Federal nursing home survey record · CMS-certified nursing home· Not a state assisted-living licensing record
FOUR SEASONS REHABILITATION & CARE
DURANT, OK · 122 certified beds · Last Life Safety survey May 15, 2025
CMS Certification Number 375238 · first certified September 1995
Ownership
Operated by ELMBROOK MANAGEMENT COMPANY · For profit - Individual
- Ownership changed February 26, 2021 (change of ownership)from SCG DURANT FOUR SEASONS LLC
Position within OK
9 citations — more than 60% of the 283 certified nursing homes in OK. Compared within OK rather than nationally because which state a facility is in explains about 30% of the variation in citation counts between facilities, while bed count explains under 1%. State survey agencies differ far more than the buildings do. How this is calculated
The latest survey found 4 citations; the earlier surveys on file averaged 2.5. With 3 surveys on file this is a direction of travel, not a conclusion.
When is the next survey likely?
The window is open now: July 2026 to November 2026. This facility’s last Life Safety survey was May 2025. Facilities in OK are typically surveyed 14–18 months after the last one (median 16), measured over 276 consecutive surveys in the last two years of CMS records.
A range the record supports, not a prediction of a date. State agencies vary widely — from about 11 months in Pennsylvania to about three years in Virginia. How the window is measured
Get an email about FOUR SEASONS REHABILITATION & CARE
One email when it happens. No account; stop it any time with one click.
1 inspection-and-testing tag has been cited here at more than one survey. Nationally, that pattern is common: about three quarters of cited facilities have at least one repeated tag, and half of the facilities cited for sprinkler inspection and testing in CMS’s current file are cited for it again. A repeat is usually a recordkeeping gap rather than a new hazard.
Physical environment (health survey)
2 physical-environment citations on the health survey. Cited by the health surveyors under Appendix PP, not the Life Safety Code surveyor: equipment in safe operating condition, the call system, bed rails, pest control, hazards, the environment. Counted separately from the 9 Life Safety citations above. The Physical Environment Index
How that compares
Compared with the median facility in OK, and nationally. Surveyors differ markedly between states, so the OK figure is the meaningful one.
| Measure | Citations |
|---|---|
| This facility | 9 |
| Median facility in OK | 8 |
| Median facility nationally | 11 |
Survey history
| Survey date | Citations |
|---|---|
| October 28, 2022 | 2 |
| January 29, 2024 | 3 |
| May 15, 2025 | 4 |
Most-cited tags
| Tag | What the surveyor checks | Times cited | Last cited |
|---|---|---|---|
| K-0291 | Install emergency lighting that can last at least 1 1/2 hours. | 2 | 2024-01-29 |
| K-0911 | Meet requirements for the installation and maintenance of electrical systems. | 1 | 2025-05-15 |
| K-0918 | Have generator or other power source capable of supplying service within 10 seconds. | 1 | 2025-05-15 |
| K-0344 | Have an alternate power supply for its alarm system. | 1 | 2025-05-15 |
| K-0321 | Ensure that special areas are constructed so that walls can resist fire for one hour or have an approved fire extinguishing system. | 1 | 2024-01-29 |
| K-0353 | Inspect, test, and maintain automatic sprinkler systems. | 1 | 2025-05-15 |
| K-0362 | Ensure that corridors are separated from use areas by walls constructed to limit the passage of smoke. | 1 | 2024-01-29 |
| K-0374 | Install smoke barrier doors that can resist smoke for at least 20 minutes. | 1 | 2022-10-28 |
What the citations cover
- Smoke Deficiencies 5
- Gas, Vacuum, and Electrical Systems Deficiencies 2
- Egress Deficiencies 2
| Category | Citations |
|---|---|
| Smoke Deficiencies | 5 |
| Gas, Vacuum, and Electrical Systems Deficiencies | 2 |
| Egress Deficiencies | 2 |
Every citation on file
As published by CMS, newest survey first. Descriptions are CMS’s own wording.
May 15, 2025 — 4 citations
| Tag | What the surveyor checks | Status |
|---|---|---|
| K-0344 | Have an alternate power supply for its alarm system. | Deficient, Provider has date of correction (June 20, 2025) |
| K-0353 | Inspect, test, and maintain automatic sprinkler systems. | Deficient, Provider has date of correction (June 20, 2025) |
| K-0911 | Meet requirements for the installation and maintenance of electrical systems. | Deficient, Provider has date of correction (June 20, 2025) |
| K-0918 | Have generator or other power source capable of supplying service within 10 seconds. | Deficient, Provider has date of correction (June 20, 2025) |
January 29, 2024 — 3 citations
| Tag | What the surveyor checks | Status |
|---|---|---|
| K-0291 | Install emergency lighting that can last at least 1 1/2 hours. | Deficient, Provider has date of correction (April 26, 2024) |
| K-0321 | Ensure that special areas are constructed so that walls can resist fire for one hour or have an approved fire extinguishing system. | Deficient, Provider has date of correction (April 26, 2024) |
| K-0362 | Ensure that corridors are separated from use areas by walls constructed to limit the passage of smoke. | Deficient, Provider has date of correction (April 26, 2024) |
October 28, 2022 — 2 citations
| Tag | What the surveyor checks | Status |
|---|---|---|
| K-0291 | Install emergency lighting that can last at least 1 1/2 hours. | Deficient, Provider has date of correction (November 21, 2022) |
| K-0374 | Install smoke barrier doors that can resist smoke for at least 20 minutes. | Deficient, Provider has date of correction (November 21, 2022) |