
Egress Deficiencies1
Services Deficiencies1

Every citation on file

As published by CMS, newest survey first. Descriptions are CMS’s own wording.

February 19, 2026 — 1 citation

Citations issued on February 19, 2026
TagWhat the surveyor checksStatus
K-0712Have simulated fire drills held at unexpected times.Deficient, Provider has date of correction (March 25, 2026)

February 5, 2025 — 14 citations

Citations issued on February 5, 2025
TagWhat the surveyor checksStatus
K-0225Have stairways and smokeproof enclosures used as exits that meet safety requirements.Deficient, Provider has date of correction (March 5, 2025)
K-0311Have an enclosure around a vertical opening shaft.Deficient, Provider has date of correction (March 24, 2025)
K-0345Have approved installation, maintenance and testing program for fire alarm systems.Deficient, Provider has date of correction (March 5, 2025)
K-0353Inspect, test, and maintain automatic sprinkler systems.Deficient, Provider has date of correction (March 20, 2025)
K-0363Install corridor and hallway doors that block smoke.Deficient, Provider has date of correction (March 5, 2025)
K-0374Install smoke barrier doors that can resist smoke for at least 20 minutes.Deficient, Provider has date of correction (March 24, 2025)
K-0531Have elevators that firefighters can control in the event of a fire.Deficient, Provider has date of correction (March 5, 2025)
K-0711Provide a written emergency evacuation plan.Deficient, Provider has date of correction (March 24, 2025)
K-0712Have simulated fire drills held at unexpected times.Deficient, Provider has date of correction (March 24, 2025)
K-0761To conduct inspection, testing and maintenance of fire doors by qualified individuals.Deficient, Provider has date of correction (March 24, 2025)
K-0781Have restrictions on the use of portable space heaters.Deficient, Provider has date of correction (March 5, 2025)
K-0912Have power receptacles that are properly grounded.Deficient, Provider has date of correction (March 5, 2025)
K-0914Ensure receptacles at patient bed locations and where general anesthesia is administered, are tested after initial installation, replacement or servicing.Deficient, Provider has date of correction (March 5, 2025)
K-0918Have generator or other power source capable of supplying service within 10 seconds.Deficient, Provider has date of correction (March 20, 2025)

February 9, 2024 — 2 citations

Citations issued on February 9, 2024
TagWhat the surveyor checksStatus
K-0345Have approved installation, maintenance and testing program for fire alarm systems.Deficient, Provider has date of correction (March 13, 2024)
K-0712Have simulated fire drills held at unexpected times.Deficient, Provider has date of correction (March 13, 2024)

Reflects the CMS posting of August 1, 2026. Surveys conducted in the last few months may not appear yet.