Federal nursing home survey record · CMS-certified nursing home· Not a state assisted-living licensing record

NEW MARK REHAB AND HEALTHCARE CENTER

KANSAS CITY, MO · 199 certified beds · Last Life Safety survey November 21, 2025

CMS Certification Number 265308 · first certified January 1987

Ownership

Operated by AMA HOLDINGS · For profit - Limited Liability company

  • Ownership changed September 1, 2024 (change of ownership)from NM OF NASHUA LLC
41
Citations on file
Rolling three-year window
4
Life Safety surveys
In the same window
12
Tags cited more than once
Across separate surveys
19
Inspection & testing records
Of the citations on file

Position within MO

41 citations — more than 93% of the 487 certified nursing homes in MO. Compared within MO rather than nationally because which state a facility is in explains about 30% of the variation in citation counts between facilities, while bed count explains under 1%. State survey agencies differ far more than the buildings do. How this is calculated

Improvingfewer citations at the latest survey than at its earlier surveys in the window.

The latest survey found 1 citation; the earlier surveys in the window averaged 13.3. With 4 surveys on file this is a direction of travel, not a conclusion.

When is the next survey likely?

The window opens January 2027 — about 4 months from now. This facility’s last Life Safety survey was November 2025. Facilities in MO are typically surveyed 14–21 months after the last one (median 17), measured over 567 consecutive surveys in the last two years of CMS records.

A range the record supports, not a prediction of a date. State agencies vary widely — from about 11 months in Pennsylvania to three years in Maryland. How the window is measured

Get an email about NEW MARK REHAB AND HEALTHCARE CENTER

One email when it happens. No account; stop it any time with one click.

Which alerts

7 inspection-and-testing tags have been cited here at more than one survey. Nationally, that pattern is common: about three quarters of cited facilities have at least one repeated tag, and half of the facilities ever cited for sprinkler inspection and testing are cited for it again. A repeat is usually a recordkeeping gap rather than a new hazard.

Emergency preparedness

4 of the 41 citations on file are Emergency Preparedness E-tags. E-tags are cited under 42 CFR §483.73 and concern the emergency plan, training, drills, communications and supplies. Nationally about half of certified facilities have at least one. The Emergency Preparedness Index

Physical environment (health survey)

8 physical-environment citations on the health survey. Cited by the health surveyors under Appendix PP, not the Life Safety Code surveyor: equipment in safe operating condition, the call system, bed rails, pest control, hazards, the environment. Counted separately from the 41 Life Safety citations above. The Physical Environment Index

  • F-0584 Honor the resident's right to a safe, clean, comfortable and homelike environment, including but not limited to receiving treatment and supports for daily living safely.
  • F-0689 Ensure that a nursing home area is free from accident hazards and provides adequate supervision to prevent accidents.
  • F-0908 Keep all essential equipment working safely.
  • F-0880 Provide and implement an infection prevention and control program.
  • F-0909 Regularly inspect all bed frames, mattresses, and bed rails (if any) for safety; and all bed rails and mattresses must attach safely to the bed frame.

How that compares

Citations on file over three years

Compared with the median facility in MO, and nationally. Surveyors differ markedly between states, so the MO figure is the meaningful one.

This facility41MO median18National median11
Citations on file over three years, compared
MeasureCitations
This facility41
Median facility in MO18
Median facility nationally11

Survey history

Citations at each Life Safety survey
222022-0972024-04112025-0612025-11
Citations at each Life Safety survey
Survey dateCitations
September 29, 202222
April 11, 20247
June 19, 202511
November 21, 20251

Most-cited tags

Most-cited tags at this facility
K-02112K-09182K-05112K-09142K-03722K-03212E-00152K-09202
Most-cited tags at this facility
TagWhat the surveyor checksTimes citedLast cited
K-0211Keep aisles, corridors, and exits free of obstruction in case of emergency.22025-06-19
K-0918Have generator or other power source capable of supplying service within 10 seconds.22025-06-19
K-0511Have properly installed electrical wiring and gas equipment.22024-04-11
K-0914Ensure receptacles at patient bed locations and where general anesthesia is administered, are tested after initial installation, replacement or servicing.22025-06-19
K-0372Ensure smoke barriers are constructed to a 1 hour fire resistance rating.22025-06-19
K-0321Ensure that special areas are constructed so that walls can resist fire for one hour or have an approved fire extinguishing system.22025-06-19
E-0015Address subsistence needs for staff and patients.22025-11-21
K-0920Ensure proper usage of power strips and extension cords.22025-06-19

What the citations cover

Citations by CMS category
  • Smoke Deficiencies 14
  • Egress Deficiencies 7
  • Gas, Vacuum, and Electrical Systems Deficiencies 6
  • Emergency Preparedness Deficiencies 4
  • Other 10
Citations by CMS category
CategoryCitations
Smoke Deficiencies14
Egress Deficiencies7
Gas, Vacuum, and Electrical Systems Deficiencies6
Emergency Preparedness Deficiencies4
Services Deficiencies4
Miscellaneous Deficiencies4
Electrical Deficiencies1
Construction Deficiencies1

Every citation on file

As published by CMS, newest survey first. Descriptions are CMS’s own wording.

November 21, 2025 — 1 citation

Citations issued on November 21, 2025
TagWhat the surveyor checksStatus
E-0015Address subsistence needs for staff and patients.Deficient, Provider has date of correction (November 22, 2025)

June 19, 2025 — 11 citations

Citations issued on June 19, 2025
TagWhat the surveyor checksStatus
K-0211Keep aisles, corridors, and exits free of obstruction in case of emergency.Deficient, Provider has date of correction (July 29, 2025)
K-0293Have properly located and lighted "Exit" signs.Deficient, Provider has date of correction (July 29, 2025)
K-0321Ensure that special areas are constructed so that walls can resist fire for one hour or have an approved fire extinguishing system.Deficient, Provider has date of correction (July 29, 2025)
K-0324Provide properly protected cooking facilities.Deficient, Provider has date of correction (July 29, 2025)
K-0345Have approved installation, maintenance and testing program for fire alarm systems.Deficient, Provider has date of correction (July 29, 2025)
K-0355Properly select, install, inspect, or maintain portable fire extinguishes.Deficient, Provider has date of correction (July 29, 2025)
K-0372Ensure smoke barriers are constructed to a 1 hour fire resistance rating.Deficient, Provider has date of correction (July 29, 2025)
K-0712Have simulated fire drills held at unexpected times.Deficient, Provider has date of correction (July 29, 2025)
K-0914Ensure receptacles at patient bed locations and where general anesthesia is administered, are tested after initial installation, replacement or servicing.Deficient, Provider has date of correction (July 29, 2025)
K-0918Have generator or other power source capable of supplying service within 10 seconds.Deficient, Provider has date of correction (July 29, 2025)
K-0920Ensure proper usage of power strips and extension cords.Deficient, Provider has date of correction (July 29, 2025)

April 11, 2024 — 7 citations

Citations issued on April 11, 2024
TagWhat the surveyor checksStatus
K-0271Have exits that are accessible at all times.Waiver has been granted
K-0291Install emergency lighting that can last at least 1 1/2 hours.Deficient, Provider has date of correction (May 22, 2024)
K-0311Have an enclosure around a vertical opening shaft.Waiver has been granted
K-0353Inspect, test, and maintain automatic sprinkler systems.Deficient, Provider has date of correction (May 22, 2024)
K-0361Ensure that waiting areas, nurse’s stations, gift shops, and cooking facilities, open to the corridor are properly protected.Deficient, Provider has date of correction (May 22, 2024)
K-0511Have properly installed electrical wiring and gas equipment.Deficient, Provider has date of correction (May 22, 2024)
K-0761To conduct inspection, testing and maintenance of fire doors by qualified individuals.Deficient, Provider has date of correction (May 22, 2024)

September 29, 2022 — 22 citations

Citations issued on September 29, 2022
TagWhat the surveyor checksStatus
E-0004Develop and maintain an Emergency Preparedness Program (EP).Deficient, Provider has date of correction (November 11, 2022)
E-0015Address subsistence needs for staff and patients.Deficient, Provider has date of correction (November 11, 2022)
E-0039Conduct testing and exercise requirements.Deficient, Provider has date of correction (November 11, 2022)
K-0161Use approved construction type or materials.Deficient, Provider has date of correction (January 10, 2023)
K-0211Keep aisles, corridors, and exits free of obstruction in case of emergency.Deficient, Provider has date of correction (November 11, 2022)
K-0225Have stairways and smokeproof enclosures used as exits that meet safety requirements.Deficient, Provider has date of correction (November 11, 2022)
K-0291Install emergency lighting that can last at least 1 1/2 hours.Deficient, Provider has date of correction (November 11, 2022)
K-0321Ensure that special areas are constructed so that walls can resist fire for one hour or have an approved fire extinguishing system.Deficient, Provider has date of correction (November 11, 2022)
K-0345Have approved installation, maintenance and testing program for fire alarm systems.Deficient, Provider has date of correction (November 11, 2022)
K-0353Inspect, test, and maintain automatic sprinkler systems.Deficient, Provider has date of correction (November 28, 2022)
K-0354Follow proper procedures when the automatic sprinkler systems was out of service for more than 10 hours.Deficient, Provider has date of correction (November 11, 2022)
K-0363Install corridor and hallway doors that block smoke.Deficient, Provider has date of correction (November 11, 2022)
K-0372Ensure smoke barriers are constructed to a 1 hour fire resistance rating.Waiver has been granted (January 10, 2023)
K-0511Have properly installed electrical wiring and gas equipment.Deficient, Provider has date of correction (November 11, 2022)
K-0521Ensure heating and ventilation systems that have been properly installed according to the manufacturer's instructions.Deficient, Provider has date of correction (November 11, 2022)
K-0531Have elevators that firefighters can control in the event of a fire.Deficient, Provider has date of correction (November 11, 2022)
K-0711Provide a written emergency evacuation plan.Deficient, Provider has date of correction (November 11, 2022)
K-0761To conduct inspection, testing and maintenance of fire doors by qualified individuals.Deficient, Provider has date of correction (November 28, 2022)
K-0901Ensure that building systems meet requirements determined by risk assessment procedures performed by qualified personnel.Deficient, Provider has date of correction (November 11, 2022)
K-0914Ensure receptacles at patient bed locations and where general anesthesia is administered, are tested after initial installation, replacement or servicing.Deficient, Provider has date of correction (November 11, 2022)
K-0918Have generator or other power source capable of supplying service within 10 seconds.Deficient, Provider has date of correction (November 11, 2022)
K-0920Ensure proper usage of power strips and extension cords.Deficient, Provider has date of correction (November 11, 2022)