Federal nursing home survey record · CMS-certified nursing home· Not a state assisted-living licensing record
OHMAN FAMILY LIVING AT HOLLY
NEWBURY, OH · 92 certified beds · Last Life Safety survey December 11, 2025
CMS Certification Number 365947 · first certified January 1994
Ownership
Independently operated (no chain recorded by CMS) · For profit - Corporation
No change of ownership on CMS record since January 1, 2016, when the records begin.
Position within OH
18 citations — more than 57% of the 922 certified nursing homes in OH. Compared within OH rather than nationally because which state a facility is in explains about 30% of the variation in citation counts between facilities, while bed count explains under 1%. State survey agencies differ far more than the buildings do. How this is calculated
The latest survey found 4 citations; the earlier surveys in the window averaged 7. With 3 surveys on file this is a direction of travel, not a conclusion.
When is the next survey likely?
The window opens August 2027 — about 10 months from now. This facility’s last Life Safety survey was December 2025. Facilities in OH are typically surveyed 20–32 months after the last one (median 26), measured over 889 consecutive surveys in the last two years of CMS records.
A range the record supports, not a prediction of a date. State agencies vary widely — from about 11 months in Pennsylvania to three years in Maryland. How the window is measured
Get an email about OHMAN FAMILY LIVING AT HOLLY
One email when it happens. No account; stop it any time with one click.
1 inspection-and-testing tag has been cited here at more than one survey. Nationally, that pattern is common: about three quarters of cited facilities have at least one repeated tag, and half of the facilities ever cited for sprinkler inspection and testing are cited for it again. A repeat is usually a recordkeeping gap rather than a new hazard.
Physical environment (health survey)
2 physical-environment citations on the health survey. Cited by the health surveyors under Appendix PP, not the Life Safety Code surveyor: equipment in safe operating condition, the call system, bed rails, pest control, hazards, the environment. Counted separately from the 18 Life Safety citations above. The Physical Environment Index
How that compares
Compared with the median facility in OH, and nationally. Surveyors differ markedly between states, so the OH figure is the meaningful one.
| Measure | Citations |
|---|---|
| This facility | 18 |
| Median facility in OH | 16 |
| Median facility nationally | 11 |
Survey history
| Survey date | Citations |
|---|---|
| February 27, 2020 | 9 |
| February 16, 2023 | 5 |
| December 11, 2025 | 4 |
Most-cited tags
| Tag | What the surveyor checks | Times cited | Last cited |
|---|---|---|---|
| K-0222 | Add doors in an exit area that do not require the use of a key from the exit side unless in case of special locking arrangements. | 2 | 2025-12-11 |
| K-0918 | Have generator or other power source capable of supplying service within 10 seconds. | 2 | 2023-02-16 |
| K-0915 | Have proper power supply for life support equipment. | 1 | 2025-12-11 |
| K-0353 | Inspect, test, and maintain automatic sprinkler systems. | 1 | 2023-02-16 |
| K-0291 | Install emergency lighting that can last at least 1 1/2 hours. | 1 | 2025-12-11 |
| K-0361 | Ensure that waiting areas, nurse’s stations, gift shops, and cooking facilities, open to the corridor are properly protected. | 1 | 2025-12-11 |
| K-0363 | Install corridor and hallway doors that block smoke. | 1 | 2020-02-27 |
| K-0352 | Properly install and monitor supervisory attachments on automatic sprinkler systems. | 1 | 2020-02-27 |
What the citations cover
- Smoke Deficiencies 8
- Egress Deficiencies 4
- Gas, Vacuum, and Electrical Systems Deficiencies 4
- Services Deficiencies 1
- Other 1
| Category | Citations |
|---|---|
| Smoke Deficiencies | 8 |
| Egress Deficiencies | 4 |
| Gas, Vacuum, and Electrical Systems Deficiencies | 4 |
| Services Deficiencies | 1 |
| Construction Deficiencies | 1 |
Every citation on file
As published by CMS, newest survey first. Descriptions are CMS’s own wording.
December 11, 2025 — 4 citations
| Tag | What the surveyor checks | Status |
|---|---|---|
| K-0222 | Add doors in an exit area that do not require the use of a key from the exit side unless in case of special locking arrangements. | Deficient, Provider has date of correction (January 15, 2026) |
| K-0291 | Install emergency lighting that can last at least 1 1/2 hours. | Deficient, Provider has date of correction (January 15, 2026) |
| K-0361 | Ensure that waiting areas, nurse’s stations, gift shops, and cooking facilities, open to the corridor are properly protected. | Deficient, Provider has date of correction (January 15, 2026) |
| K-0915 | Have proper power supply for life support equipment. | Deficient, Provider has date of correction (January 15, 2026) |
February 16, 2023 — 5 citations
| Tag | What the surveyor checks | Status |
|---|---|---|
| K-0222 | Add doors in an exit area that do not require the use of a key from the exit side unless in case of special locking arrangements. | Deficient, Provider has date of correction (April 10, 2023) |
| K-0345 | Have approved installation, maintenance and testing program for fire alarm systems. | Deficient, Provider has date of correction (April 10, 2023) |
| K-0353 | Inspect, test, and maintain automatic sprinkler systems. | Deficient, Provider has date of correction (April 10, 2023) |
| K-0372 | Ensure smoke barriers are constructed to a 1 hour fire resistance rating. | Deficient, Provider has date of correction (April 10, 2023) |
| K-0918 | Have generator or other power source capable of supplying service within 10 seconds. | Deficient, Provider has date of correction (April 10, 2023) |
February 27, 2020 — 9 citations
| Tag | What the surveyor checks | Status |
|---|---|---|
| K-0161 | Use approved construction type or materials. | Deficient, Provider has date of correction (April 10, 2020) |
| K-0227 | Have ramps, exits, fire escape ladders, steps, and areas of refuge that meet safety requirements. | Deficient, Provider has date of correction (April 10, 2020) |
| K-0341 | Install a fire alarm system that can be heard throughout the facility. | Deficient, Provider has date of correction (April 10, 2020) |
| K-0344 | Have an alternate power supply for its alarm system. | Deficient, Provider has date of correction (April 10, 2020) |
| K-0352 | Properly install and monitor supervisory attachments on automatic sprinkler systems. | Deficient, Provider has date of correction (April 10, 2020) |
| K-0363 | Install corridor and hallway doors that block smoke. | Deficient, Provider has date of correction (April 10, 2020) |
| K-0521 | Ensure heating and ventilation systems that have been properly installed according to the manufacturer's instructions. | Waiver has been granted (April 10, 2020) |
| K-0914 | Ensure receptacles at patient bed locations and where general anesthesia is administered, are tested after initial installation, replacement or servicing. | Deficient, Provider has date of correction (April 10, 2020) |
| K-0918 | Have generator or other power source capable of supplying service within 10 seconds. | Deficient, Provider has date of correction (April 10, 2020) |
Reflects the CMS posting of August 1, 2026. Surveys conducted in the last few months may not appear yet.