Piedmont Hills Center for Nursing and Rehab
Greensboro, NC · 126 certified beds · Last Life Safety survey February 27, 2026
CMS Certification Number 345116 · first certified December 1980
Ownership
Operated by ALLIANCE HEALTH GROUP · For profit - Limited Liability company
- Ownership changed August 1, 2024 (change of ownership)to PIEDMONT HILLS CENTER FOR NURSING AND REHABILITATION from CAROLINA PINES AT GREENSBORO LLC
Position within NC
40 citations — more than 100% of the 419 certified nursing homes in NC. Compared within NC rather than nationally because which state a facility is in explains about 30% of the variation in citation counts between facilities, while bed count explains under 1%. State survey agencies differ far more than the buildings do. How this is calculated
The latest survey found 12 citations; the earlier surveys in the window averaged 14. With 3 surveys on file this is a direction of travel, not a conclusion.
When is the next survey likely?
The window opens April 2027 — about 7 months from now. This facility’s last Life Safety survey was February 2026. Facilities in NC are typically surveyed 14–16 months after the last one (median 15), measured over 412 consecutive surveys in the last two years of CMS records.
A range the record supports, not a prediction of a date. State agencies vary widely — from about 11 months in Pennsylvania to three years in Maryland. How the window is measured
Get an email about Piedmont Hills Center for Nursing and Rehab
One email when it happens. No account; stop it any time with one click.
7 inspection-and-testing tags have been cited here at more than one survey. Nationally, that pattern is common: about three quarters of cited facilities have at least one repeated tag, and half of the facilities ever cited for sprinkler inspection and testing are cited for it again. A repeat is usually a recordkeeping gap rather than a new hazard.
Physical environment (health survey)
5 physical-environment citations on the health survey. Cited by the health surveyors under Appendix PP, not the Life Safety Code surveyor: equipment in safe operating condition, the call system, bed rails, pest control, hazards, the environment. Counted separately from the 40 Life Safety citations above. The Physical Environment Index
- F-0689 Ensure that a nursing home area is free from accident hazards and provides adequate supervision to prevent accidents.
- F-0584 Honor the resident's right to a safe, clean, comfortable and homelike environment, including but not limited to receiving treatment and supports for daily living safely.
- F-0880 Provide and implement an infection prevention and control program.
How that compares
Compared with the median facility in NC, and nationally. Surveyors differ markedly between states, so the NC figure is the meaningful one.
| Measure | Citations |
|---|---|
| This facility | 40 |
| Median facility in NC | 9 |
| Median facility nationally | 11 |
Survey history
| Survey date | Citations |
|---|---|
| December 4, 2023 | 18 |
| December 5, 2024 | 10 |
| February 27, 2026 | 12 |
Most-cited tags
| Tag | What the surveyor checks | Times cited | Last cited |
|---|---|---|---|
| K-0363 | Install corridor and hallway doors that block smoke. | 3 | 2026-02-27 |
| K-0918 | Have generator or other power source capable of supplying service within 10 seconds. | 3 | 2026-02-27 |
| K-0321 | Ensure that special areas are constructed so that walls can resist fire for one hour or have an approved fire extinguishing system. | 3 | 2026-02-27 |
| K-0372 | Ensure smoke barriers are constructed to a 1 hour fire resistance rating. | 2 | 2026-02-27 |
| K-0161 | Use approved construction type or materials. | 2 | 2026-02-27 |
| K-0914 | Ensure receptacles at patient bed locations and where general anesthesia is administered, are tested after initial installation, replacement or servicing. | 2 | 2026-02-27 |
| K-0531 | Have elevators that firefighters can control in the event of a fire. | 2 | 2026-02-27 |
| K-0211 | Keep aisles, corridors, and exits free of obstruction in case of emergency. | 2 | 2026-02-27 |
What the citations cover
- Smoke Deficiencies 16
- Gas, Vacuum, and Electrical Systems Deficiencies 8
- Egress Deficiencies 6
- Services Deficiencies 5
- Other 5
| Category | Citations |
|---|---|
| Smoke Deficiencies | 16 |
| Gas, Vacuum, and Electrical Systems Deficiencies | 8 |
| Egress Deficiencies | 6 |
| Services Deficiencies | 5 |
| Construction Deficiencies | 3 |
| Miscellaneous Deficiencies | 2 |
Every citation on file
As published by CMS, newest survey first. Descriptions are CMS’s own wording.
February 27, 2026 — 12 citations
| Tag | What the surveyor checks | Status |
|---|---|---|
| K-0161 | Use approved construction type or materials. | Deficient, Provider has plan of correction (August 14, 2026) |
| K-0211 | Keep aisles, corridors, and exits free of obstruction in case of emergency. | Deficient, Provider has plan of correction (August 14, 2026) |
| K-0291 | Install emergency lighting that can last at least 1 1/2 hours. | Deficient, Provider has plan of correction (August 14, 2026) |
| K-0321 | Ensure that special areas are constructed so that walls can resist fire for one hour or have an approved fire extinguishing system. | Deficient, Provider has plan of correction (August 14, 2026) |
| K-0342 | Have a complete alarm system manually initiated and initiated by fire sprinkler system connection. | Deficient, Provider has plan of correction (August 14, 2026) |
| K-0345 | Have approved installation, maintenance and testing program for fire alarm systems. | Deficient, Provider has plan of correction (August 14, 2026) |
| K-0363 | Install corridor and hallway doors that block smoke. | Deficient, Provider has plan of correction (August 14, 2026) |
| K-0372 | Ensure smoke barriers are constructed to a 1 hour fire resistance rating. | Deficient, Provider has plan of correction (August 14, 2026) |
| K-0531 | Have elevators that firefighters can control in the event of a fire. | Deficient, Provider has plan of correction (August 14, 2026) |
| K-0914 | Ensure receptacles at patient bed locations and where general anesthesia is administered, are tested after initial installation, replacement or servicing. | Deficient, Provider has plan of correction (August 14, 2026) |
| K-0918 | Have generator or other power source capable of supplying service within 10 seconds. | Deficient, Provider has plan of correction (August 14, 2026) |
| K-0920 | Ensure proper usage of power strips and extension cords. | Deficient, Provider has plan of correction (August 14, 2026) |
December 5, 2024 — 10 citations
| Tag | What the surveyor checks | Status |
|---|---|---|
| K-0225 | Have stairways and smokeproof enclosures used as exits that meet safety requirements. | Deficient, Provider has date of correction (April 17, 2025) |
| K-0291 | Install emergency lighting that can last at least 1 1/2 hours. | Deficient, Provider has date of correction (April 17, 2025) |
| K-0321 | Ensure that special areas are constructed so that walls can resist fire for one hour or have an approved fire extinguishing system. | Deficient, Provider has date of correction (April 17, 2025) |
| K-0363 | Install corridor and hallway doors that block smoke. | Deficient, Provider has date of correction (April 17, 2025) |
| K-0521 | Ensure heating and ventilation systems that have been properly installed according to the manufacturer's instructions. | Deficient, Provider has date of correction (April 17, 2025) |
| K-0531 | Have elevators that firefighters can control in the event of a fire. | Deficient, Provider has date of correction (April 17, 2025) |
| K-0712 | Have simulated fire drills held at unexpected times. | Deficient, Provider has date of correction (April 17, 2025) |
| K-0781 | Have restrictions on the use of portable space heaters. | Deficient, Provider has date of correction (April 17, 2025) |
| K-0918 | Have generator or other power source capable of supplying service within 10 seconds. | Deficient, Provider has date of correction (April 17, 2025) |
| K-0923 | Have proper medical gas storage and administration areas. | Deficient, Provider has date of correction (April 17, 2025) |
December 4, 2023 — 18 citations
| Tag | What the surveyor checks | Status |
|---|---|---|
| K-0100 | Meet other general requirements. | Deficient, Provider has date of correction (March 20, 2024) |
| K-0161 | Use approved construction type or materials. | Deficient, Provider has date of correction (March 20, 2024) |
| K-0211 | Keep aisles, corridors, and exits free of obstruction in case of emergency. | Deficient, Provider has date of correction (March 20, 2024) |
| K-0225 | Have stairways and smokeproof enclosures used as exits that meet safety requirements. | Deficient, Provider has date of correction (March 20, 2024) |
| K-0311 | Have an enclosure around a vertical opening shaft. | Deficient, Provider has date of correction (March 20, 2024) |
| K-0321 | Ensure that special areas are constructed so that walls can resist fire for one hour or have an approved fire extinguishing system. | Deficient, Provider has date of correction (March 20, 2024) |
| K-0324 | Provide properly protected cooking facilities. | Deficient, Provider has date of correction (March 20, 2024) |
| K-0345 | Have approved installation, maintenance and testing program for fire alarm systems. | Deficient, Provider has date of correction (March 20, 2024) |
| K-0353 | Inspect, test, and maintain automatic sprinkler systems. | Deficient, Provider has date of correction (March 20, 2024) |
| K-0363 | Install corridor and hallway doors that block smoke. | Deficient, Provider has date of correction (March 20, 2024) |
| K-0364 | Install properly constructed windows in hallway walls or doors. | Deficient, Provider has date of correction (March 20, 2024) |
| K-0372 | Ensure smoke barriers are constructed to a 1 hour fire resistance rating. | Deficient, Provider has date of correction (March 20, 2024) |
| K-0374 | Install smoke barrier doors that can resist smoke for at least 20 minutes. | Deficient, Provider has date of correction (March 20, 2024) |
| K-0511 | Have properly installed electrical wiring and gas equipment. | Deficient, Provider has date of correction (March 20, 2024) |
| K-0521 | Ensure heating and ventilation systems that have been properly installed according to the manufacturer's instructions. | Deficient, Provider has date of correction (March 20, 2024) |
| K-0914 | Ensure receptacles at patient bed locations and where general anesthesia is administered, are tested after initial installation, replacement or servicing. | Deficient, Provider has date of correction (March 20, 2024) |
| K-0918 | Have generator or other power source capable of supplying service within 10 seconds. | Deficient, Provider has date of correction (March 20, 2024) |
| K-0923 | Have proper medical gas storage and administration areas. | Deficient, Provider has date of correction (March 20, 2024) |
Reflects the CMS posting of August 1, 2026. Surveys conducted in the last few months may not appear yet.