Federal nursing home survey record · CMS-certified nursing home· Not a state assisted-living licensing record

Columbus Health and Rehab

Columbus, WI · 50 certified beds · Last Life Safety survey May 21, 2026

CMS Certification Number 525445 · first certified November 1989

Ownership

Operated by MISSION HEALTH COMMUNITIES · For profit - Corporation

No change of ownership on CMS record since January 1, 2016, when the records begin.

19
Citations on file
Rolling three-year window
3
Life Safety surveys
In the same window
5
Tags cited more than once
Across separate surveys
8
Inspection & testing records
Of the citations on file

Position within WI

19 citations — more than 54% of the 323 certified nursing homes in WI. Compared within WI rather than nationally because which state a facility is in explains about 30% of the variation in citation counts between facilities, while bed count explains under 1%. State survey agencies differ far more than the buildings do. How this is calculated

Improvingfewer citations at the latest survey than at its earlier surveys in the window.

The latest survey found 3 citations; the earlier surveys in the window averaged 8. With 3 surveys on file this is a direction of travel, not a conclusion.

When is the next survey likely?

The window opens July 2027 — about 9 months from now. This facility’s last Life Safety survey was May 2026. Facilities in WI are typically surveyed 13–15 months after the last one (median 14), measured over 516 consecutive surveys in the last two years of CMS records.

A range the record supports, not a prediction of a date. State agencies vary widely — from about 11 months in Pennsylvania to three years in Maryland. How the window is measured

Get an email about Columbus Health and Rehab

One email when it happens. No account; stop it any time with one click.

Which alerts

2 inspection-and-testing tags have been cited here at more than one survey. Nationally, that pattern is common: about three quarters of cited facilities have at least one repeated tag, and half of the facilities ever cited for sprinkler inspection and testing are cited for it again. A repeat is usually a recordkeeping gap rather than a new hazard.

Physical environment (health survey)

2 physical-environment citations on the health survey. Cited by the health surveyors under Appendix PP, not the Life Safety Code surveyor: equipment in safe operating condition, the call system, bed rails, pest control, hazards, the environment. Counted separately from the 19 Life Safety citations above. The Physical Environment Index

  • F-0689 Ensure that a nursing home area is free from accident hazards and provides adequate supervision to prevent accidents.
  • F-0880 Provide and implement an infection prevention and control program.

How that compares

Citations on file over three years

Compared with the median facility in WI, and nationally. Surveyors differ markedly between states, so the WI figure is the meaningful one.

This facility19WI median17National median11
Citations on file over three years, compared
MeasureCitations
This facility19
Median facility in WI17
Median facility nationally11

Survey history

Citations at each Life Safety survey
72024-0392025-0332026-05
Citations at each Life Safety survey
Survey dateCitations
March 7, 20247
March 12, 20259
May 21, 20263

Most-cited tags

Most-cited tags at this facility
K-03212K-03532K-03512K-03722K-09202K-09111K-07121K-09121
Most-cited tags at this facility
TagWhat the surveyor checksTimes citedLast cited
K-0321Ensure that special areas are constructed so that walls can resist fire for one hour or have an approved fire extinguishing system.22025-03-12
K-0353Inspect, test, and maintain automatic sprinkler systems.22025-03-12
K-0351Install an approved automatic sprinkler system.22026-05-21
K-0372Ensure smoke barriers are constructed to a 1 hour fire resistance rating.22025-03-12
K-0920Ensure proper usage of power strips and extension cords.22026-05-21
K-0911Meet requirements for the installation and maintenance of electrical systems.12024-03-07
K-0712Have simulated fire drills held at unexpected times.12024-03-07
K-0912Have power receptacles that are properly grounded.12026-05-21

What the citations cover

Citations by CMS category
  • Smoke Deficiencies 10
  • Gas, Vacuum, and Electrical Systems Deficiencies 5
  • Miscellaneous Deficiencies 2
  • Egress Deficiencies 1
  • Other 1
Citations by CMS category
CategoryCitations
Smoke Deficiencies10
Gas, Vacuum, and Electrical Systems Deficiencies5
Miscellaneous Deficiencies2
Egress Deficiencies1
Services Deficiencies1

Every citation on file

As published by CMS, newest survey first. Descriptions are CMS’s own wording.

May 21, 2026 — 3 citations

Citations issued on May 21, 2026
TagWhat the surveyor checksStatus
K-0351Install an approved automatic sprinkler system.Deficient, Provider has date of correction (June 15, 2026)
K-0912Have power receptacles that are properly grounded.Deficient, Provider has date of correction (June 15, 2026)
K-0920Ensure proper usage of power strips and extension cords.Deficient, Provider has date of correction (June 15, 2026)

March 12, 2025 — 9 citations

Citations issued on March 12, 2025
TagWhat the surveyor checksStatus
K-0211Keep aisles, corridors, and exits free of obstruction in case of emergency.Deficient, Provider has date of correction (April 2, 2025)
K-0321Ensure that special areas are constructed so that walls can resist fire for one hour or have an approved fire extinguishing system.Deficient, Provider has date of correction (April 2, 2025)
K-0331Construct fire resistant interior walls.Deficient, Provider has date of correction (April 2, 2025)
K-0351Install an approved automatic sprinkler system.Deficient, Provider has date of correction (April 2, 2025)
K-0353Inspect, test, and maintain automatic sprinkler systems.Deficient, Provider has date of correction (April 2, 2025)
K-0372Ensure smoke barriers are constructed to a 1 hour fire resistance rating.Deficient, Provider has date of correction (April 2, 2025)
K-0521Ensure heating and ventilation systems that have been properly installed according to the manufacturer's instructions.Deficient, Provider has date of correction (April 2, 2025)
K-0920Ensure proper usage of power strips and extension cords.Deficient, Provider has date of correction (April 2, 2025)
K-0923Have proper medical gas storage and administration areas.Deficient, Provider has date of correction (April 2, 2025)

March 7, 2024 — 7 citations

Citations issued on March 7, 2024
TagWhat the surveyor checksStatus
K-0321Ensure that special areas are constructed so that walls can resist fire for one hour or have an approved fire extinguishing system.Deficient, Provider has date of correction (April 5, 2024)
K-0353Inspect, test, and maintain automatic sprinkler systems.Deficient, Provider has date of correction (April 5, 2024)
K-0363Install corridor and hallway doors that block smoke.Deficient, Provider has date of correction (April 5, 2024)
K-0372Ensure smoke barriers are constructed to a 1 hour fire resistance rating.Deficient, Provider has date of correction (April 5, 2024)
K-0711Provide a written emergency evacuation plan.Deficient, Provider has date of correction (April 5, 2024)
K-0712Have simulated fire drills held at unexpected times.Deficient, Provider has date of correction (April 5, 2024)
K-0911Meet requirements for the installation and maintenance of electrical systems.Deficient, Provider has date of correction (April 5, 2024)

Reflects the CMS posting of August 1, 2026. Surveys conducted in the last few months may not appear yet.