Federal nursing home survey record · CMS-certified nursing home· Not a state assisted-living licensing record
CAREONE AT RIDGEWOOD AVENUE
PARAMUS, NJ · 110 certified beds · Last Life Safety survey June 4, 2025
CMS Certification Number 315426 · first certified May 1998
Ownership
Operated by CAREONE · For profit - Corporation
No change of ownership on CMS record since January 1, 2016, when the records begin.
Position within NJ
14 citations — more than 44% of the 348 certified nursing homes in NJ. Compared within NJ rather than nationally because which state a facility is in explains about 30% of the variation in citation counts between facilities, while bed count explains under 1%. State survey agencies differ far more than the buildings do. How this is calculated
The latest survey found 9 citations; the earlier surveys in the window averaged 2.5. With 3 surveys on file this is a direction of travel, not a conclusion.
When is the next survey likely?
The window is open now: September 2026 to February 2027. This facility’s last Life Safety survey was June 2025. Facilities in NJ are typically surveyed 16–20 months after the last one (median 17), measured over 431 consecutive surveys in the last two years of CMS records.
A range the record supports, not a prediction of a date. State agencies vary widely — from about 11 months in Pennsylvania to three years in Maryland. How the window is measured
Get an email about CAREONE AT RIDGEWOOD AVENUE
One email when it happens. No account; stop it any time with one click.
Physical environment (health survey)
1 physical-environment citation on the health survey. Cited by the health surveyors under Appendix PP, not the Life Safety Code surveyor: equipment in safe operating condition, the call system, bed rails, pest control, hazards, the environment. Counted separately from the 14 Life Safety citations above. The Physical Environment Index
- F-0689 Ensure that a nursing home area is free from accident hazards and provides adequate supervision to prevent accidents.
How that compares
Compared with the median facility in NJ, and nationally. Surveyors differ markedly between states, so the NJ figure is the meaningful one.
| Measure | Citations |
|---|---|
| This facility | 14 |
| Median facility in NJ | 15 |
| Median facility nationally | 11 |
Survey history
| Survey date | Citations |
|---|---|
| June 30, 2021 | 1 |
| September 28, 2023 | 4 |
| June 4, 2025 | 9 |
Most-cited tags
| Tag | What the surveyor checks | Times cited | Last cited |
|---|---|---|---|
| K-0341 | Install a fire alarm system that can be heard throughout the facility. | 2 | 2025-06-04 |
| K-0324 | Provide properly protected cooking facilities. | 1 | 2023-09-28 |
| K-0531 | Have elevators that firefighters can control in the event of a fire. | 1 | 2025-06-04 |
| K-0347 | Properly provide smoke detection systems in areas open to corridors. | 1 | 2025-06-04 |
| K-0225 | Have stairways and smokeproof enclosures used as exits that meet safety requirements. | 1 | 2025-06-04 |
| K-0918 | Have generator or other power source capable of supplying service within 10 seconds. | 1 | 2025-06-04 |
| K-0351 | Install an approved automatic sprinkler system. | 1 | 2025-06-04 |
| K-0321 | Ensure that special areas are constructed so that walls can resist fire for one hour or have an approved fire extinguishing system. | 1 | 2025-06-04 |
What the citations cover
- Smoke Deficiencies 8
- Egress Deficiencies 3
- Gas, Vacuum, and Electrical Systems Deficiencies 2
- Services Deficiencies 1
| Category | Citations |
|---|---|
| Smoke Deficiencies | 8 |
| Egress Deficiencies | 3 |
| Gas, Vacuum, and Electrical Systems Deficiencies | 2 |
| Services Deficiencies | 1 |
Every citation on file
As published by CMS, newest survey first. Descriptions are CMS’s own wording.
June 4, 2025 — 9 citations
| Tag | What the surveyor checks | Status |
|---|---|---|
| K-0222 | Add doors in an exit area that do not require the use of a key from the exit side unless in case of special locking arrangements. | Deficient, Provider has date of correction (July 20, 2025) |
| K-0225 | Have stairways and smokeproof enclosures used as exits that meet safety requirements. | Deficient, Provider has date of correction (July 20, 2025) |
| K-0321 | Ensure that special areas are constructed so that walls can resist fire for one hour or have an approved fire extinguishing system. | Deficient, Provider has date of correction (July 20, 2025) |
| K-0341 | Install a fire alarm system that can be heard throughout the facility. | Deficient, Provider has date of correction (July 20, 2025) |
| K-0347 | Properly provide smoke detection systems in areas open to corridors. | Deficient, Provider has date of correction (July 20, 2025) |
| K-0351 | Install an approved automatic sprinkler system. | Deficient, Provider has date of correction (July 20, 2025) |
| K-0363 | Install corridor and hallway doors that block smoke. | Deficient, Provider has date of correction (July 20, 2025) |
| K-0531 | Have elevators that firefighters can control in the event of a fire. | Deficient, Provider has date of correction (July 20, 2025) |
| K-0918 | Have generator or other power source capable of supplying service within 10 seconds. | Deficient, Provider has date of correction (July 20, 2025) |
September 28, 2023 — 4 citations
| Tag | What the surveyor checks | Status |
|---|---|---|
| K-0324 | Provide properly protected cooking facilities. | Deficient, Provider has date of correction (October 11, 2023) |
| K-0341 | Install a fire alarm system that can be heard throughout the facility. | Deficient, Provider has date of correction (October 16, 2023) |
| K-0372 | Ensure smoke barriers are constructed to a 1 hour fire resistance rating. | Deficient, Provider has date of correction (October 16, 2023) |
| K-0911 | Meet requirements for the installation and maintenance of electrical systems. | Deficient, Provider has date of correction (October 16, 2023) |
June 30, 2021 — 1 citation
| Tag | What the surveyor checks | Status |
|---|---|---|
| K-0281 | Install proper backup exit lighting. | Deficient, Provider has date of correction (July 28, 2021) |