Federal nursing home survey record · CMS-certified nursing home· Not a state assisted-living licensing record
River Pointe of Trinity Healthcare and Rehabilitat
TRINITY, TX · 104 certified beds · Last Life Safety survey June 16, 2026
CMS Certification Number 675900 · first certified December 2001
Ownership
Operated by THE ENSIGN GROUP · For profit - Corporation
No change of ownership on CMS record since January 1, 2016, when the records begin.
Position within TX
5 citations — more than 28% of the 1,177 certified nursing homes in TX. Compared within TX rather than nationally because which state a facility is in explains about 30% of the variation in citation counts between facilities, while bed count explains under 1%. State survey agencies differ far more than the buildings do. How this is calculated
The latest survey found 1 citation; the earlier surveys in the window averaged 2. With 3 surveys on file this is a direction of travel, not a conclusion.
When is the next survey likely?
The window opens July 2027 — about 10 months from now. This facility’s last Life Safety survey was June 2026. Facilities in TX are typically surveyed 13–14 months after the last one (median 14), measured over 1,905 consecutive surveys in the last two years of CMS records.
A range the record supports, not a prediction of a date. State agencies vary widely — from about 11 months in Pennsylvania to three years in Maryland. How the window is measured
Get an email about River Pointe of Trinity Healthcare and Rehabilitat
One email when it happens. No account; stop it any time with one click.
Physical environment (health survey)
4 physical-environment citations on the health survey. Cited by the health surveyors under Appendix PP, not the Life Safety Code surveyor: equipment in safe operating condition, the call system, bed rails, pest control, hazards, the environment. Counted separately from the 5 Life Safety citations above. The Physical Environment Index
How that compares
Compared with the median facility in TX, and nationally. Surveyors differ markedly between states, so the TX figure is the meaningful one.
| Measure | Citations |
|---|---|
| This facility | 5 |
| Median facility in TX | 7 |
| Median facility nationally | 11 |
Survey history
| Survey date | Citations |
|---|---|
| March 20, 2024 | 1 |
| April 30, 2025 | 3 |
| June 16, 2026 | 1 |
Most-cited tags
| Tag | What the surveyor checks | Times cited | Last cited |
|---|---|---|---|
| K-0372 | Ensure smoke barriers are constructed to a 1 hour fire resistance rating. | 1 | 2024-03-20 |
| K-0353 | Inspect, test, and maintain automatic sprinkler systems. | 1 | 2026-06-16 |
| K-0321 | Ensure that special areas are constructed so that walls can resist fire for one hour or have an approved fire extinguishing system. | 1 | 2025-04-30 |
| K-0712 | Have simulated fire drills held at unexpected times. | 1 | 2025-04-30 |
| K-0511 | Have properly installed electrical wiring and gas equipment. | 1 | 2025-04-30 |
What the citations cover
- Smoke Deficiencies 3
- Miscellaneous Deficiencies 1
- Services Deficiencies 1
| Category | Citations |
|---|---|
| Smoke Deficiencies | 3 |
| Miscellaneous Deficiencies | 1 |
| Services Deficiencies | 1 |
Every citation on file
As published by CMS, newest survey first. Descriptions are CMS’s own wording.
June 16, 2026 — 1 citation
| Tag | What the surveyor checks | Status |
|---|---|---|
| K-0353 | Inspect, test, and maintain automatic sprinkler systems. | Deficient, Provider has date of correction (June 22, 2026) |
April 30, 2025 — 3 citations
| Tag | What the surveyor checks | Status |
|---|---|---|
| K-0321 | Ensure that special areas are constructed so that walls can resist fire for one hour or have an approved fire extinguishing system. | Deficient, Provider has date of correction (May 15, 2025) |
| K-0511 | Have properly installed electrical wiring and gas equipment. | Deficient, Provider has date of correction (May 15, 2025) |
| K-0712 | Have simulated fire drills held at unexpected times. | Deficient, Provider has date of correction (May 15, 2025) |
March 20, 2024 — 1 citation
| Tag | What the surveyor checks | Status |
|---|---|---|
| K-0372 | Ensure smoke barriers are constructed to a 1 hour fire resistance rating. | Deficient, Provider has date of correction (April 3, 2024) |
Reflects the CMS posting of August 1, 2026. Surveys conducted in the last few months may not appear yet.