Federal nursing home survey record · CMS-certified nursing home· Not a state assisted-living licensing record
Stratford Manor Health & Rehab
Monroe, NC · 60 certified beds · Last Life Safety survey April 10, 2025
CMS Certification Number 345345 · first certified January 1991
Ownership
Independently operated (no chain recorded by CMS) · For profit - Limited Liability company
- Ownership changed February 1, 2019 (change of ownership)to ACCORDIUS HEALTH AT MONROE LLC from SSC MONROE OPERATING COMPANY LLC
Position within NC
14 citations — more than 71% of the 419 certified nursing homes in NC. Compared within NC rather than nationally because which state a facility is in explains about 30% of the variation in citation counts between facilities, while bed count explains under 1%. State survey agencies differ far more than the buildings do. How this is calculated
The latest survey found 1 citation; the earlier surveys in the window averaged 6.5. With 3 surveys on file this is a direction of travel, not a conclusion.
When is the next survey likely?
Well past the typical window (June 2026 to August 2026), and past the point by which nine in ten NC facilities have been surveyed. This facility’s last Life Safety survey was April 2025. Facilities in NC are typically surveyed 14–16 months after the last one (median 15), measured over 412 consecutive surveys in the last two years of CMS records.
A range the record supports, not a prediction of a date. State agencies vary widely — from about 11 months in Pennsylvania to three years in Maryland. How the window is measured
Get an email about Stratford Manor Health & Rehab
One email when it happens. No account; stop it any time with one click.
1 inspection-and-testing tag has been cited here at more than one survey. Nationally, that pattern is common: about three quarters of cited facilities have at least one repeated tag, and half of the facilities ever cited for sprinkler inspection and testing are cited for it again. A repeat is usually a recordkeeping gap rather than a new hazard.
Physical environment (health survey)
4 physical-environment citations on the health survey. Cited by the health surveyors under Appendix PP, not the Life Safety Code surveyor: equipment in safe operating condition, the call system, bed rails, pest control, hazards, the environment. Counted separately from the 14 Life Safety citations above. The Physical Environment Index
How that compares
Compared with the median facility in NC, and nationally. Surveyors differ markedly between states, so the NC figure is the meaningful one.
| Measure | Citations |
|---|---|
| This facility | 14 |
| Median facility in NC | 9 |
| Median facility nationally | 11 |
Survey history
| Survey date | Citations |
|---|---|
| June 17, 2022 | 3 |
| November 30, 2023 | 10 |
| April 10, 2025 | 1 |
Most-cited tags
| Tag | What the surveyor checks | Times cited | Last cited |
|---|---|---|---|
| K-0321 | Ensure that special areas are constructed so that walls can resist fire for one hour or have an approved fire extinguishing system. | 3 | 2025-04-10 |
| K-0521 | Ensure heating and ventilation systems that have been properly installed according to the manufacturer's instructions. | 2 | 2023-11-30 |
| K-0511 | Have properly installed electrical wiring and gas equipment. | 1 | 2023-11-30 |
| K-0363 | Install corridor and hallway doors that block smoke. | 1 | 2023-11-30 |
| K-0222 | Add doors in an exit area that do not require the use of a key from the exit side unless in case of special locking arrangements. | 1 | 2023-11-30 |
| K-0918 | Have generator or other power source capable of supplying service within 10 seconds. | 1 | 2023-11-30 |
| K-0324 | Provide properly protected cooking facilities. | 1 | 2023-11-30 |
| K-0161 | Use approved construction type or materials. | 1 | 2022-06-17 |
What the citations cover
- Smoke Deficiencies 7
- Services Deficiencies 3
- Egress Deficiencies 2
- Gas, Vacuum, and Electrical Systems Deficiencies 1
- Other 1
| Category | Citations |
|---|---|
| Smoke Deficiencies | 7 |
| Services Deficiencies | 3 |
| Egress Deficiencies | 2 |
| Gas, Vacuum, and Electrical Systems Deficiencies | 1 |
| Construction Deficiencies | 1 |
Every citation on file
As published by CMS, newest survey first. Descriptions are CMS’s own wording.
April 10, 2025 — 1 citation
| Tag | What the surveyor checks | Status |
|---|---|---|
| K-0321 | Ensure that special areas are constructed so that walls can resist fire for one hour or have an approved fire extinguishing system. | Deficient, Provider has date of correction (June 2, 2025) |
November 30, 2023 — 10 citations
| Tag | What the surveyor checks | Status |
|---|---|---|
| K-0222 | Add doors in an exit area that do not require the use of a key from the exit side unless in case of special locking arrangements. | Deficient, Provider has date of correction (February 8, 2024) |
| K-0291 | Install emergency lighting that can last at least 1 1/2 hours. | Deficient, Provider has date of correction (February 8, 2024) |
| K-0321 | Ensure that special areas are constructed so that walls can resist fire for one hour or have an approved fire extinguishing system. | Deficient, Provider has date of correction (February 8, 2024) |
| K-0324 | Provide properly protected cooking facilities. | Deficient, Provider has date of correction (February 8, 2024) |
| K-0353 | Inspect, test, and maintain automatic sprinkler systems. | Deficient, Provider has date of correction (February 8, 2024) |
| K-0355 | Properly select, install, inspect, or maintain portable fire extinguishes. | Deficient, Provider has date of correction (February 8, 2024) |
| K-0363 | Install corridor and hallway doors that block smoke. | Deficient, Provider has date of correction (February 8, 2024) |
| K-0511 | Have properly installed electrical wiring and gas equipment. | Deficient, Provider has date of correction (February 8, 2024) |
| K-0521 | Ensure heating and ventilation systems that have been properly installed according to the manufacturer's instructions. | Deficient, Provider has date of correction (February 8, 2024) |
| K-0918 | Have generator or other power source capable of supplying service within 10 seconds. | Deficient, Provider has date of correction (February 8, 2024) |
June 17, 2022 — 3 citations
| Tag | What the surveyor checks | Status |
|---|---|---|
| K-0161 | Use approved construction type or materials. | Deficient, Provider has date of correction (August 28, 2022) |
| K-0321 | Ensure that special areas are constructed so that walls can resist fire for one hour or have an approved fire extinguishing system. | Deficient, Provider has date of correction (August 28, 2022) |
| K-0521 | Ensure heating and ventilation systems that have been properly installed according to the manufacturer's instructions. | Deficient, Provider has date of correction (August 28, 2022) |
Reflects the CMS posting of August 1, 2026. Surveys conducted in the last few months may not appear yet.